Baltimore Contractors, LLC v. Mayor & City Council of Baltimore

869 A.2d 396, 161 Md. App. 388, 2005 Md. App. LEXIS 21
CourtCourt of Special Appeals of Maryland
DecidedFebruary 28, 2005
DocketNo. 2808
StatusPublished

This text of 869 A.2d 396 (Baltimore Contractors, LLC v. Mayor & City Council of Baltimore) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Baltimore Contractors, LLC v. Mayor & City Council of Baltimore, 869 A.2d 396, 161 Md. App. 388, 2005 Md. App. LEXIS 21 (Md. Ct. App. 2005).

Opinion

SHARER, J.

This appeal arises from a disagreement about the form of dispute resolution to be utilized under a construction contract between the parties. We are asked to decide whether the parties are bound to arbitrate their contractual dispute, or whether the aggrieved contractor is required to pursue an administrative remedy.

Appellant, Baltimore Contractors, LLC (“Contractor”), claims that appellee, Mayor and City Council of Baltimore (“the City”), materially breached the building contract under which it was to construct a police station for the City. After limited, unsuccessful, attempts to resolve the dispute through administrative channels, Contractor brought an action in the Circuit Court for Baltimore City, seeking a declaratory judgment that the City was compelled to submit the issues to binding arbitration.

Concluding that Contractor had failed to exhaust its administrative remedies, the circuit court granted summary judgment in favor of the City. That ruling has led to this appeal, in which appellant presents for our review two questions, which we have distilled into:

Whether the contract, considering provisions of the Baltimore City Charter, requires that the parties submit to binding arbitration of their dispute.1

[391]*391We shall hold that the parties are bound by the provisions of the Baltimore City Charter, Article II, Section 4A, and must adhere to the procedures provided therein. Therefore, we shall affirm.

FACTUAL BACKGROUND

Appellant, a general contractor, entered into a contract with the City, the owner, for the construction of a project known as the Northern District Police Station. The original contract price was $4,360,000, and the contract called for completion of the project in 270 calendar days. Contractor claims that the City, through a series of delays and failures of performance, materially breached the contract in a number of ways, causing damage.

In an effort to resolve the various disputes, Contractor submitted its claims to Gerald W. Weeks, the City Inspector assigned to the project. After reviewing those claims, Weeks determined them to be without merit. Contractor then sought further review by Keith Scroggins, head of the City’s Bureau of General Services. That review produced a similar decision.

Appealing the Scroggins decision, Contractor submitted its claim to George Winfield, the City’s Director of Public Works, in August 2003, and sought an evidentiary hearing. In accordance with Baltimore City’s established dispute resolution procedure, Winfield began the process of creating a scheduling order for a hearing.

Before Winfield could complete the hearing process, Contractor, on August 29, 2003, filed this action seeking a declaration that the City was compelled to arbitrate. As a resuit, the administrative procedure was stayed.

We shall address additional facts as necessary to provide context.

[392]*392PROCEDURAL HISTORY

Count I of Contractor’s complaint sought a declaratory-judgment that the dispute resolution clause in the contract required the parties to proceed to binding arbitration.2

On October 31, 2003, the City filed a Motion to Dismiss, or in the Alternative, Motion for Summary Judgment, asserting that Contractor was not entitled to judicial relief because it had failed to exhaust its administrative remedies.3 On November 7, 2004, Contractor filed its Cross Motion for Summary Judgment and opposition to the City’s motion, again asserting that the contract compelled arbitration.

The issues came on for a motions hearing in the circuit court on December 22, 2003, at which counsel argued their respective positions. No testimony was taken. On February 23, 2004, the court -filed a written memorandum opinion, denying Contractor’s Motion for Summary Judgment and granting the City’s Motion for Summary Judgment. A final judgment was entered in favor of the City on all three counts of the complaint.

