Law v. United States

195 Ct. Cl. 370, 1971 U.S. Ct. Cl. LEXIS 54, 1971 WL 17828
CourtUnited States Court of Claims
DecidedJuly 14, 1971
DocketNo. 453-59
StatusPublished
Cited by38 cases

This text of 195 Ct. Cl. 370 (Law v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Law v. United States, 195 Ct. Cl. 370, 1971 U.S. Ct. Cl. LEXIS 54, 1971 WL 17828 (cc 1971).

Opinion

Pee Cueiam: This case was referred to Trial Commissioner Saul Bicbard Gramer with directions to make findings of fact and recommendation for conclusions of law under the order of reference and Buie 134(h). The commissioner has done so in an opinion and report filed on April 16, 1971, wherein he concluded “that defendant has failed to meet the burden of proof * * * that plaintiff * * * ‘corruptly’ practiced or attempted ‘to practice any fraud against the United States in the proof, statement, establishment, or allowance’ of the claim herein” and recommended that judgment be entered for plaintiff in the amount of $216,574.53. Plaintiff and defendant each obtained an extension of time to file a notice of intention to except to the commissioner’s report and recommendation but neither filed such notice or any exception. On May 28, 1971, the parties filed a stipulation of settlement wherein, among other things, it is stated that the “stipulation is made for the purpose of enabling the court to enter judgment in favor of plaintiffs and against the defendant in the sum of $216,574.53 and to dismiss, with prejudice, the defendant’s plea in fraud.” Subsequently, on June 14, 1971, for plaintiff and June 15, 1971, for defendant, each party filed a motion for enlargement or extension of time to file a notice of intention to except to the commissioner’s report, reciting therein the filing of the stipulation of May 28, 1971 and the fact that it had not yet been acted upon by the court.

[377]*377Since the court agrees with, the commissioner’s opinion, findings and recommended conclusion of law, it hereby adopts the same, without oral argument, together with the stipulation of the parties, filed May 28, 1971, as the basis for its judgment in this case. Therefore, plaintiffs (trustees in dissolution) are entitled to recover, judgment is entered for plaintiffs (trustees in dissolution) in the sum of $216,574.53 and defendant’s plea in fraud is dismissed with prejudice.

OPINION OP COMMISSIONER

Gamer, Commissioner:

Daniel J. Cronin, Inc. (hereinafter sometimes referred to as “Cronin”), was a New Jersey corporation which, on May 11, 1951, entered into a $6,580,000 lump sum contract with defendant, acting through the Bureau of Yards and Docks, Department of the Navy, to perform certain construction work at the United States Naval Aeronautical Turbine Laboratory, Trenton, New Jersey. The work was described as the construction of a “High Pressure Blower Wing, Test Wing and Miscellaneous Construction.” The project in effect constituted a laboratory for the testing of turbo prop and turbo jet airplane engines under simulated flight conditions. Cronin’s work principally consisted of the erection of several buildings and the installation of an electrical distribution system and mechanical piping, including piping running between and connecting the buildings. Various complicated machines and pieces of equipment were to be installed in and around the structures which Cronin was to build. Most of these quite sophisticated machines and equipment items were to be furnished and installed by defendant. However, defendant acted through separate contracts with third parties under which such parties undertook to manufacture and install the machines and equipment. Included in Cronin’s work was the construction of the foundations for such machines and equipment. After the installation of such machines and equipment by defendant (i.e.: the third parties) , it was then Cronin’s responsibility to connect them to the piping. Thus, by reason of defendant’s undertaking the furnishing and the installation of the machines and equipment in and around the buildings and on the foundations which Cronin was to construct, there was cast upon defendant [378]*378the burden of effecting a rather intricate type of coordination between Cronin’s construction work and the work of the third-party machine and equipment contractors.

Cronin’s contract called for the completion of its work within 450 days after receipt of the notice of award. The receipt of such notice on May 11,1951 fixed August 3,1952 as the completion date. There was, however, an extraordinary time overrun of almost four years, the contract work not being finally accepted until June 28,1956, or 1,423 days after the original completion date. Cronin, was granted time extensions for the full overrun period, thus being relieved of any liability for liquidated damages (the contract rate being $1,200 per day).

