Star Development Group, LLC v. Darwin National Assurance

CourtCourt of Appeals for the Fourth Circuit
DecidedMay 8, 2020
Docket19-1042
StatusUnpublished

This text of Star Development Group, LLC v. Darwin National Assurance (Star Development Group, LLC v. Darwin National Assurance) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Star Development Group, LLC v. Darwin National Assurance, (4th Cir. 2020).

Opinion

UNPUBLISHED

UNITED STATES COURT OF APPEALS FOR THE FOURTH CIRCUIT

No. 19-1042

STAR DEVELOPMENT GROUP, LLC; HOPKINS HOSPITALITY INVESTORS, LLC; HOPKINS INVESTORS, LLC,

Plaintiffs - Appellants,

v.

DARWIN NATIONAL ASSURANCE COMPANY; CONSTRUCTURE MANAGEMENT, INC.,

Defendants - Appellees.

Appeal from the United States District Court for the District of Maryland, at Baltimore. Richard D. Bennett, District Judge. (1:16-cv-01246-RDB)

Submitted: March 11, 2020 Decided: May 8, 2020

Before KEENAN, WYNN, and RICHARDSON, Circuit Judges.

Affirmed by unpublished opinion. Judge Wynn wrote the opinion, in which Judge Keenan and Judge Richardson joined.

Kenneth K. Sorteberg, HUDDLES, JONES, SORTEBERG & DACHILLE, P.C., Columbia, Maryland, for Appellants. Adam M. Tuckman, WATT, TIEDER, HOFFAR & FITZGERALD, LLP, McLean, Virginia, for Appellees.

Unpublished opinions are not binding precedent in this circuit. WYNN, Circuit Judge:

Plaintiffs-Appellants Star Development Group, LLC (“Star”), Hopkins Hospitality

Investors, LLC, and Hopkins Investors, LLC (collectively, “Hopkins”) appeal the district

court’s denial of their petition to vacate an arbitration award in favor of Defendants-

Appellees Constructure Management, Inc. (“Constructure”) and Darwin National

Assurance Company (“Darwin”). Plaintiffs also appeal the district court’s grant of

attorneys’ fees to Defendants. Conducting a deferential and circumscribed review of the

arbitration decision under controlling law, we discern no legal or factual error sufficient to

overturn the arbitration award. Nor do we find any error in the district court’s grant of

attorneys’ fees. We thus affirm.

I.

A.

In 2013, Star and Constructure entered into a contract (the “Contract”) for the

construction of a Homewood Suites hotel in Laurel, Maryland. 1 Hopkins owns the

property, Star was its construction and development manager, Constructure was the general

contractor for the hotel’s construction, and Darwin 2 served as Constructure’s surety for

performance and payment to Star and Hopkins under the Contract. The construction

covered two distinct sections of the hotel: a tower portion containing the guest rooms, and

a one-story area containing the lobby, restaurant, and meeting areas.

1 The Contract consists of two documents, a “Standard Form of Agreement Between Owner and Contractor” and “General Conditions of the Contract for Construction.” References to the “Contract” in this opinion encompass both. 2 Darwin is now known as Allied World Specialty Insurance. 2 The Contract specified a maximum cost of $11 million and an original completion

date of July 26, 2014 (the “Substantial Completion Date”). The construction was ultimately

completed approximately one year later, on August 6, 2015.

B.

In 2016, Plaintiffs sued Defendants in Maryland state court for breach of contract.

Defendants removed the case to the United States District Court for the District of

Maryland on the basis of diversity. That court then stayed the case while the parties

participated in arbitration pursuant to the Contract.

The parties asserted a variety of claims against each other before a panel of three

American Arbitration Association construction arbitrators (the “Arbitration Panel”).

Relevant to this appeal, following an eight-day hearing, the Arbitration Panel issued a final

award (the “Award”) denying Star’s alleged $4 million in delay damages arising from the

hotel’s completion 376 days after the Substantial Completion Date. Star claimed that the

delay was entirely Constructure’s fault, while Constructure claimed the delay was

excusable.

The Arbitration Panel held the parties concurrently responsible for the delay,

reasoning that Star delayed completion of the one-story section while Constructure delayed

completion of the tower section. Specifically, in the months and days leading up to the

Substantial Completion Date, Star submitted numerous structural design changes to the

one-story section, requiring Constructure to add extra steel supports. The Arbitration Panel

thus attributed the delay in completion of the one-story portion to Star. As to the tower

section, the Arbitration Panel found that the main delay arose from Constructure’s

3 difficulty in managing its primary subcontractor. It thus attributed that delay to

Constructure.

