PCL Construction Services, Inc. v. United States

96 F. App'x 672
CourtCourt of Appeals for the Federal Circuit
DecidedApril 7, 2004
DocketNo. 03-5060
StatusPublished
Cited by8 cases

This text of 96 F. App'x 672 (PCL Construction Services, Inc. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
PCL Construction Services, Inc. v. United States, 96 F. App'x 672 (Fed. Cir. 2004).

Opinion

DYK, Circuit Judge.

Appellant PCL Construction Services, Inc. (“PCL”) alleges that, by providing defective construction drawings, the United States Bureau of Reclamation (“USBR”) breached PCL’s contract to build a parking structure and a visitor’s center at the site of the Hoover Dam. After trial, the Court of Federal Claims rejected PCL’s claim for breach of contract damages. PCL Constr. Servs., Inc. v. United States, 47 Fed.Cl. 745 (2000) (“PCL II”). PCL further argues that the contract was illegally funded and that it can recover on a theory of quantum meruit. The Court of Federal Claims also rejected this theory, on summary judgment. PCL Constr. Servs., Inc. v. United States, 41 Fed.Cl. 242 (1998) (“PCL I”). We affirm.

BACKGROUND

On September 5, 1991, the USBR awarded a contract to PCL for the construction of a visitor center and parking structure at the site of the Hoover Dam. The contract was a firm fixed-price contract with a price of $38,854,000, but it was to be funded through annual Congressional appropriations over the term of the contract. The contract specified, among other things, that the parking structure was to be built in a box canyon located off of the main canyon in which the Hoover Dam stands. During the construction of the Hoover Dam, the box canyon had been partially filled and leveled with boulders, rock fragments, and other debris. As a result, although the contours of the rock fill were known, the specific contours of the underlying canyon surface were unknown.

The USBR had previously entered into a contract under which The Promontory Partnership (“Promontory”) designed the visitor center and parking structure. Pursuant to this contract, Promontory had prepared the drawings for the PCL contract. The USBR provided 465 such drawings, among which were several drawings depicting the rock fill contours and estimated location of the underlying canyon surface. The drawings also depicted the locations of column footings, which were designed to support the parking structure and had to be founded upon the “competent rock” of the underlying canyon surface. These drawings proved to be inaccurate, and the design of some of the parking structure supports had to be revised when the actual contours of the surface of the canyon were ascertained after construction began. PCL argues that these inaccuracies were design defects for which the USBR is responsible. Only the alleged design defects in the foundation drawings for a portion of the parking structure are at issue in this appeal.

The contract required PCL to complete construction of the parking structure by February 15, 1994, but the structure was not deemed substantially complete until May 12, 1995, when the USBR began using it and the visitor center. PCL maintained that this delay was caused by the USBR; that the delay disrupted PCL’s performance of the contract; and that the additional costs PCL incurred as a result of the delay and disruption were recoverable on a breach of contract theory. PCL filed a breach of contract claim in the amount of $31,040,071 with the contracting [674]*674officer on July 25, 1995. The USBR subsequently began withholding funds from PCL, stating that “withholding of funds is necessary for the protection of the Government’s interest in accrued liquidated damages, outstanding required submittals, and credits due the Government for changes and/or reductions in work.” PCL II, 47 Fed.Cl. at 781. The contracting officer denied PCL’s breach of contract claim on September 21, 1995. PCL stopped performing work related to the contract on November 22, 1995, and the USBR assessed liquidated damages and terminated the contract for default on March 6, 1996.

On October 4, 1995, before the default termination, PCL filed a complaint against the USBR in the Court of Federal Claims, alleging breach of contract and asserting also that it was entitled to recover on a theory of quantum meruit because the contract had been illegally funded in violation of the Anti-Deficiency Act, 31 U.S.C. §§ 1341-42 (2000).1 PCL filed a second complaint on July 23,1996, after the termination, alleging that the USBR had terminated the contract and assessed liquidated damages improperly. The Court of Federal Claims consolidated the two cases and, on June 26, 1998, granted summary judgment in favor of the USBR on PCL’s claim that the incremental funding of the contract was illegal, holding that 43 U.S.C. § 388 authorized such funding for the project.2 PCL I, 41 Fed.Cl. at 257.

The issues of liability and quantum as to PCL’s remaining claims were bifurcated for trial, and, after a fifty-one day trial, the Court of Federal Claims held that (1) the USBR had not breached the contract and (2) it had properly terminated the contract for default, id. at 812. On August 28, 2002, the court held that the USBR was not entitled to liquidated damages and that PCL was entitled to the funds that the USBR had retained. PCL Constr. Servs., Inc. v. United States, 53 Fed.Cl. 479, 493 (2002) (“PCL III”). The court entered judgment in both of the consolidated cases on December 30, 2002. PCL timely appealed, and we have jurisdiction pursuant to 28 U.S.C. § 1295(a)(3).3

DISCUSSION

We review legal decisions by the Court of Federal Claims without deference, and we review the court’s factual findings for clear error. Ferreira v. United States, 350 F.3d 1318, 1324 (Fed.Cir.2003).

I

A

The appellant contends that, by providing site and foundation drawings that in-[675]*675eluded substantial errors, the USBR breached its obligation under the contract to provide accurate drawings. However, the Court of Federal Claims noted that the contract included provisions notifying PCL that the drawings might include errors. Section 01030, paragraph 1.02(B) of the contract provided:

The drawings and specifications are based upon such data which could reasonably be secured and contain design information which is customarily provided for the construction process. Extreme accuracy is not guaranteed, nor is perfection in these documents implied .... Contractor shall expect that there may be some omissions, discrepancies, and conflicts within the design documents and with the actual field and construction conditions encountered. The contract therefore requires significant supervision and engineering efforts by the constructors in order to help resolve such issues when they arise.

(J.A. at A3694.) The court further noted that the contract stated that the “[d]ata and information shown and indicated [on maps and drawings of existing topography] are as accurate as could be obtained but are not guaranteed.” PCL II, 47 Fed.Cl. at 790 (quoting J.A. at A3703).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harry Pepper and Associates, Inc.
Armed Services Board of Contract Appeals, 2021
East Coast Repair & Fabrication, LLC v. United States
199 F. Supp. 3d 1006 (E.D. Virginia, 2016)
Wayne Knorr, Inc. v. Department of Transportation
973 A.2d 1061 (Commonwealth Court of Pennsylvania, 2009)
PCL Construction Services, Inc. v. United States
84 Fed. Cl. 601 (Federal Claims, 2008)
A. G. Cullen Construction, Inc. v. State System of Higher Education
898 A.2d 1145 (Commonwealth Court of Pennsylvania, 2006)
George Sollitt Construction Co. v. United States
64 Fed. Cl. 229 (Federal Claims, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
96 F. App'x 672, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pcl-construction-services-inc-v-united-states-cafc-2004.