Dewey Jordan, Inc. v. Maryland-National Capital Park & Planning Commission

265 A.2d 892, 258 Md. 490, 1970 Md. LEXIS 1023
CourtCourt of Appeals of Maryland
DecidedJune 9, 1970
DocketNo. 393
StatusPublished
Cited by4 cases

This text of 265 A.2d 892 (Dewey Jordan, Inc. v. Maryland-National Capital Park & Planning Commission) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dewey Jordan, Inc. v. Maryland-National Capital Park & Planning Commission, 265 A.2d 892, 258 Md. 490, 1970 Md. LEXIS 1023 (Md. 1970).

Opinion

Finan, J.,

delivered the opinion of the Court.

This is an action at law for breach of contract whereby the appellant, Dewey Jordan, Inc., contractor, seeks to recover $36,448 from the Maryland-National Park and Planning Commission, contracting authority, a public body corporate. The subject matter of the contract was the construction of an earthen dam on Rock Creek, Montgomery County. The contract price was $374,960 of which 94.6% was furnished by the United States Government through the Soil Conservation Service of the Department of Agriculture. The contracting authority initiated the project as a part of its park system, for the purpose of providing both recreational facilities and flood control. All engineering design and studies were performed by the Soil Conservation Service with final approval by the contracting authority. Contract documents were prepared with the assistance of the Soil Conservation Service on its forms. As part of the invitation to bid, the contracting authority gave the contractor a set of plans and specifications.

The contract was executed on November 29, 1965, and provided for completion of the dam within 252 days after receipt of notice to proceed. Among the provisions of the “Construction Specifications,” sub-title “Rock Fill,” were the following pertinent sections:

“§ 6.2. Materials
6.2.1 The rock shall be sound, durable and of suitable quality to assure performance in the cli[492]*492mate in which it is used. The rock shall be obtained from required excavations or other approved sources. This material shall be well graded with maximum dimension of thirty-six (36) inches and enough fines to fill the voids.”

From the record it appears to be an undisputed fact that the plans upon which the contractor bid the job and initiated the work provided that the “Down Stream Rock Fill” material was to be taken from designated borrow pits located near the job site and on the Park lands. Prior to the invitation for bids, the contracting authority conducted a series of test borings in these areas to determine suitability of the material and the data thus obtained was included in the plans.

Notice to proceed with the contract was received by the contractor on December 8,1965, and work commenced two days thereafter. Work continued without interruption until October 17, 1966, when the contracting authority discovered that the “Downstream Rock Fill” material was too fine. Through a representative of the Soil Conservation Service on the job, a Mr. Jon De Groot, a “Suspend Work Order” was issued “that tests may be made on ‘Downstream Rock Fill’ to determine effectiveness of drainage system.” As a result of the order, construction operations were shut down and the contractor’s men and equipment stood idle until November 14, 1966. On this last date the contracting authority issued an order to resume work stating, inter alia, “Evaluation of Drainage System Complete. Corrective measures will not require removal of completed work.” The corrective measures referred to were embodied in “Contract Modification No. 5” issued pursuant to the “Changes” article of the contract and consisted of the addition of a “toe drain” to the original dam structure.

At this juncture, for an understanding of the issue before this Court, it will be helpful to refer to pertinent provisions of the “Changes” article and “Suspension of Work” article of the contract:

[493]*493“3. Changes:
The Contracting Officer [chief engineer of the contracting authority] may, at any time by written order, and without notice to the sureties make changes in the drawings and/or specifications of this contract if within the general scope. If such changes cause an increase or decrease in the Contractor’s cost of, or time required for, performance of the contract, an equitable adjustment shall be made and the contract modified in writing accordingly. * * *”
26. Suspension of Work:
(a) The Contracting Officer may order suspension of the work in whole or in part for such time as he deems necessary due to weather or such other conditions as he considers unfavorable for the satisfactory prosecution of the work. (Emphasis supplied.)
(c) The Contracting Officer may order suspension of the work in whole or in part for such times as he deems necessary because of the failure of the Contractor to comply with any of the provisions of this contract * * *.
(d) When the Contracting Officer orders any suspension of the work under the provisions of this clause, the Contractor shall not be entitled to any costs or damages resulting from delays due to such suspension of the work.

The contractor claims that the one month shut down of the job, due to no fault of its own, cost it $36,448 the amount for which suit was brought. In its amended declaration the contractor sought to establish its right to recovery on three grounds, (1) in assumpsit for work done and materials provided; (2) that under the “Changes” article, the contracting authority was required to pay the contractor its costs during the shutdown and in failing [494]*494to do so, breached the contract; and (3) on the theory that there was an implied warranty that the plans and specifications of the contracting authority were suitable for the construction of the dam and that this warranty was breached when the contracting authority shut down the job to investigate the “Downstream Rock Fill” material and thereafter modified the contract to include installation of the “toe drain.”

The matter was tried before the lower court without a jury which, after hearing much testimony and argument from counsel, rendered judgment in favor of the defendant-contracting authority. Judge Shearin, in a well reasoned opinion, thought that the case was controlled by the interpretation given the “Changes” article of the contract by the Court in United States v. Rice, 317 U. S. 61 (1942), a case which we will later discuss. However, we do not believe Rice to be apposite and for the reasons we shall proceed to relate, we reverse the judgment given below.

This appeal presents us with two questions:

1. Does either the “Suspension of Work” article or the “Changes” article of the contract dispose of the issues in this case?

2. Did the lower court err in not finding that there was an actionable breach of an implied warranty that the plans and specifications were adequate and sufficient for the purposes intended?

The appellee relying on United States v. Rice, 317 U. S. 61 (1942), argues that it should prevail as § 26(a) of the “Suspension of Work” article of the contract gives it the right to request a reasonable work suspension, and that the suspension of work in the instant case was a reasonable one for a reasonable purpose, namely, “to investigate and test certain suspicious circumstances that arose during the construction of the dam.” Accordingly, the contractor had to bear the standby costs incident to such stoppage. Furthermore, appellee contends that under the “Changes” article compensation may properly [495]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Balfour Beatty Infrastructure, Inc. v. Rummel Klepper & Kahl, LLP
130 A.3d 1024 (Court of Special Appeals of Maryland, 2016)
Gladwynne Const. v. Mayor and City Council of Baltimore
807 A.2d 1141 (Court of Special Appeals of Maryland, 2002)
New Pueblo Constructors, Inc. v. State
696 P.2d 185 (Arizona Supreme Court, 1985)
Dewey Jordan v. MD.-NAT'L CAP. P. & P.
265 A.2d 892 (Court of Appeals of Maryland, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
265 A.2d 892, 258 Md. 490, 1970 Md. LEXIS 1023, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dewey-jordan-inc-v-maryland-national-capital-park-planning-commission-md-1970.