Mayor of Baltimore v. Poe

104 A. 360, 132 Md. 637
CourtCourt of Appeals of Maryland
DecidedJuly 10, 1918
StatusPublished
Cited by5 cases

This text of 104 A. 360 (Mayor of Baltimore v. Poe) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mayor of Baltimore v. Poe, 104 A. 360, 132 Md. 637 (Md. 1918).

Opinion

Constable, J.,

delivered the opinion of the Court.

There are cross-appeals in this case; each party appealing from the judgment rendered iu favor of the receivers of The Hoel Construction Company.

The case arose out of the contracts awarded to The Hoel Construction Company by the City of Baltimore through the Board of Awards for the construction of the Sewage P'ump1ing Station near East Falls in Baltimore City. It was proposed by the city to erect the station building by two separate contracts: one for the substructure or foundation, called Contract Ho. 3, and the other for the erection of the superstructure, called Contract Ho. 4, and invited bids for that work. The specifications for Contract Ho. 3 provided that if that contract was awarded to one bidder, and the contract -for the superstructure was awarded to another’ bidder the number of working days from the date of the commencement of the work to its completion would he limited to two hundred days, but that if the contracts for both the substructure and the superstructure were awarded to the same bidder the number of working days from the date of commencement to completion would be limited to 420 days. The same provision as to limit of time for completing the substructure and the super *640 structure was made in the specifications for Contract Ho. 4; 220 working days if different bidders and 420 days if the same bidder was awarded both contracts.

The Hoel Construction Company, being the lowest bidder for each of the two contracts, was awarded both.

Provision is made for computing what shall be working days under the terms of the contracts as follows:

“Every day except Sundays' and also except legal holidays on which no work is done, shall be considered a working day, provided that it is not unfitted either by wind, rain, snow or temperature for working out of doors.
“The length of time (expressed in days and parts of days) during which the work has been delayed by any act or omission of the Sewerage Commission shall be allowed to the contractor and excluded from such computation.”

Calvin W. Hendrick, Chief Engineer of the City, was in charge of Contract Ho. 3, or the substructure contract, and Henry Brauns, an architect, was in charge of Contract Ho. 4, or the superstructure contract. Contract Ho. 3 contained this provision: “The engineer shall determine the number of working days that the contractor is in default in completing the work to be done under this contract, and shall certify the same to the Commission in writing. * * * His determination and certificate shall be final and conclusive.” Contract Ho. 4 contains the same provision except the architect is substituted for the engineer.

Provision is also made in the contracts that for each and every working day that the engineer or architect shall certify that the contractor is in default in completing the work to be done under the specifications, the contractor shall pay to the city the sum of thirty-five dollars, and that for each day the Work may be completed before the time fixed in the contracts for such completion the contractor shall be allowed a premium of thirty-five dollars. Also the following provision:

*641 “53. The contractor shall do such extra work as may ho ordered in writing hy the architect or engineer with the authorization of the Commission. Ho claims for extra work will he considered or allowed unless said work has been so ordered by the architect or engineer, nor unless the Commission shall approve such claim for extra work and certify in writing that in its opinion such extra work was necessary for the public interest, stating in the certificate its reasons.”

And the further provision:

“14. To prevent disputes and litigations, the architect or engineer shall in all cases determine the amount or quantity, quality, acceptability and value of the work and materials which are to be paid for under this contract; shall decide all disputes, questions and doubts relating to the work and the performance thereof, and shall in all casos decide every question which may arise relative to the contract or to the obligations of tbe contractor thereunder.
“His determination and decision shall he final and conclusive upon the contractor and all whom he may employ to execute the various branches of the work, whether as sub-contractors or otherwise, and upon all parties from whom materials may be purchased, either by the contractor or by any sub-contractor. In case any question shall arise between the contractor and the city touching the contract, the estimate or certificate and decision of the architect or engineer shall he a condition precedent to the right of the contractor to receive any moneys under the contract.”

Provision was also made that the contractor would be required to comply strictly with all the requirements of the building regulations and other ordinances of the City of Baltimore. And also the following provision was contained in both contracts:

“48. The Commission reserves the right to suspend the whole or any part of the work to be done hereunder, if it shall deem it for the interest of the *642 City of Baltimore to do so, without • compensation to the contractor for such suspension, other than extending the time for completing the work as much as it may have been delayed by such suspension.”

The purpose of this building was to receive by gravity all the sewage from South and West Baltimore, and after treating it there to force it by means of gigantic pumps to the disposal plant some miles away. It was necessary for carrying out this purpose to have the foundations unusually strong, and to insure that, the following provision was made in Contract No. 3:

“68. It is expected that satisfactory material for the foundations will be found at El. 23, but the contractor shall carry the excavation to a greater depth wherever, in the opinion of the engineer, such greater depth is necessary to secure a suitable foundation. If, on the other hand, a satisfactory foundation is found at a less depth than El. 23, the excavation shall be discontinued at that depth, if directed by the engineer.”

The contracts and specifications are contained in printed books covering over 180 pages, and as it would be impossible to reproduce them in full, we have confined ourselves to quoting those which we consider most applicable to this controversy.

The work on the substructure was begun on June 29, 1908, and the whole building completed August 24, 1911, and under1 date of August 25th and September 11, 1911, the architect and the engineer respectively certified to the Oommission that the number of days the contractor was in default under the contracts was 144% working, days, at thirty-five dollars per day, and therefore subject to damages of $5,-083.75. The amount of money certified to be due under the contracts less $5,083.75 was paid over to the contractor.

Receivers were appointed for the Noel Construction Company and this action was commenced by them on the 6th *643

Free access — add to your briefcase to read the full text and ask questions with AI

Related

James Julian, Inc. v. State Highway Administration
492 A.2d 308 (Court of Special Appeals of Maryland, 1985)
American Structures, Inc. v. Mayor of Baltimore
364 A.2d 55 (Court of Appeals of Maryland, 1976)
Mutual Chemical Co. of America v. Mayor of Baltimore
33 F. Supp. 881 (D. Maryland, 1940)
Mayor & City Council of Baltimore v. M. A. Talbott Co.
105 A. 149 (Court of Appeals of Maryland, 1918)

Cite This Page — Counsel Stack

Bluebook (online)
104 A. 360, 132 Md. 637, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mayor-of-baltimore-v-poe-md-1918.