The Arbitration Panel then denied Star’s delay damages claims as waived. In

reaching this conclusion, the Arbitration Panel had to consider § 8.3.1.2 of the Contract.

That section prevented Constructure from seeking a time extension for any delay to which

it contributed:

Notwithstanding Section 8.3.1.1, or anything to the contrary set forth in the Contract, in no event shall Contractor [Constructure] be entitled to an extension of the Contract Time, nor to recover Extended General Conditions nor to recover any other damages, costs or expenses of any kind as a result of a delay or suspension, if such delay or suspension for which Contractor claims entitlement: (a) was caused in whole or in part, directly or indirectly, by the wrongful acts or omissions or other default of Contractor or any other Contractor Party; and/or (b) is concurrent with a delay caused in whole or in part, directly or indirectly, by the wrongful acts or omissions or other default of Contractor or any other Contractor Party.

J.A. 151 (emphases added). Star’s theory of delay damages was that § 8.3.1.2 barred

Constructure from seeking a time extension where it contributed to a delay, regardless of

any delay imposed by Star. Accordingly, reasoned Star, Constructure was liable for any

slippage in the schedule past the Substantial Completion Date. And because § 8.3.1.2 was

part of the Contract, Star contended it overrode any otherwise applicable defense related

to concurrent delays found in general construction contract law.

The Arbitration Panel disagreed, finding that Star, through its dilatory conduct,

waived the Substantial Completion Date. Specifically, the Arbitration Panel noted that: (1)

Star repeatedly submitted structural design changes to the single-story section, including

several changes submitted days before the Substantial Completion Date, rendering

4 completion by that date impossible; (2) Star did not submit any evidence showing that it

intended to hold Constructure to the original completion date or attempted to establish a

new completion date; and (3) Star did not respond to a 39-day extension request for poor

weather conditions that Constructure submitted in September 2014. 3 Finding the

Substantial Completion Date waived, the Arbitration Panel found that Constructure was

only obligated to complete the construction in a reasonable time period. The Arbitration

Panel found that it did so, thus foreclosing Star’s claims for delay damages. 4

In the Award, the Arbitration Panel also granted Constructure $1,766,033.00 in

unpaid contract balance. In this appeal, Plaintiffs dispute $368,504.18 of that amount,

representing the cost of structural steel additions to the one-story portion of the hotel arising

from Star’s late-submitted alterations to the building plans (the “Steel Costs”).

C.

Following the Arbitration Panel’s issuance of the Award, Plaintiffs petitioned the

district court to vacate the Award and Defendants petitioned to confirm the Award and for

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United Steelworkers v. Enterprise Wheel & Car Corp.
363 U.S. 593 (Supreme Court, 1960)
Southland Corp. v. Keating
465 U.S. 1 (Supreme Court, 1984)
Salve Regina College v. Russell
499 U.S. 225 (Supreme Court, 1991)
Mastrobuono v. Shearson Lehman Hutton, Inc.
514 U.S. 52 (Supreme Court, 1995)
Hall Street Associates, L. L. C. v. Mattel, Inc.
552 U.S. 576 (Supreme Court, 2008)
Blinderman Construction Co., Inc. v. The United States
695 F.2d 552 (Federal Circuit, 1982)
Porter Hayden Company v. Century Indemnity Company
136 F.3d 380 (Fourth Circuit, 1998)
Federal Insurance v. Allstate Insurance
341 A.2d 399 (Court of Appeals of Maryland, 1975)
Snyder v. BERLINER CONSTRUCTION CO.
555 A.2d 523 (Court of Special Appeals of Maryland, 1989)
Rourke v. Amchem Products, Inc.
863 A.2d 926 (Court of Appeals of Maryland, 2004)
University National Bank v. Wolfe
369 A.2d 570 (Court of Appeals of Maryland, 1977)
Stephen L. Messersmith, Inc. v. Barclay Townhouse Associates
547 A.2d 1048 (Court of Appeals of Maryland, 1988)
Womach v. Thomas
486 A.2d 15 (Court of Chancery of Delaware, 1984)
Blitz v. Beth Isaac Adas Israel Congregation
720 A.2d 912 (Court of Appeals of Maryland, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
Star Development Group, LLC v. Darwin National Assurance, Counsel Stack Legal Research, https://law.counselstack.com/opinion/star-development-group-llc-v-darwin-national-assurance-ca4-2020.