Mayor of Baltimore v. Allied Contractors, Inc.

204 A.2d 546, 236 Md. 534, 1964 Md. LEXIS 911
CourtCourt of Appeals of Maryland
DecidedNovember 16, 1964
Docket[No. 53, September Term, 1964.]
StatusPublished
Cited by30 cases

This text of 204 A.2d 546 (Mayor of Baltimore v. Allied Contractors, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mayor of Baltimore v. Allied Contractors, Inc., 204 A.2d 546, 236 Md. 534, 1964 Md. LEXIS 911 (Md. 1964).

Opinion

Hammond, J.,

delivered the opinion of the Court.

This case comes to us confused by the granting below of a summary judgment after two days of testimony on the issues on which the parties differed, but as we see it the points on which the decision must turn are (a) whether the determina *538 tion by the Director of Public Works of Baltimore that a specified number of dollars was due the appellee, Allied Contractors, Inc., for extra work and expense caused by the City during performance of a construction contract was made by him under the contract provisions that :

“To prevent disputes and litigations, the Director will be the referee in case any question shall arise between the Contractor and the City touching the Contract, and his determination, decision and/or estimate shall be final and conclusive upon the Contractor, and shall also be a condition precedent to the right of the Contractor to receive any moneys under the Contract”

and (b) if so, whether the City was finally bound by the determination or could, as it attempted to do, repudiate the determination and tender a lesser sum in full settlement.

Allied was awarded the contract for the erection of a bridge over Northern Parkway by the City in June 1958. Due to a change in plans, notice to proceed was not given until November. Claiming damages and extra costs of $104,266.26 because of this delay and other reasons attributed to the City — such as extra work, additional costs of winter concreting, changes in construction procedures, added costs of a structural steel assessed to Allied by its suppliers because delivery was delayed, and the cost of rebuilding forms that had been made unusable Allied made demand for payment of this sum upon the City. In March 1961, apparently pursuant to a suggestion by the consulting engineers, J. E. Greiner and Co., Allied submitted a written detailed summary of its claims to. the City’s highways engineer, Walters, sending a copy to the bridge engineer, Kravetz, and a copy to Greiner.

On April 13, 1961, a meeting was held in Walters’ office attended by him, Kravetz, an assistant of Kravetz, and three Greiner engineers. The Greiner men explained that they could make recommendations on all claims but that final decision on some would depend on the policy of the City in regard to the lapse of time between an award and the notice to proceed. They then made comments and specific recommendations to the City officials on each of Allied’s various claims, generally recom *539 mending no allowance at all but, as to some, suggesting payment of a small percentage of the amount claimed.

A week later, on April 20, 1961, Walters wrote Allied saying that after examination “and carefully weighing all the circumstances connected with this contract,” the City disallowed all claims. The letter then suggested that under Sec. 4-39 of the contract specifications the matter could go to the Director of Public Works, Werner, for his controlling decision. On May 12, Allied wrote Werner saying that Walters had disallowed their claims on April 20 and that “in accordance with Section 4-39 of the specifications of this contract, we wish to appeal this decision.”

Werner then directed Walters and Kravetz to make an investigation and analysis of the facts and figures involved in the claims. A meeting was held on May 22, 1961, attended by Walters and Kravetz, representing the City, and Allied’s president, Pécora, and its vice-president, Kingan. One small claim was approved and it was agreed that the others would first be gone over by the City and Allied and, if possible, agreed on, and then submitted to Werner for his decision. A number of meetings followed, culminating with two full days of investigation by Kravetz at Allied’s office (on Friday, September 29, and Saturday, September 30), during which each claim was again checked in detail. Kravetz was given Allied’s complete files including material and time sheets, cancelled checks and other written data he wanted for verifications. As a result of this detailed study, Allied’s claim of $104,266.26 was cut to $71,106.90. Kravetz told Allied he would recommend to his superior Walters that this amount be paid and if Walters agreed that it should the figure would be submitted to Werner for his final decision, and Allied assented.

Walters did accept Kravetz’ recommendation after a meeting' in late October with Pécora and Kravetz at which the claims again were gone over thoroughly. Walters suggested to Pécora that he “set up” a meeting with Werner for submission of the claims as reduced. The meeting was held on November 3, attended by Werner, Walters, Kravetz and Pécora. The claims were discussed one by one, with consideration being given to their backgrounds and reasons for being, and their *540 merits and amounts, as originally submitted and as reduced. After this, Walters recommended payment of the claims and Werner said he would accept the recommendation.

