Dean Construction Co., Inc. v. The United States

411 F.2d 1238, 188 Ct. Cl. 62, 1969 U.S. Ct. Cl. LEXIS 29
CourtUnited States Court of Claims
DecidedJune 20, 1969
Docket95-67
StatusPublished
Cited by22 cases

This text of 411 F.2d 1238 (Dean Construction Co., Inc. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dean Construction Co., Inc. v. The United States, 411 F.2d 1238, 188 Ct. Cl. 62, 1969 U.S. Ct. Cl. LEXIS 29 (cc 1969).

Opinion

COWEN, Chief Judge.

This case involves two causes of action. In the first, plaintiff alleges that defendant breached its contract with plaintiff by delaying plaintiff’s performance of a contract to build a new facility at the National Institutes of Health in Bethesda, Maryland. In the second cause of action, plaintiff alleges that the General Services Administration Board of Contract Appeals decision, which denied plaintiff’s request for additional time extensions beyond those granted by the contracting officer, is arbitrary and capricious and not supported by substantial evidence, and thus should not be accorded finality by this court in reviewing the contract dispute under the provisions of the Wunderlich Act, 41 U.S.C. §§ 321, 322 (1964). Plaintiff has made a motion for summary judgment as to both its causes of action. Defendant has moved for summary judgment in the second cause of action (under the Wunderlich Act), and opposes plaintiff’s motion for summary judgment on the breach claim. For the reasons set out in the opinion, we grant defendant’s motion for summary judgment on the second cause of action, and deny plaintiff’s motion for summary judgment in both causes of action.

On June 25, 1959, plaintiff entered into a contract with defendant, represented by the General Services Administration (G.S.A.), to construct new operating facilities for the National Institutes of Health. The contract contained a standard “Changes” clause which allowed for time extensions by the contracting officer. The contract also contained a liquidated damages provision, but did not contain a “Suspension of Work” provision. A contract price of $1,469,000 was set, and the time of performance was to be 510 calendar days from receipt of Notice to Proceed, which was given on July 14, 1959; the project was thus to be completed by December 5, 1960. However, defendant did not actually accept the project as substantially completed until January 30, 1962, an overrun of 421 days. When the 326 days allowed by the contracting officer as time extensions (to be discussed below) are taken into account, the plaintiff still overran the completion date by 95 days. Accordingly, liquidated damages for 95 days were assessed against plaintiff pursuant to the terms of the contract.

On July 9, 1962, plaintiff sent a letter to the contracting officer, setting forth 20 enumerated instances of defendant’s alleged disruptions and delays of the project. Each item was briefly described, and plaintiff’s previous correspondence and defendant’s action (or inaction) were noted. On the basis of the delays described, plaintiff claimed losses of $383,806.34, and sought an equitable adjustment of the contract price.

On October 25, 1962, plaintiff sent another letter to the contracting officer. In this letter plaintiff repeated the several items of delay that had been included in its letter of July 9, 1962, and, in addition, set forth 25 additional delays, making a total of 45 numbered items * of delay for which plaintiff claimed defendant was responsible. After each *1240 item was listed the number of days plaintiff contended were lost due to the delay. The total claimed days of delay amounted to over 5,600, or more than 15 years. However, the claim apparently included a considerable amount of overlap, and plaintiff requested a time extension of only 823 days, though it did not attribute any specific number of days’ delay to any separately described cause in arriving at this figure.

On April 23, 1963, the contracting officer formally notified plaintiff that its claim for money damages was being disallowed because the provisions of the contract precluded payment for the damages covered by plaintiff’s claims. The contracting officer stated that the matter of time extensions would be dealt with later. The denial by the contracting officer was timely appealed to the Board by plaintiff, but both plaintiff and defendant later moved the Board to dismiss the appeal for want of jurisdiction. Both parties agreed that the monetary damages claim was a breach claim (there being no “Suspension of Work” clause) that was not within the Board’s jurisdiction. The Board then dismissed the appeal for want of jurisdiction, General Services Board of Contract Appeals, Docket No. 1050, May 26, 1965.

