Star Development Group, LLC v. Darwin National Assurance

Court of Appeals for the Fourth Circuit·Decided May 8, 2020·No. 19-1042·Unpublished

Opinion

UNPUBLISHED

UNITED STATES COURT OF APPEALS FOR THE FOURTH CIRCUIT

No. 19-1042

STAR DEVELOPMENT GROUP, LLC; HOPKINS HOSPITALITY INVESTORS, LLC; HOPKINS INVESTORS, LLC,

Plaintiffs - Appellants,

v.

DARWIN NATIONAL ASSURANCE COMPANY; CONSTRUCTURE MANAGEMENT, INC.,

Defendants - Appellees.

Appeal from the United States District Court for the District of Maryland, at Baltimore. Richard D. Bennett, District Judge. (1:16-cv-01246-RDB)

Submitted: March 11, 2020 Decided: May 8, 2020

Before KEENAN, WYNN, and RICHARDSON, Circuit Judges.

Affirmed by unpublished opinion. Judge Wynn wrote the opinion, in which Judge Keenan and Judge Richardson joined.

Kenneth K. Sorteberg, HUDDLES, JONES, SORTEBERG & DACHILLE, P.C., Columbia, Maryland, for Appellants. Adam M. Tuckman, WATT, TIEDER, HOFFAR & FITZGERALD, LLP, McLean, Virginia, for Appellees.

Unpublished opinions are not binding precedent in this circuit.

WYNN, Circuit Judge:

Plaintiffs-Appellants Star Development Group, LLC (“Star”), Hopkins Hospitality Investors, LLC, and Hopkins Investors, LLC (collectively, “Hopkins”) appeal the district court’s denial of their petition to vacate an arbitration award in favor of Defendants- Appellees Constructure Management, Inc. (“Constructure”) and Darwin National Assurance Company (“Darwin”). Plaintiffs also appeal the district court’s grant of attorneys’ fees to Defendants. Conducting a deferential and circumscribed review of the arbitration decision under controlling law, we discern no legal or factual error sufficient to overturn the arbitration award. Nor do we find any error in the district court’s grant of attorneys’ fees. We thus affirm.

I.

A.

In 2013, Star and Constructure entered into a contract (the “Contract”) for the construction of a Homewood Suites hotel in Laurel, Maryland. 1 Hopkins owns the property, Star was its construction and development manager, Constructure was the general contractor for the hotel’s construction, and Darwin 2 served as Constructure’s surety for performance and payment to Star and Hopkins under the Contract. The construction covered two distinct sections of the hotel: a tower portion containing the guest rooms, and a one-story area containing the lobby, restaurant, and meeting areas.

1 The Contract consists of two documents, a “Standard Form of Agreement Between Owner and Contractor” and “General Conditions of the Contract for Construction.” References to the “Contract” in this opinion encompass both. 2 Darwin is now known as Allied World Specialty Insurance.

The Contract specified a maximum cost of $11 million and an original completion date of July 26, 2014 (the “Substantial Completion Date”). The construction was ultimately completed approximately one year later, on August 6, 2015.

B.

In 2016, Plaintiffs sued Defendants in Maryland state court for breach of contract.

Defendants removed the case to the United States District Court for the District of Maryland on the basis of diversity. That court then stayed the case while the parties participated in arbitration pursuant to the Contract.

The parties asserted a variety of claims against each other before a panel of three American Arbitration Association construction arbitrators (the “Arbitration Panel”). Relevant to this appeal, following an eight-day hearing, the Arbitration Panel issued a final award (the “Award”) denying Star’s alleged $4 million in delay damages arising from the hotel’s completion 376 days after the Substantial Completion Date. Star claimed that the delay was entirely Constructure’s fault, while Constructure claimed the delay was excusable.

The Arbitration Panel held the parties concurrently responsible for the delay, reasoning that Star delayed completion of the one-story section while Constructure delayed completion of the tower section. Specifically, in the months and days leading up to the Substantial Completion Date, Star submitted numerous structural design changes to the one-story section, requiring Constructure to add extra steel supports. The Arbitration Panel thus attributed the delay in completion of the one-story portion to Star. As to the tower section, the Arbitration Panel found that the main delay arose from Constructure’s

difficulty in managing its primary subcontractor. It thus attributed that delay to Constructure.

