PCL Construction Services, Inc. v. United States

53 Fed. Cl. 479, 2002 U.S. Claims LEXIS 233, 2002 WL 2001282
CourtUnited States Court of Federal Claims
DecidedAugust 28, 2002
DocketNo. 95-666C, 96-442C
StatusPublished
Cited by12 cases

This text of 53 Fed. Cl. 479 (PCL Construction Services, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
PCL Construction Services, Inc. v. United States, 53 Fed. Cl. 479, 2002 U.S. Claims LEXIS 233, 2002 WL 2001282 (uscfc 2002).

Opinion

OPINION

HORN, Judge.

FINDINGS OF FACT

The above captioned case concerns a contract between the government and the plaintiff, PCL Construction Services, Inc. (PCL), for the construction of a Visitor’s Center and Parking Structure at the Hoover Dam. This opinion addresses two of three remaining issues, PCL’s entitlement to amounts retained by the government for liquidated damages and PCL’s entitlement for amounts retained by the government for uncompleted punch list items. The court is awaiting the conclusion of settlement negotiations regarding the other remaining issue in the case, the defendant’s counterclaim regarding an allegedly defective turntable. The parties continue to inform the court that settlement discussions are proceeding well and that settlement remains likely on the turntable issue. Although it was anticipated that this opinion would be issued simultaneously with resolution of the turntable issue, and, therefore, resolve all the issues in the cases, the court has decided to release this opinion while the parties continue to engage in settlement of the remaining issue in anticipation of further encouraging settlement.

PCL filed two complaints (Case Nos. 95-666C and 96-442Q against the United States, arising from the alleged actions of the United Stated Bureau of Reclamation (USBR). PCL seeks recovery of over $31,000,000.00 under “breach of contract” and “illegal contract” theories in Case No. 95-666C, and over $1,300,000.00 million under “breach of contract,” “improper termination for default,” and “illegal assessment of liquidated damages” in Case No. 96-442C. On October 4,1995, PCL filed a “preliminary complaint” premised upon a contracting officer’s final decision denying PCL’s July 27, 1995 certified claim for $31,040,071.00 based upon alleged breach of contract and illegality of contract. This complaint was assigned Case No. 95-666C. This complaint was amended on April 1, 1996, following discovery. The plaintiffs counts in Case No. 95-666C assert breach of contract premised upon fraud in the inducement and misrepresentation by the government (Counts I, II and IV), breach of contract premised upon superior knowledge by the government (Counts III and VI), breach of contract arising from a breach of warranty by the government (Count V), breach of contract stemming from hindrance and delay by the government (Count VII), cardinal change (Count VIII), illegal contract (Count IX), and Antideficiency Act violation (Count X). Shortly after the amended complaint in Case No. 95-666C was filed, PCL filed a second complaint on July 23, 1996, which was assigned Case No. 96-442C. The complaint in this second action was premised upon (1) a contracting officer’s final decision denying PCL’s November 22, 1995 certified claim for $1,351,838.00 seeking monies retained by USBR, (2) a March 11, 1996 letter from the contracting officer terminating PCL for default based upon an alleged breach of the contract by PCL, and (3) a March 26,1996 letter from the contracting officer assessing liquidated damages against PCL in the amount of $1,285,800.00.

This court granted summary judgment in the government’s favor on “Count X of Case No. 95-666C, PCL’s claim that alleged the contract was illegal due to violations of 31 U.S.C. §§ 1341, 1342, and 1502, statutes which are directed at precluding the award of government contracts in excess of, or in advance of, appropriations and forbid the acceptance of voluntary services. See PCL Constr. Servs., Inc. v. United States, 41 Fed.Cl. 242, 264 (1998). Trial was held on the remaining claims. Construction of the Parking Structure and Visitor Center at the Hoover Dam was complex and difficult. The facts of this case, and the problems encountered by the parties during construction of the project, were fully detailed in this court’s lengthy post-trial opinion, PCL Construction Services, Inc. v. United States, 47 Fed.Cl. 745 (2000), and those facts are incorporated into this opinion. Only a brief recitation of the most pertinent facts to the present motion will be repeated here.