Meanwhile, on December 16, 1963, the contracting officer responded to plaintiff’s request for time extensions. In a formal notice to plaintiff, the contracting officer allowed the following time extensions : 1

Calendar days
Item No. ■ 1 — Lack of drawings from elevator contractor...... 61
Item No. 6 — Delay in approval of mechanical and electrical equipment .................................. 60
Item No. 13- — Delay in approving movable metal partitions .... 139
Item No. Ik — Delay in approving metal case work............ 6 Items Nos. 3, 9, 18, 19, 20, 26, 27, 28, 29, 32, 33, 34, 35, 36, 37, 38, 39, 40, and 44............................ 60
Total 326

In the same letter, the contracting officer assessed liquidated damages of $11,-875 for 95 days. Attached to his decision was a formal statement of findings of fact, which indicated the basis for the time extensions granted for Items 1, 6, 13, and 14 (essentially delays for which the contracting officer felt the government was responsible), as well as the reasons for rejecting plaintiff’s other claims. The additional time extensions were denied either because the contracting officer felt plaintiff was not entitled to them, or because they overlapped with periods of time for which extensions had already been granted. The 60 days which were attributable to the last group of items shown above were allowed as an “equitable” time extension, although the contracting officer stated that it was not possible to pinpoint exactly how much time was due for each item.

The letter of the contracting officer served as the basis of appeal to the Board under the provisions of the contract. At the Board hearing, plaintiff contested the contracting officer’s disallowance of the time extensions requested and urged that liquidated damages were improp *1241 erly assessed. Although initially plaintiff claimed that some of the time extensions granted for certain items were insufficient, ultimately plaintiff put in issue only items for which no time extension had been allowed, or which were included in the group of items for which collectively performance time was extended for 60 days. The Board, in its case No. 1201, denied plaintiff any further time extensions. In its opinion issued November 26, 1965, the Board recited the deficiencies in plaintiff’s proof, and then denied plaintiff’s appeal on the grounds plaintiff had failed to discharge its burden of showing the extent, if any, of excusable delay beyond that allowed by the contracting officer. Plaintiff seeks review of the decision in this court.

I

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Delhur Industries, Inc. v. United States
95 Fed. Cl. 446 (Federal Claims, 2010)
PCL Construction Services, Inc. v. United States
53 Fed. Cl. 479 (Federal Claims, 2002)
Wilner v. United States
28 Fed. Cl. 783 (Federal Circuit, 1993)
Russell Corp. v. United States
35 Cont. Cas. Fed. 75,589 (Court of Claims, 1988)
Utley-James, Inc. v. United States
34 Cont. Cas. Fed. 75,478 (Court of Claims, 1988)
Iconco v. United States
32 Cont. Cas. Fed. 72,720 (Court of Claims, 1984)
Mel Williamson, Inc. v. United States
29 Cont. Cas. Fed. 82,195 (Court of Claims, 1982)
Lykes Bros. Steamship Co. v. General Dynamics Corp.
512 F. Supp. 1266 (D. Massachusetts, 1981)
Baltimore Contractors, Inc. v. United States
643 F.2d 729 (Court of Claims, 1981)
Turnkey Enterprises, Inc. v. United States
597 F.2d 750 (Court of Claims, 1979)
Whittaker Corporation v. The United States
443 F.2d 1373 (Court of Claims, 1971)
Marley v. United States
423 F.2d 324 (First Circuit, 1970)
Marley v. United States
423 F.2d 324 (Court of Claims, 1970)
Dean Construction Co. v. United States
193 Ct. Cl. 1104 (Court of Claims, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
411 F.2d 1238, 188 Ct. Cl. 62, 1969 U.S. Ct. Cl. LEXIS 29, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dean-construction-co-inc-v-the-united-states-cc-1969.