Gladwynne Const. v. Mayor and City Council of Baltimore

807 A.2d 1141, 147 Md. App. 149, 2002 Md. App. LEXIS 168, 2002 WL 31115196
CourtCourt of Special Appeals of Maryland
DecidedSeptember 25, 2002
Docket2653 Sept. Term, 2000
StatusPublished
Cited by5 cases

This text of 807 A.2d 1141 (Gladwynne Const. v. Mayor and City Council of Baltimore) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gladwynne Const. v. Mayor and City Council of Baltimore, 807 A.2d 1141, 147 Md. App. 149, 2002 Md. App. LEXIS 168, 2002 WL 31115196 (Md. Ct. App. 2002).

Opinion

HOLLANDER, Judge.

This case arises from a construction contract (the “Contract”) between Gladwynne Construction Company (“Gladwynne”), appellant and cross-appellee, and the Mayor *155 and City Council of Baltimore (the “City”), appellee and cross-appellant. The Contract had a “base bid price” of $497,000, and involved the renovation of several classrooms and science laboratories (the “Project”) at Polytechnic High School No. 403 (the “School” or “Poly”). For reasons that are in dispute, the completion of the work was delayed by almost a year.

On October 3, 1999, after the City failed to make full payment under the Contract, appellant filed suit in the Circuit Court for Baltimore City, seeking to recover damages of $244,638.14 for breach of contract, unjust enrichment, and quantum meruit. Appellant’s claim for damages included extended field costs and home office overhead costs occasioned by the delay in completion of the Contract. The City counterclaimed, seeking $97,500 in liquidated damages because of the delay. Pursuant to a partial settlement between the parties concerning the direct costs for the City’s change orders, the City paid appellant $104,422 on December 15, 2000. Thereafter, over the course of several days in December, the remaining issues were tried to the court.

When the trial concluded, the court indicated that it intended to award appellant the Contract retainage, in the amount of $25,753, as well as $66,083.55 for extended field costs due to the delay, conditioned on appellant’s successful completion by January 16, 2001, of a punch list prepared by Poly’s principal. At a subsequent hearing, the court concluded that appellant had failed to complete the punch list, and therefore it declined to award the Contract retainage. Instead, the court awarded appellant $66,083.55, for extended field costs for a period of 195 days, rather than the 309 days that appellant claimed. Moreover, the court declined to award any home office overhead expenses occasioned by the delay.

On appeal, Gladwynne presents several issues for our review, which we have reordered and rephrased:

I. Did the court err in failing to award any damages to Gladwynne for extended home office overhead?
*156 II. Did the court err in failing to award damages to appellants for extended field costs through completion of the Project in January 1999?
III. Did the court err in deducting the Contract retainage from Gladwynne’s award of damages?

In its cross-appeal, appellee presents two questions, which we have also reworded:

I. Did the trial judge err in awarding any damages to appellant?
II. Did appellant fail to comply with various provisions of the Contract?

For the reasons that follow, we shall affirm in part and vacate in part and remand for further proceedings.

FACTUAL SUMMARY 1

Gladwynne, a general contractor, submitted a bid to the City in March 1997, to do the renovation of several science laboratories and classrooms at Poly. The City awarded the contract to Gladwynne, and the parties entered into the Contract on or about August 1,1997. The work was to commence on September 2, 1997, with completion to occur within 180 calendar days, i.e., February 28, 1998. As it turned out, construction was not completed until about 489 days after it began, and some 300 days after the original completion date. The parties stipulated that the Contract was substantially completed on September 11, 1998. Nevertheless, change orders continued until December 1998, and the work was not fully completed until on or about January 31, 1999. Neither the classrooms nor the laboratories that were subject to renovation were useable or used in the fall of 1998.

*157 Pursuant to the Contract and the Project drawings, Gladwynne was to replace the utility lines located in a hollow crawlspace under a concrete slab in Room 29 of the School. The lines were to service Room 29 and science laboratories two floors above. Appellant was also obligated to install new vinyl floors, lab casework, 2 plumbing, fixtures, lights, and heating and cooling equipment. Based on the Project drawings, appellant planned to replace the utility lines by drilling two four-inch holes into the concrete crawlspace and then working inside the crawlspace to insert new utility lines. Once the new utilities were in place, the four inch holes were to be patched.

Appellant was advised to begin performance of the Contract on September 2, 1997. However, neither appellant nor the City was ever able to locate the crawlspace. While Gladwynne searched for the crawlspace, it was unable to perform any of the work with regard to replacement of the utilities. Eventually, appellant had to alter its method for replacement of the utility lines. On October 27, 1998, Scott Sider, Construction Contract Administrator, wrote to Frederick Petrella, Jr., an employee in the Construction Division of the Department of Public Works, stating, in part:

We have reviewed the Contractor’s Change Order Proposal for changing the plumbing in Rooms 29, 29A, and 29B from being in a crawl space [sic] (as indicated on the Drawings) to being buried in excavated trenches. This change order is required since the crawl space does not exist under those classrooms.

Appellant planned, instead, to break up the concrete slab in Room 29, dig a trench to hold new utilities, and then install them in poured concrete. The trenching work occurred in Rooms 29A, B, and C at Poly, and commenced on November 13, 1997.

*158 According to appellant, when it undertook to perform the trenching work, further delays ensued. For example, while appellant was digging the trenches in the floor to run the utilities in Room 29, it severed existing cable lines submerged in the concrete, which had to be repaired. The tile flooring was also damaged from the trenching and had to be removed. When the existing tiles were removed, Gladwynne found asbestos, which also had to be removed. That process was not completed until March 1, 1998. By that date, Gladwynne had progressed to the point where it should have been on November 1, 1997. According to Gladwynne, it “was already 170 days into a 180 day contract.”

As a consequence of the change in design, Gladwynne was unable to install the plastic utility pipes that it had already ordered and paid for, which were stored on site. Instead, appellant ordered a more durable utility pipe, known as Duri-ron, but had to wait until January 1998 for its arrival. In February 1998, after the trenching work was completed, and the new Duriron lines were installed, the trenches were filled with concrete. Rather than patching the four inch holes, as originally anticipated, Gladwynne had to smooth the surface of the entire floor of Room 29 to prepare it for the new vinyl floor.

In addition, the casework could not be installed until after the new floors were installed. In order to install fixtures, the casework had to be finished.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Damien F.
958 A.2d 402 (Court of Special Appeals of Maryland, 2008)
Brendsel v. WINCHESTER CONSTRUCTION CO., INC.
898 A.2d 472 (Court of Appeals of Maryland, 2006)
Brendsel v. Winchester Construction Co.
875 A.2d 789 (Court of Special Appeals of Maryland, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
807 A.2d 1141, 147 Md. App. 149, 2002 Md. App. LEXIS 168, 2002 WL 31115196, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gladwynne-const-v-mayor-and-city-council-of-baltimore-mdctspecapp-2002.