Thereupon Walters handed Werner a letter addressed to the Board of Estimates of Baltimore City recommending payment to Allied in the amount of $71,106.90, which he told Werner he had caused to be prepared in anticipation of Werner’s decision. The letter which was dated November 1 and signed by Walters (a) recited the date of the contract, June 25, 1958, the beginning of work on December 1, 1958, and its finish on August 24, 1960, resulting in a total of 349 working days compared to the 270 such days allowed by the contract, and that the final cost of the work performed by Allied was $66,790.98 more than the contract price (the parties are in agreement that previously authorized funds were available to pay the sum of $4,315.92 which is the difference between $71,106.90, the amount it had been determined Allied should receive, and $66,790.98, so that only the latter amount presently was sought from the Board of Estimates); (b) explained the reasons for the delay (deletion of a water line from the bridge and construction by the City of a sewer line in the area) ; (c) set out the details and amounts of each claim; (d) requested authority to. expend $66,790.98; and concluded (e) “these facts, together with the delays interposed by the sewer line construction and changes in plans, in our opinion justify the allowance of 79 extra working days shown by the record, and it is so recommended for your approval.”

Werner read the letter, signed it under the typed word “approved” and over the typed words “Director of Public Works” and then authorized its presentation to the Board of Estimates. He directed Walters and Kravetz to be before the Board when the letter was presented in order to be available to answer any questions. Pécora was given a copy of the letter and assured that it would be his evidence that the City had agreed to pay Allied and that payment could be expected in a matter of days after the Board of Estimates approved the request for funds.

On November 8 the Board, at a formal meeting, did approve the request. Allied was not paid because the City disbursing department would not pay more than the $66,790.98 authorized *541

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Downey v. Sharp
51 A.3d 573 (Court of Appeals of Maryland, 2012)
Gebhardt & Smith LLP v. Maryland Port Administration
982 A.2d 876 (Court of Special Appeals of Maryland, 2009)
AFSCME, Council 4, Local 1565 v. Department of Correction
945 A.2d 494 (Connecticut Appellate Court, 2008)
Phoenix Services Ltd. Partnership v. Johns Hopkins Hospital
892 A.2d 1185 (Court of Special Appeals of Maryland, 2006)
Baltimore Contractors, LLC v. Mayor & City Council of Baltimore
869 A.2d 396 (Court of Special Appeals of Maryland, 2005)
Baltimore Teachers Union v. Mayor and City Council of Baltimore
671 A.2d 80 (Court of Special Appeals of Maryland, 1996)
Port East Transfer, Inc. v. Liberty Mutual Insurance
624 A.2d 520 (Court of Appeals of Maryland, 1993)
Baltimore County v. Mayor of Baltimore
621 A.2d 864 (Court of Appeals of Maryland, 1993)
Garrity v. McCaskey
612 A.2d 742 (Supreme Court of Connecticut, 1992)
Foy v. Prudential Insurance Co. of America
559 A.2d 371 (Court of Appeals of Maryland, 1989)
Barry Properties, Inc. v. Blanton & McCleary
525 A.2d 248 (Court of Special Appeals of Maryland, 1987)
Board of Education v. Prince George's County Educators' Ass'n
522 A.2d 931 (Court of Appeals of Maryland, 1987)
Bd. of Educ. v. PG CO. EDUCATORS'ASS'N
522 A.2d 931 (Court of Appeals of Maryland, 1987)
Amalgamated Transit Union, Division 1300 v. Mass Transit Administration
504 A.2d 1132 (Court of Appeals of Maryland, 1986)
Air Power, Inc. v. Omega Equipment Corp.
459 A.2d 1120 (Court of Special Appeals of Maryland, 1983)
Mayor of Baltimore v. Ohio Casualty Insurance
438 A.2d 933 (Court of Special Appeals of Maryland, 1982)
Joseph F. Trionfo & Sons, Inc. v. Ernest B. Larosa & Sons, Inc.
381 A.2d 727 (Court of Special Appeals of Maryland, 1978)
Medical Mutual Liability Insurance Society v. Mutual Fire, Marine & Inland Insurance
379 A.2d 739 (Court of Special Appeals of Maryland, 1977)
American Structures, Inc. v. Mayor of Baltimore
364 A.2d 55 (Court of Appeals of Maryland, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
204 A.2d 546, 236 Md. 534, 1964 Md. LEXIS 911, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mayor-of-baltimore-v-allied-contractors-inc-md-1964.