We set out relevant parts of the circuit court’s memorandum, declaring the rights of the parties:

Citing Nelley v. Mayor and Mayor and City Council v. Allied Contractors, [Contractor] argues that use of the term “referee” in the contract dispute provision mandates the conclusion that the provision is an arbitration clause.
[Contractor’s] reliance on Nelley and Allied Contractors is not persuasive. The contract language at issue here was not at issue in either of those cases. In Allied Contractors, a decision made by the Director of Public Works, under a [393]*393contract provision similar to the one here, was at issue. The opinion makes reference to “arbitrator” and “arbitration,” but no party objected to that characterization. Indeed, the City was the party that referred [the claim] to the Director of Public Works in his dispute resolution capacity as arbitrator. Although whether he was an [sic] neutral, arbitrator, mediator or something else was not at issue, the language of Judge Hammond does not support the position of [Contractor]. Judge Hammond’s language suggests that the Director of Public Works is something different than an arbitrator: “It is established that when the parties have provided for a binding determination of disputed matters by a designated person, such as an architect [or] engineer, even though that person is an official or representative of one of the parties, his decision is the equivalent of the award of an arbitratorf.]” Nelley is of no greater help to the [Contractor], Again, the Court of Appeals makes casual reference to arbitrator and referee in a case about the power of referee/arbitrator to decide misrepresentation claims. The Court did not decide that a reference to a “referee” meant “arbitrator.”
[Contractor] abandoned its argument that the contract provision at issue is void[.] Even if [Contractor] has not abandoned his claim entirely, however ... the Court accepts the [City’s] position that the dispute clause of the contract is valid for the reasons stated by Judge Smalkin of the United States District Court for the District of Maryland in MCI Constructors, LLC v. Mayor and City Council, exhibit 5 to the [City’s] Memorandum. Because the only position advanced by [Contractor] is premised on its erroneous conclusion that the parties[ ] agreed to arbitration by appointing the Director of Public Works as “referee,” [contractor’s] motion for summary judgment will be denied.
Moreover, the Court agrees with [the City] that [Contractor] is required to, and has not, exhausted its administrative remedies before pursuing its claim in this Court. Accordingly, the Court will grant summary judgment for [the City] and against [Contractor] on Count 1 finding that [Contrae[394]*394tor] has abandoned] the relief sought under this count and, alternatively, that [Contractor] is not entitled to the relief sought. The Court will grant summary judgment in favor of [the City] on Counts II and III for the reason that [contractor] has not exhausted its administrative remedies.

Appellant noted this timely appeal.

Whether the contract, considering provisions of the Baltimore City Charter, requires that the parties submit to binding arbitration of their dispute.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Beyer v. Morgan State University
800 A.2d 707 (Court of Appeals of Maryland, 2002)
Nelley v. Mayor of Baltimore
166 A.2d 234 (Court of Appeals of Maryland, 1960)
Mayor of Baltimore v. Allied Contractors, Inc.
204 A.2d 546 (Court of Appeals of Maryland, 1964)
Wright v. Commercial & Savings Bank
464 A.2d 1080 (Court of Appeals of Maryland, 1983)
Brown v. Fire & Police Employees' Retirement System
826 A.2d 525 (Court of Appeals of Maryland, 2003)
Intercom Systems Corp. v. Bell Atlantic of Maryland, Inc.
763 A.2d 1196 (Court of Special Appeals of Maryland, 2000)
Wickman v. Kane
766 A.2d 241 (Court of Special Appeals of Maryland, 2001)
Okwa v. Harper
757 A.2d 118 (Court of Appeals of Maryland, 2000)
Rogers Refrigeration Co. v. Pulliam's Garage, Inc.
505 A.2d 878 (Court of Special Appeals of Maryland, 1986)
Todd v. Mass Transit Administration
816 A.2d 930 (Court of Appeals of Maryland, 2003)
Joseph F. Trionfo & Sons, Inc. v. Ernest B. Larosa & Sons, Inc.
381 A.2d 727 (Court of Special Appeals of Maryland, 1978)
Gontrum v. Mayor of Baltimore
35 A.2d 128 (Court of Appeals of Maryland, 1943)
Lema v. Bank of America, N.A.
826 A.2d 504 (Court of Appeals of Maryland, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
869 A.2d 396, 161 Md. App. 388, 2005 Md. App. LEXIS 21, Counsel Stack Legal Research, https://law.counselstack.com/opinion/baltimore-contractors-llc-v-mayor-city-council-of-baltimore-mdctspecapp-2005.