Mayor of Baltimore v. M. A. Talbott & Co.

87 A. 941, 120 Md. 354, 1913 Md. LEXIS 140
CourtCourt of Appeals of Maryland
DecidedApril 10, 1913
StatusPublished
Cited by14 cases

This text of 87 A. 941 (Mayor of Baltimore v. M. A. Talbott & Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mayor of Baltimore v. M. A. Talbott & Co., 87 A. 941, 120 Md. 354, 1913 Md. LEXIS 140 (Md. 1913).

Opinion

Boyd, C. J.,

delivered the opinion of thé Court.

The appellees sued the appellant upon seven contracts made between them for the eonstructon of sewers in the City of Baltimore, and all errors in pleading were waived. The contracts sued on required the performance of work and the furnishing of materials of a total value of over a million dollars, but the appellees had been paid the most of the contract prices, and they only recovered a verdict for $15,183.88, which was a little less than three-fourths of the claims made by them. There are three bills of exception in the record— the first two presenting' rulings as to the admissibility of evidence, and the third embracing the rulings on the prayers.

First — We will consider the first bill of exceptions and the first prayer of the plaintiff together, as they involve the construction of the contract and the question of how far the decision'of the engineer as to the paymenf of the plastering on the extrados of the arches of the sewers and on the manholes was conclusive. It was agreed by counsel that the provisions set out in the record “are the same as those contained in the other six contracts involved in this case,” and hence in discussing the case we speak of the contract, in the singular, although there were really seven.

' The contract signed by the parties recites that whereas the contract for building Section Two of the Outfall Sewer in *357 certain streets in the City of Baltimore, as shown on plans on file in the office of the Chief Engineer of the Sewerage Commission, “subject to all conditions, covenants, stipulations, terms and provisions contained in certain specifications, a copy of which is hereto attached, and in all respects made a part hereof, has recently been awarded to the contractor by the city,” etc., and whereas, one of the conditions of the said award was that a formal contract should be executed, “Flow, Therefore, This Contract Witnesseth, That the contractor doth hereby covenant and agree with the city that they will well and faithfully build said drain in accordance with each and every one of the conditions, covenants, stipulations, terms and provisions contained in said specifications * * *, and will well and faithfully comply with and perform each and every obligation imposed upon them by said specifications, or the terms of said award.” The city then covenants to pay to the contractor “when due and payable under the terms of said specifications and of said award,” the sum named, “and that it will weil and faithfully comply with and perform each and every obligation imposed upon it by said specifications or the terms of said award.”

The following provisions in the specifications are a part of the contract: Section 109. “Except when the engineer shall direct otherwise, the arch of the sewer shall he of ‘Class A’ concrete masonry, laid as elsewhere herein specified. Whenever it is advisable, in the opinion of the engineer, the arch of the sewer shall be built of reinforced concrete or brick masonry, of the qualities herein described. The ex-trados of the arch, of whatever material, shall be neatly plastered with cement mortar one-half (%) inch thick over its entire surface extending down to the springing-line on each side, the surface of the arch being thoroughly cleaned and wetted hefore-hand. This mortar shall consist of one (1) part cement, one-half (%) part lime paste, and four (4) parts clean, sharp sand. The plastering required over the extrados of the arch is to he carried forward as the masonry is laid, and immediately after the arch is completed.”

*358 “Section 124. Payment. Brick and concrete masonry will be paid for by tbe cubic yard for tbe net volume of masonry per linear foot required by the dimensions given on the plans. The length of the sewer will be determined by horizontal measurements, and deductions will be made for masonry omitted at all manholes and openings. Plastering on ex-traños of arch will not be paid for separately, but it is to be included in and covered by the price paid for masonry.”

Section 127. “The outside of all manholes shall be neatly plastered with cement mortar one-half (%) inch thick, to such point as the engineer may direct. This plastering will not be paid for separately, but it is to be included in and covered by the price paid for the masonry.”

It will be observed that the same provision is made as to the payment for the plastering on the extrados of the arches as for that on the outside of the manholes- The appellant and the appellees differ in their construction of the terms italicized. The appellant contends that by those terms the compensation of the contractors for the plastering was included in the price paid for the masonry; that they were to receive so much per cubic yard for the masonry, and in making their bid for it were supposed to include the compensation for the plastering, which they were required to do. The appellees on the other hand contend that by the proper construction of the contract they were to be paid for the plastering as if it was masonry, and that hence the measurements of the masonry should have included the half-inch called plastering. The Court below adopted the contention of the appellees both as to the construction of the contract and of the right of the Court to construe it, and hence'refused to allow the question asked the engineer, which was intended to show that he had decided that the measurement of the plastering could not be included with that of the masonry, and that no allowance could be made for it other than what was included in the payment for the masonry, and the Court also by the first prayer in effect instructed the jury to find for the appellees *359 for the amount of plastering at the price fixed for the masonry.

It is manifest that something may he said on both sides as to the proper construction of the contract. If in point of fact the appellees in their bid did not take into consideration the fact that they were required to plaster the extrados of the arches and the outside of the manholes, and did not understand that they were to include that in their bid for the masonry, then the city would virtually have that plastering done for nothing; but, on the other hand, if the estimate of the cost of the plastering was to be included in the bid for the masonry, then if it can be measured as if it was a part of the masonry, the city would have to pay twice for it. If the appellees’ theory be correct, a more simple way would have been to say: “Plastering on extrados of arch will not be paid for separately, but it is to be measured with the masonry and to be paid for at the price paid for masonry.” The appellees contend that it means that the plastering “is to be included in the masonry and covered by the price paid for the masonry,” but the appellant replies that it does not say the plastering is to be included in the measurement of the masonry, but that the payment for the plastering “is to be included in and covered by the price paid for the masonry”— that is to say, included in the price and covered by the price paid for the masonry.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

James Julian, Inc. v. State Highway Administration
492 A.2d 308 (Court of Special Appeals of Maryland, 1985)
Joseph F. Trionfo & Sons, Inc. v. Ernest B. Larosa & Sons, Inc.
381 A.2d 727 (Court of Special Appeals of Maryland, 1978)
American Structures, Inc. v. Mayor of Baltimore
364 A.2d 55 (Court of Appeals of Maryland, 1976)
Nelley v. Mayor of Baltimore
166 A.2d 234 (Court of Appeals of Maryland, 1960)
Schiavi v. Mayor of Baltimore
40 F. Supp. 184 (D. Maryland, 1941)
Pumphrey v. Pumphrey
191 A. 235 (Court of Appeals of Maryland, 1937)
Christhilf v. Mayor of Baltimore
136 A. 527 (Court of Appeals of Maryland, 1927)
Trustees of Aitz Chaim Hebrew Congregation v. Butterhoff
118 A. 658 (Court of Appeals of Maryland, 1922)
Tomlinson v. Ashland County
173 N.W. 300 (Wisconsin Supreme Court, 1919)
Mayor of Baltimore v. Poe
104 A. 360 (Court of Appeals of Maryland, 1918)
Mayor & City Council of Baltimore v. M. A. Talbott Co.
105 A. 149 (Court of Appeals of Maryland, 1918)
McEvoy v. Willard E. Harn Co.
98 A. 522 (Court of Appeals of Maryland, 1916)
Mayor of Baltimore v. Clark
97 A. 911 (Court of Appeals of Maryland, 1916)
Mayor of Baltimore v. Ault
94 A. 1044 (Court of Appeals of Maryland, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
87 A. 941, 120 Md. 354, 1913 Md. LEXIS 140, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mayor-of-baltimore-v-m-a-talbott-co-md-1913.