The Arbitration Panel then denied Star’s delay damages claims as waived. In reaching this conclusion, the Arbitration Panel had to consider § 8.3.1.2 of the Contract. That section prevented Constructure from seeking a time extension for any delay to which it contributed:

Notwithstanding Section 8.3.1.1, or anything to the contrary set forth in the Contract, in no event shall Contractor [Constructure] be entitled to an extension of the Contract Time, nor to recover Extended General Conditions nor to recover any other damages, costs or expenses of any kind as a result of a delay or suspension, if such delay or suspension for which Contractor claims entitlement: (a) was caused in whole or in part, directly or indirectly, by the wrongful acts or omissions or other default of Contractor or any other Contractor Party; and/or (b) is concurrent with a delay caused in whole or in part, directly or indirectly, by the wrongful acts or omissions or other default of Contractor or any other Contractor Party.

J.A. 151 (emphases added). Star’s theory of delay damages was that § 8.3.1.2 barred Constructure from seeking a time extension where it contributed to a delay, regardless of any delay imposed by Star. Accordingly, reasoned Star, Constructure was liable for any slippage in the schedule past the Substantial Completion Date. And because § 8.3.1.2 was part of the Contract, Star contended it overrode any otherwise applicable defense related to concurrent delays found in general construction contract law.

The Arbitration Panel disagreed, finding that Star, through its dilatory conduct, waived the Substantial Completion Date. Specifically, the Arbitration Panel noted that: (1) Star repeatedly submitted structural design changes to the single-story section, including several changes submitted days before the Substantial Completion Date, rendering

completion by that date impossible; (2) Star did not submit any evidence showing that it intended to hold Constructure to the original completion date or attempted to establish a new completion date; and (3) Star did not respond to a 39-day extension request for poor weather conditions that Constructure submitted in September 2014. 3 Finding the Substantial Completion Date waived, the Arbitration Panel found that Constructure was only obligated to complete the construction in a reasonable time period. The Arbitration Panel found that it did so, thus foreclosing Star’s claims for delay damages. 4 In the Award, the Arbitration Panel also granted Constructure $1,766,033.00 in unpaid contract balance. In this appeal, Plaintiffs dispute $368,504.18 of that amount, representing the cost of structural steel additions to the one-story portion of the hotel arising from Star’s late-submitted alterations to the building plans (the “Steel Costs”).

C.

Following the Arbitration Panel’s issuance of the Award, Plaintiffs petitioned the district court to vacate the Award and Defendants petitioned to confirm the Award and for

Free access — add to your briefcase to read the full text and ask questions with AI

Star Development Group, LLC v. Darwin National Assurance, (4th Cir. 2020).

Star Development Group, LLC v. Darwin National Assurance (Star Development Group, LLC v. Darwin National Assurance) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

United Steelworkers v. Enterprise Wheel & Car Corp.
363 U.S. 593 (Supreme Court, 1960)
Southland Corp. v. Keating
465 U.S. 1 (Supreme Court, 1984)
Salve Regina College v. Russell
499 U.S. 225 (Supreme Court, 1991)
Mastrobuono v. Shearson Lehman Hutton, Inc.
514 U.S. 52 (Supreme Court, 1995)
Hall Street Associates, L. L. C. v. Mattel, Inc.
552 U.S. 576 (Supreme Court, 2008)
Blinderman Construction Co., Inc. v. The United States
695 F.2d 552 (Federal Circuit, 1982)
Porter Hayden Company v. Century Indemnity Company
136 F.3d 380 (Fourth Circuit, 1998)
Federal Insurance v. Allstate Insurance
341 A.2d 399 (Court of Appeals of Maryland, 1975)
Snyder v. BERLINER CONSTRUCTION CO.
555 A.2d 523 (Court of Special Appeals of Maryland, 1989)
Rourke v. Amchem Products, Inc.
863 A.2d 926 (Court of Appeals of Maryland, 2004)
University National Bank v. Wolfe
369 A.2d 570 (Court of Appeals of Maryland, 1977)
Stephen L. Messersmith, Inc. v. Barclay Townhouse Associates
547 A.2d 1048 (Court of Appeals of Maryland, 1988)
Womach v. Thomas
486 A.2d 15 (Court of Chancery of Delaware, 1984)
Blitz v. Beth Isaac Adas Israel Congregation
720 A.2d 912 (Court of Appeals of Maryland, 1998)