Joseph F. Trionfo & Sons, Inc. v. Ernest B. Larosa & Sons, Inc.

381 A.2d 727, 38 Md. App. 598, 1978 Md. App. LEXIS 332
CourtCourt of Special Appeals of Maryland
DecidedJanuary 18, 1978
Docket548, September Term, 1977
StatusPublished
Cited by17 cases

This text of 381 A.2d 727 (Joseph F. Trionfo & Sons, Inc. v. Ernest B. Larosa & Sons, Inc.) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Joseph F. Trionfo & Sons, Inc. v. Ernest B. Larosa & Sons, Inc., 381 A.2d 727, 38 Md. App. 598, 1978 Md. App. LEXIS 332 (Md. Ct. App. 1978).

Opinion

Moore, J.,

delivered the opinion of the Court.

The ever-expanding body of law with respect to “arbitration” is involved in this appeal which arises out of a controversy between a general contractor on a school construction project (the appellant) and the excavation and site-work subcontractor (the appellee). The narrow question presented is whether an agreement to arbitrate existed, as claimed by the general contractor, against whom the subcontractor recovered a judgment in excess of $200,000 after a thirteen-day jury trial. The Uniform Arbitration Act, *600 Md. Cts. & Jud. Proc. Code Ann. §§ 3-201 et seq. (1974), adopted in 1965 in Maryland, does not address the substantive requirements for an agreement to arbitrate the subject matter of a dispute. Flood v. Country Mutual Insurance Co., 242 N.E.2d 149 (111. 1968). See Bel Pre Medical Center, Inc. v. Frederick Contractors, Inc., 21 Md. App. 307, 320 A. 2d 558 (1974) , rev’d on other grounds, 274 Md. 307, 334 A. 2d 526 (1975) . I

The construction of the New North Harford Middle School on Route 165 in Harford County forms the backdrop for this dispute. On January 21,1974, appellant, Joseph F. Trionfo & Sons, Inc., a general contractor, entered into an agreement with the Board of Education of Harford County for the building of the school. 1 The contract specifications included certain “Conditions of Contract.” Article 2 of the Conditions dealt with the architect, and contained a subsection entitled “Administration of the Contract.” The relevant portions of this subsection provided as follows:

“The Architect will make periodic visits to the site to determine in general if the Work is proceeding in accordance with the Contract Documents. On the basis of his on-site observations as an architect, he will endeavor to guard the Owner against defects and deficiencies in the Work of the Contractor. The Architect will not be required to make exhaustive or continuous on-site inspections to check the quality or quantity of the Work____
“Based on such observations and the Contractor’s Applications for Payment, the Architect will determine the amounts owing to the Contractor and will issue Certificates for Payment in such amounts, as provided.
*601 “The Architect will be, in the first instance, the interpreter of the requirements of the Contract Documents. The Architect will, within a reasonable time, render such interpretations as he may deem necessary for the proper execution or progress of the Work.
“Claims, disputes and other matters in question between the Contractor and the Owner relating to the execution or progress of the Work or the interpretation of the Contract Documents shall be referred to the Architect for decision. [2]
“All interpretations and decisions of the Architect shall be consistent with the intent of the Contract Documents. In his capacity as interpreter, he will exercise his best efforts to insure faithful performance by both the Owner and the Contractor and will not show partiality to either.
“The Architect’s decision in matters relating to artistic effect will be final if consistent with the intent of the Contract Documents.” (Emphasis added.)

On the same date, appellant entered into a subcontract with appellee, Ernest B. LaRosa & Sons, Inc., whereby, for the sum of $203,000, appellee was to “supply all labor, materiel and equipment” to complete the work under the main contract involving excavation, paving, landscaping and fencing. The agreement was made on a printed form headed by appellant’s full corporate name. The second paragraph of the subcontract, after a description of the subcontractor’s responsibilities, contained the following boilerplate language, incorporating by reference certain sections of the agreement between the Board of Education as owner and the appellant as general contractor:

“. . . all as provided for in the contract between Contractor and Owner as aforesaid, which said contract, plans, specifications and general conditions *602 are hereby made a part hereof so far as the same are applicable to the work to be done hereunder, as fully as though the same were herein set out at length, and Sub-Contractor hereby assumes and agrees in carrying out this agreement to comply with all the stipulations and conditions of said contract, and the plans and specifications and general conditions accompanying the same or any parts thereof, that are applicable to the work to be done hereunder or that may be construed as applicable thereto by the architect or engineer in charge of said work; it being the intent hereof that in respect to the work covered hereunder Sub-Contractor shall be under the same obligations to Contractor under this contract as Contractor is to Owner under the terms of the general contract aforesaid, the Contractor shall be entitled to all the rights, privileges and remedies as against Sub-Contractor, which Owner may have or be construed to have under the general contract against Contractor, and that any direction or order of the architect or engineer aforesaid which may be binding upon or given to Contractor shall ipso facto be construed as binding upon or given to Sub-Contractor as soon as Sub-Contractor receives notice thereof.” (Emphasis added.)

An addendum to the form contract between appellant and appellee further provided, in pertinent part:

“If sub-contractor encounters rock, boulders, or buried logs, trees, stumps, or any sub-surface conditions the contract price shall be increased [$15.00] per cubic yard, and if blasting is required the cost thereof will also be added to the contract price.” 3

On March 26,1975, appellee brought an action at law in the *603 Circuit Court for Harford County against appellant, 4 alleging that in the performance of the subcontract, appellee did encounter and excavate rock and boulders and that extra compensation was due, under the terms of the subcontract, which appellant had failed and refused to pay. Appellant filed as its first pleading a “Motion Raising Preliminary Objection or in the Alternative to Order Arbitration and Stay These Proceedings.” A claim was therein made that the main contract designated the architect “as the arbitrator of all matters involving claims and disputes concerning amounts owing and interpretations of the Contract Documents,” and that such provision was effectively incorporated by reference into the subcontract. 5

Judge Harry E. Dyer, Jr. presided at the hearing on the motion, and denied appellant’s request that arbitration be ordered, holding essentially that:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Park Plus v. Palisades of Towson
272 A.3d 309 (Court of Appeals of Maryland, 2022)
American Bank Holdings, Inc. v. Kavanagh
82 A.3d 867 (Court of Appeals of Maryland, 2013)
Kuhn Construction, Inc. v. Diamond State Port Corp.
990 A.2d 393 (Supreme Court of Delaware, 2010)
Essex Corp. v. Susan Katharine Tate Burrowbridge, LLC
940 A.2d 199 (Court of Special Appeals of Maryland, 2008)
Baltimore Contractors, LLC v. Mayor & City Council of Baltimore
869 A.2d 396 (Court of Special Appeals of Maryland, 2005)
Nowak v. NAHB RESEARCH CENTER, INC.
848 A.2d 705 (Court of Special Appeals of Maryland, 2004)
Montgomery County v. Fraternal Order of Police Montgomery County Lodge 35, Inc.
810 A.2d 519 (Court of Special Appeals of Maryland, 2002)
Gladwynne Const. v. Mayor and City Council of Baltimore
807 A.2d 1141 (Court of Special Appeals of Maryland, 2002)
NRT Mid-Atlantic, Inc. v. Innovative Properties, Inc.
797 A.2d 824 (Court of Special Appeals of Maryland, 2002)
Bloch v. Bloch
693 A.2d 364 (Court of Special Appeals of Maryland, 1997)
Society of American Foresters v. Renewable Natural Resources Foundation
689 A.2d 662 (Court of Special Appeals of Maryland, 1997)
Regina Construction Corp. v. Envirmech Contracting Corp.
565 A.2d 693 (Court of Special Appeals of Maryland, 1989)
Gauntt Construction Co. v. Delaware River & Bay Authority
575 A.2d 70 (New Jersey Superior Court App Division, 1989)
Gauntt Const. v. RIVER & BAY AUTH.
575 A.2d 70 (New Jersey Superior Court App Division, 1989)
Grane v. Grane
493 N.E.2d 1112 (Appellate Court of Illinois, 1986)
Mayor of Baltimore v. Ohio Casualty Insurance
438 A.2d 933 (Court of Special Appeals of Maryland, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
381 A.2d 727, 38 Md. App. 598, 1978 Md. App. LEXIS 332, Counsel Stack Legal Research, https://law.counselstack.com/opinion/joseph-f-trionfo-sons-inc-v-ernest-b-larosa-sons-inc-mdctspecapp-1978.