[482]*482The government awarded PCL the contract for the construction of the Visitor Center and Parking Structure on September 5, 1991. The government issued a notice to proceed to PCL on October 21, 1991. The scheduled completion date for the Parking Structure was February 15, 1992. The scheduled completion date for the Visitor Center was July 15, 1993. In April, 1994, approximately two and one-half years after the government issued a notice to proceed to PCL, plaintiff submitted an uncertified Request for Equitable Adjustment (REA), claiming entitlement to recover $23,229,471.00 and to a schedule extension of 363 days because of delays and disruptions arising from alleged defective contract drawings and specifications, differing site conditions, time required for resolution of Requests for Information (RFI), and time impacts due to contract changes. On February 24, 1995, USBR notified PCL that it had evaluated the REA and requested that PCL participate in a fact-finding session regarding preparation of an as-built schedule in order to agree upon responsibility for critical delays to the project. PCL interpreted this as a denial of the REA in its entirety.

In a letter dated March 14, 1995, the contracting officer státed that an assessment of liquidated damages would be made against PCL when “responsibilities for time associated with delays are made.” The contracting officer also stated that liquidated damages would then be assessed against PCL for those delays which are “not found to be the responsibility of the Government____” Less than three months later, on June 9,1995, the contracting officer issued to PCL a Certificate of Substantial Completion certifying that the contract was substantially complete as of May 11, 1995. PCL was notified that the project was considered to be substantially complete except for the results of the joint inspection on May 12, 1995, and the “deficient items noted and listed during the [previous] joint inspections.” The USBR began using the Visitor Center and Parking Structure on May 12,1995 and has continued to do so. The USBR opened the facilities for tourism on June 21,1995.

Despite not having completed all of the previously listed deficiencies, PCL requested the final acceptance inspection to be held on August 25, 1995. PCL’s request was contrary to the terms of the contract, which required PCL to request final acceptance only when all contract work was considered to be complete. Therefore, USBR rejected PCL’s request. PCL withdrew its request for a final acceptance inspection and outlined a procedure to address the remaining deficiency items, and requested a consolidated deficiency listing. USBR provided PCL with a consolidated deficiency listing and concurred with PCL’s suggested procedure for resolving the deficiency items. USBR also reminded PCL of its obligation to provide a written certification that the contract work had been completed in accordance with contract section 01700 1.10.A. PCL never provided the required written certification.

PCL and some of its subcontractors remained on site performing under the contract until November, 1995. At trial, government witnesses testified that most of the items on the deficiency lists in Exhibit 2147 remained outstanding to the day of the trial.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

East Coast Repair & Fabrication, LLC v. United States
199 F. Supp. 3d 1006 (E.D. Virginia, 2016)
Structural Concepts, Inc. v. United States
103 Fed. Cl. 84 (Federal Claims, 2012)
Wayne Knorr, Inc. v. Department of Transportation
973 A.2d 1061 (Commonwealth Court of Pennsylvania, 2009)
PCL Construction Services, Inc. v. United States
84 Fed. Cl. 601 (Federal Claims, 2008)
Cumberland Casualty & Surety Co. v. United States
82 Fed. Cl. 500 (Federal Claims, 2008)
Bell BCI Co. v. United States
72 Fed. Cl. 164 (Federal Claims, 2006)
A. G. Cullen Construction, Inc. v. State System of Higher Education
898 A.2d 1145 (Commonwealth Court of Pennsylvania, 2006)
George Sollitt Construction Co. v. United States
64 Fed. Cl. 229 (Federal Claims, 2005)
R.P. Wallace, Inc. v. United States
63 Fed. Cl. 402 (Federal Claims, 2004)
PCL Construction Services, Inc. v. United States
96 F. App'x 672 (Federal Circuit, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
53 Fed. Cl. 479, 2002 U.S. Claims LEXIS 233, 2002 WL 2001282, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pcl-construction-services-inc-v-united-states-uscfc-2002.