Dillon Properties, Inc. v. Minmar Builders, Inc.

262 A.2d 740, 257 Md. 274, 1970 Md. LEXIS 1308
CourtCourt of Appeals of Maryland
DecidedMarch 9, 1970
Docket[No. 190, September Term, 1969.]
StatusPublished
Cited by3 cases

This text of 262 A.2d 740 (Dillon Properties, Inc. v. Minmar Builders, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dillon Properties, Inc. v. Minmar Builders, Inc., 262 A.2d 740, 257 Md. 274, 1970 Md. LEXIS 1308 (Md. 1970).

Opinion

FINAN, J.,

delivered the opinion of the Court.

Plaintiff-appellee, Minmar Builders, Inc., prime contractor (contractor), brought suit against the defendant-appellant (owner) Dillon Properties, Inc., to recover the unpaid balance of its contract price. The agreement dated June 14, 1965, was an American Institute of Architects Standard Form and contained specifications for the construction of a trucking terminal with an asphalt parking lot on three sides of the terminal building at a total price of $113,427. The undisputed unpaid contract balance was $24,124.50. The owner counterclaimed for $14,175, representing the cost of repairing the paved area approximately two and a half years after the work was performed by the contractor. The court, sitting without a jury, after six days of trial during which it heard testimony from sixteen witnesses, entered judgment for the contractor in the amount of $21,087 after first making a deduction in the amount of $3,037.50 which was the amount it allowed on the owner’s counterclaim.

The dispute concerned the paving portion of the contract which called for a 6 inch gravel base topped by 2 inches of bituminous concrete. There was testimony that the laying of the base course was almost completed when *276 on April 8, 1966, Mr. Sprinkle, project manager for the owner’s architect, visited the project site at about 3:00 P.M. for the second time that day and expressed his opinion that more work was necessary to properly prepare the subbase. He so informed the subcontractor’s foreman. After Mr. Sprinkle left, the paving of the lot was completed. The paving contractor visited the job site the following morning and observed no faulty work.

On Monday, April 11, 1966, Mr. Sprinkle noticed some depressions on the lot appearing like tire tracks from a ten-wheeler, some puddles and what is known in the trade as “cold spots.” On his next visit to the job site on April 20, he noticed that a truck had driven over the pavement and disturbed it extensively. He did not know whose truck it was. The only truck of the contractor’s which he observed was a pickup truck, whereas the construction of the gasoline pump area and the installation of the tanks in the rear of the building, which were not the responsibility of the contractor, would have involved the use of a crane with a bucket, together with concrete mixing trucks.

During the first week of August, 1966, the Jacobs Transfer Company commenced occupancy of the terminal and has continued use of it since that date. During the winter and spring of. 1967-1968 an additional three truck bays were constructed on the rear of the existing terminal building. During the months following the completion of the paving work in April of 1966, numerous cracks, referred to in the industry as “alligatoring,” ap■peared. There was testimony that this could be caused by “cold spots” which occurred in laying the asphalt, by poor compaction of the subgrade and poor drainage. From April, 1966, and extending almost to the date of the trial in the court below, there occurred between the parties an exchange of numerous and varied theories as to the cause of the damage and attendant liabilities. The contractor sought to place the blame on the owner because of its failure to retain in the contract a provision in the original design for construction calling for a pe *277 rimeter of drainage tile, the lack of which drainage system the contractor claims contributed to the resulting damage in the parking area. The contractor further contended that the architect ignored its calling to his attention a design deficiency regarding the thickness of the asphalt and the subbase. The owner countered by alleging that the work was performed in a negligent manner and left in a state of incompletion. In the late fall of 1966, the contractor offered to repair the lot to the architect’s satisfaction if the owner would turn over to it a payment then due in the amount of $9,271.80, which sum had been certified for payment by the architect on November 8, 1966. However, the owner rejected this in its entirety, insisting that the lot be completely repaired before any more funds were paid to the contractor. At this time the contractor also was willing for the owner to retain more than $15,000 still due, pending the satisfactory completion of the work.

In January of 1966, the contractor obtained an estimate from the Alaska Paving Company on the cost of the necessary corrective work. This estimate was $3,-037.50, exclusive of the area for the gasoline pump island which was the owner’s responsibility. However, the parties could not get together on this proposition. Thereafter, in December of 1967, the contractor filed this action. In October of 1968, the owner, almost two years after the contractor offered to repair the lot, undertook the repairs that are now the subject oí the $14,175 counterclaim. During this two year period the lot was in continuous use. The cost of repairs charged as a counterclaim by the owner does not take into consideration any damage caused by the owner in the installation and later relocation of the gasoline pumps; the damage caused by the movement of construction equipment across the lot for the seven or eight month period that the construction was in progress on the three additional truck bays; or the damages caused by normal wear and tear during the more than two years the lot was in constant use by the trucking company tenant.

*278 The main thrust of the appellant’s argument is that the judgment should be reversed and remanded for a new trial because it is based on the misstatement of facts by the court; that the court failed to analyze the evidence; and that it made a number of findings of mixed questions of law and fact in which it misapplied the law. However, as we interpret the brief and argument of the appellant, what it in essence asks this Court to do, is to substitute its evaluation and judgment of the facts for that of the lower court. This, even the appellant recognizes, we cannot do under Maryland Rule 886 a, unless the trial judge was clearly erroneous. Grain Dealers Mut. Ins. Co. v. Van Buskirk, 241 Md. 58, 70, 215 A. 2d 467 (1965). Cf. Greenberg v. Dunn, 245 Md. 651, 655, 227 A. 2d 242 (1967). Furthermore, the same rule requires that “due regard will be given to the opportunity of the lower court to judge the credibility of the witnesses.” Johnson v. State, 238 Md. 643, 644, 210 A. 2d 399 (1965). After reviewing some 409 pages of the record extract and numerous exhibits, we do not think that the lower court was clearly erroneous in its analysis of the facts, nor do we think it wrong in its application of the law to the facts.

The basic failure which the owner found with the work performed by the contractor relates to the subbase of the asphalt paving, which it declares was improperly prepared. It is noted that Article 13 of the contract provides, that “if any work should be covered up without approval or consent of the architect, it must, if required by the architect, be uncovered for examination at the contractor’s expense.” Yet, the evidence is devoid of any demand by the architect at the time the paving was completed or within a reasonable time thereafter, that the contractor uncover any of the asphalt pavement to enable the architect, on behalf of the owner, to determine whether specifications had been followed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State of Maryland Deposit Insurance Fund Corp. v. Billman
580 A.2d 1044 (Court of Appeals of Maryland, 1990)
Dewey Jordan v. MD.-NAT'L CAP. P. & P.
265 A.2d 892 (Court of Appeals of Maryland, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
262 A.2d 740, 257 Md. 274, 1970 Md. LEXIS 1308, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dillon-properties-inc-v-minmar-builders-inc-md-1970.