Mel Williamson, Inc. v. United States

29 Cont. Cas. Fed. 82,195, 229 Ct. Cl. 846, 1982 U.S. Ct. Cl. LEXIS 49, 1982 WL 26558
CourtUnited States Court of Claims
DecidedFebruary 2, 1982
DocketNo. 8-81C
StatusPublished
Cited by11 cases

This text of 29 Cont. Cas. Fed. 82,195 (Mel Williamson, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mel Williamson, Inc. v. United States, 29 Cont. Cas. Fed. 82,195, 229 Ct. Cl. 846, 1982 U.S. Ct. Cl. LEXIS 49, 1982 WL 26558 (cc 1982).

Opinion

This case is presented to the court pursuant to 41 U.S.C. §§ 321, 322 (1976), the Wunderlich Act. Plaintiff seeks summary judgment in contesting the final decision of the Armed Services Board of Contract Appeals ( asbca ) in Mel Williamson, Inc., asbca No. 22983, 80-2 BCA ¶ 14,631 (1980). Defendant has filed a cross-motion for summary [847]*847judgment. We allow defendant’s motion and affirm the ASBCA.

The contract, No. F04609-77-90133, was executed by plaintiff and the United States Department of the Air Force (defendant) on September 22, 1977. Under this contract defendant agreed to pay plaintiff for certain repair work and installation of fire detection systems in several buildings located at George Air Force Base, California. Only item 2 of three items of the contract is in dispute before the court. This item involves the repairs for four buildings. A modified completion deadline for this work was set for March 30, 1978. On March 31 1978, defendant issued a show-cause notice for default termination on item 2, citing 11 violations of the contract. Correspondence and a conference followed and defendant extended the deadline to May 18, 1978. The work wa not completed by that date and on May 19, 1978, defendant issued a notice of termination for default, giving six reasons therefor.

Plaintiff appealed the termination to the asbca, which, in a detailed 27-page printed decision with findings, cited above, agreed to by six administrative judges, ruled on 13 separate issues relating to the six charges set forth in the termination notice, and concluded that, while plaintiff was entitled to prevail on some of those issues, those issues on which defendant prevailed were sufficient to sustain the termination for default. Further, liquidated damages in the sum of $8,272 were assessed against plaintiff. It is our responsibility to determine, under the Wunderlich Act standards, whether the asbca decision is correct as a matter of law and whether the board’s findings and conclusions are supported by substantial evidence and are final or whether they are arbitrary, capricious, or in bad faith and must be set aside. Plaintiffs burden here is substantial. It must convince the court that either there was no evidence to support the asbca’s findings or that the evidence contrary to those findings is so overwhelming or so detracts from that in support of the findings as to render the decision less than substantial on the record as a whole. Marley v. United States, 191 Ct. Cl. 205, 214, 423 F.2d 324, 329 (1970); Dean Constr. Co. v. United States, 188 Ct. Cl. 62, 67-68, 411 F.2d 1238, 1241 (1969). Plaintiff now contends that four findings [848]*848and conclusions of the asbca are unsupported by substantial evidence. We consider those findings and conclusions in the order in which they are named.

Removal of Asbestos Siding (Finding D)

It is undisputed that the contract required plaintiff to install new exterior siding over existing asbestos siding, that this did not prove feasible, that defendant agreed the old siding would have to be removed, that plaintiff agreed to do this without cost, that plaintiff did remove the old siding which took 2 or 3 weeks and then properly applied the new siding. Plaintiff now says that the delay was excusable and a contract extra ordered by defendant. The record does not show that plaintiff requested a time extension or compensation for extra work at the time. Before the asbca plaintiff sought a time extension for excusable delay but did not seek extra funds for the work. The board did not grant any time extension. It said: "Appellant has presented no evidence indicating to what extent, if any, its overall contract performance was delayed by the task of removing the old asbestos siding.” As we understand it, the plaintiff makes the same argument to the court that it made to the board which found plaintiff had not sustained its burden of proof on this matter. Plaintiff argues that it is self-evident the delay was excusable and a time extension should have been granted because the siding was early in the rehabilitation work called for by the contract and had to be completed before interior work began. This argument appears in the transcript. Argument is not fact. On this matter we must sustain the factfinder. No basis for reversal under Wunder-lich Act standards has been shown. Jefferson Constr. Co. v. United States, 177 Ct. Cl. 581, 368 F.2d 247 (1966).

Carpet Installation (Finding F)

The contract required plaintiff to install carpeting over the existing floor tile. Plaintiff was advised by his flooring subcontractor that the existing tile did not have a solid bond to the existing subfloor which was rotted. The subcontractor stated that for this reason he could not [849]*849guarantee his work. On March 15, 1978, plaintiff wrote the contract administrator about this problem and requested instructions before the work proceeded. The next day the contracting officer advised plaintiff that his failure to acquaint himself with the site conditions did not relieve him from properly estimating the difficulty or cost of successfully performing the work in a skillful and workmanlike manner and that he should go ahead and complete the contract pursuant to the specifications, as he had agreed to do. Five days later plaintiff advised his subcontractor to proceed. Plaintiff claims he was delayed 3 weeks, but there is no evidence that this is so. The asbca found:

7. Carpeting was to be one of the last items of work performed. (Citation omitted.) It would not be installed until the painting had been completed. Appellant was not ready to install carpeting until late April and that was when the carpeting was in fact installed so that there was no delay to appellant’s overall contract performance from difficulties arising from the condition of the flooring and subflooring. (Citation omitted.) [80-2 BCA at 72,168.]

The board denied plaintiffs claim for additional compensation for an extra involving the carpets and any delay attributable to their installation. Plaintiff did not replace any subflooring or perform any additional work. The carpet was installed prior to the revised deadline for completion of item 2. Thus, the board properly concluded that the evidence did not indicate that if plaintiff encountered any problems relating to the carpeting that they delayed completion of the overall project.

Warped Wardrobe Doors (Finding H)

The contract drawings provided for wardrobes in each room. These wardrobes were double cabinets, floor to ceiling in height. They were separated by a 2-foot space where there was a counter and a mirror above it. Each cabinet had double wood doors 1-inch thick. Defendant required plaintiff to eliminate the 2-foot space and to widen the cabinets and their doors. Defendant ignored warnings that this would probably cause the doors to warp, which they did. Plaintiff had recommended thicker doors. They [850]*850were later furnished by another contractor who did so as the representative of plaintiffs bonding company.

Defendant threatened to terminate plaintiffs contract for faulty workmanship.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brooks v. United States
Federal Claims, 2018
Urban v. United States
119 Fed. Cl. 57 (Federal Claims, 2014)
K-Con Building Systems, Inc. v. United States
115 Fed. Cl. 558 (Federal Claims, 2014)
Coastal Environmental Group, Inc. v. United States
114 Fed. Cl. 124 (Federal Claims, 2014)
Fireman's Fund Insurance v. United States
92 Fed. Cl. 598 (Federal Claims, 2010)
Lopez-Velazquez v. United States
85 Fed. Cl. 114 (Federal Claims, 2008)
BLR Group of America, Inc. v. United States
84 Fed. Cl. 634 (Federal Claims, 2008)
R.P. Wallace, Inc. v. United States
63 Fed. Cl. 402 (Federal Claims, 2004)
Morganti National, Inc. v. United States
49 Fed. Cl. 110 (Federal Claims, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
29 Cont. Cas. Fed. 82,195, 229 Ct. Cl. 846, 1982 U.S. Ct. Cl. LEXIS 49, 1982 WL 26558, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mel-williamson-inc-v-united-states-cc-1982.