Luring the course of construction, Cronin frequently complained about delays to and interference with its work allegedly caused by defendant. In addition, defendant initiated a very large number of changes and there was much controversy over the proper amount of compensation therefor. To help him decide the claims which Cronin submitted, at that time (1954) amounting to over $850,000 for the time overrun and almost $900,000 for increased change order compensation, the contracting officer appointed, at different times, two boards to investigate the claims and make recommendations with respect thereto. Thereafter, the contracting officer made certain allowances in connection with the change orders and disallowed the time overrun claim on the ground that it was a claim in the nature of damages for breach of contract, not compensable under the contract provisions. Cronin’s appeal to the Armed Services Board of Contract Appeals resulted in additional change order allowances but the Board dismissed the claims for delay as being beyond its jurisdiction.

Thereafter, Cronin filed an 82-page petition herein, consisting of 141 paragraphs, contending that the entire 1,423-day overrun was wholly attributable to scores of breaches of contract committed by defendant and claiming damages with respect thereto in the amount of $1,045,000. However, only one change order claim in the amount of approximately $15,600 is set forth in the petition.

As part of the pretrial proceedings, there was issued, under the court’s rules, a pretrial order addressed to the issue of [379]*379damages for the delays allegedly caused by defendant. The order directed Cronin to furnish to defendant, with respect to such of the damages as were based on Cronin’s books of account or other records, a statement showing the items and figures appearing in such books and records which Cronin intended to prove, and to make such books and records available for examination by defendant. In accordance therewith, Cronin submitted various accounting schedules detailing the basis of its claimed damages. The pretrial order also directed defendant, upon such submission by Cronin, to examine the books and records upon which the Cronin accounting schedules were based, and then, in turn, to submit to Cronin schedules showing the results of defendant’s examination, including an explanation of any differences between its schedules and Cronin’s.

Pursuant to the pretrial order, defendant (through four Special Agents of the Federal Bureau of Investigation, Department of Justice) examined the books and records of Cronin upon which the damage schedules had been based. Upon receiving the results of their examination, defendant came to the conclusion that certain of the Cronin damage schedules included, as alleged legitimate expenses of contract performance by the corporation, expenditures which were in fact the personal indebtednesses of its officers.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harry Pepper and Associates, Inc.
Armed Services Board of Contract Appeals, 2021
Nassar Group International
Armed Services Board of Contract Appeals, 2019
Safety Training Systems, Inc.
Armed Services Board of Contract Appeals, 2014
Fireman's Fund Insurance v. United States
92 Fed. Cl. 598 (Federal Claims, 2010)
Tecom, Inc. v. United States
66 Fed. Cl. 736 (Federal Claims, 2005)
Morganti National, Inc. v. United States
49 Fed. Cl. 110 (Federal Claims, 2001)
Louis Leustek & Sons, Inc. v. United States
41 Fed. Cl. 657 (Federal Claims, 1998)
Scott Timber Co. v. United States
42 Cont. Cas. Fed. 77,312 (Federal Claims, 1998)
Asco-Falcon II Shipping Co. v. United States
39 Cont. Cas. Fed. 76,731 (Federal Claims, 1994)
Ingalls Shipbuilding, Inc. v. United States
36 Cont. Cas. Fed. 75,908 (Court of Claims, 1990)
Colorado State Bank of Walsh v. United States
18 Cl. Ct. 611 (Court of Claims, 1989)
Nydan Construction Company, Inc. v. The United States
862 F.2d 320 (Federal Circuit, 1988)
Blue Cross & Blue Shield Ass'n v. United States
34 Cont. Cas. Fed. 75,408 (Court of Claims, 1987)
Martin J. Simko Construction, Inc. v. United States
33 Cont. Cas. Fed. 74,888 (Court of Claims, 1986)
Salem Engineering & Construction Corp. v. United States
31 Cont. Cas. Fed. 71,312 (Court of Claims, 1983)
McCarthy v. United States
1 Cl. Ct. 446 (Court of Claims, 1983)
Mel Williamson, Inc. v. United States
29 Cont. Cas. Fed. 82,195 (Court of Claims, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
195 Ct. Cl. 370, 1971 U.S. Ct. Cl. LEXIS 54, 1971 WL 17828, Counsel Stack Legal Research, https://law.counselstack.com/opinion/law-v-united-states-cc-1971.