Vulcan Rail & Construction Co. v. United States

158 Ct. Cl. 234, 1962 U.S. Ct. Cl. LEXIS 181, 1962 WL 9257
CourtUnited States Court of Claims
DecidedJuly 18, 1962
DocketNo. 345-58
StatusPublished
Cited by9 cases

This text of 158 Ct. Cl. 234 (Vulcan Rail & Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vulcan Rail & Construction Co. v. United States, 158 Ct. Cl. 234, 1962 U.S. Ct. Cl. LEXIS 181, 1962 WL 9257 (cc 1962).

Opinion

Dureee, Judge,

delivered the opinion of the court:

In this action plaintiff seeks $170,675.75 for damages alleged to have resulted from Government delays of plaintiff’s performance of a certain Government contract.

On June 12,1953, plaintiff submitted a bid, in response to an invitation to bid from the Office of the District Engineer, Philadelphia District, U.S. Army Corps of Engineers, for the manufacture of steel towers designed to support water tanks of three sizes. After a survey made by Army civilian inspectors to determine whether plaintiff was qualified to perform that work, on June 29, 1953, plaintiff was notified that its bid was accepted for 58 of the 10,500 gallon tank towers, at a unit cost of $1,042, and 244 of the 21,000 gallon tank towers at a unit cost of $2,126. Subsequently the number of larger towers under contract was reduced to 169. The total contract price was $419,730.

On July 1, 1953, plaintiff, by letter, acknowledged the notice of award of the contract. In addition to the acknowl-[236]*236edgement of the notice of award, that letter contained the following paragraph:

It is necessary that we have 6 additional sets of drawings and would appreciate receiving these as soon as possible. Wo might add that the one set covering the 21,000 gal. tanks received with your inquiry were very poor prints and were hardly legible.

Plaintiff alleges that Government delay in furnishing sufficiently legible drawings for the 21,000 gallon tank towers was a primary cause of the protraction of the period required to complete its performance of the contract from 262 days to 518 days, thus occasioning the additional costs for which plaintiff currently seeks damages.

Actually, it was only the illegibility of sheet number 2 of the drawings for the large tank towers that plaintiff contends caused the delays in production. Among other things this sheet contained the specifications for the materials required under the contract for fabrication of the towers. The alleged illegibility did not however prevent plaintiff from ordering the steel necessary for work on the contract on July 9, 1953. This order was subsequently revised on July 22, but only to accord with a reduction in the number of towers covered by the contract.

On July 15, 1953, plaintiff wrote to the Corps of Engineers in New York advising that office that “we found the following minor discrepancies and omissions in the drawings submitted to us.” The letter then enumerated specific defects and requested clarification accordingly. On July 30, 1953, plaintiff was advised by letter from the New York office of the Corps of Engineers that the clarifications proposed by plaintiff had been accepted in their entirety.

Again, in a letter dated August 20,1953, plaintiff reminded defendant that in its letter dated July 1, 1953, it had requested six copies of the drawings for both types of towers, and stated that it had received copies of the drawings only for the large towers. Plaintiff requested that the defendant look into the matter and send the other copies at the earliest moment. We deem it worthy of note that the letter acknowledges the receipt of copies of the drawings for the large towers and makes no reference to their alleged illegibility. [237]*237This is especially important inasmuch as it is the purported illegibility of the drawings for the large towers that plaintiff contends caused the delay in performance of the contract.

In a letter dated September 3, 1953, the Office of District Engineer, New York District, sent plaintiff new drawings to incorporate the changes that had been proposed earlier by plaintiff and accepted by defendant. Plaintiff did not have these drawings in its plant for more than a few days, however, inasmuch as they were recalled to Washington by the Government in order to make additional copies. The copies were not returned to plaintiff until sent by the Corps of Engineers with a letter dated January 6,1954.

We are not convinced that plaintiff has sustained its burden of proving actual delays directly attribuable to the events described above. Initially, the drawings were sufficiently clear for plaintiff to tender firm bids involving substantial sums of money on the contract. While this is certainly not dispositive, we believe it relevant to the matter before us. Moreover, the fact that plaintiff, in its letter of July 15,1953, evinced sufficient comprehension of the drawings to point out discrepancies and minor errors therein for the Government’s clarification, argues against its contention that the drawings were so illegible as to impede production. The Government’s letter of July 30, 1953, accepting plaintiff’s proposed clarification should have completed plaintiff’s coni’ prehension of the drawings. Were this not sufficient, the fact that plaintiff did receive clear drawings, revised to incorporate its proposed clarifications, under the Government’s covering letter of September 3, 1953, detracts further from plaintiff’s assertions regarding the causes of delay. While it is true that these clear, complete drawings were in plaintiff’s possession for only a few days, the fact that plaintiff had them for study at that time, to supplement the previous correspondence and earlier drawings, should have clarifiéd and completed its understanding of them. We find this interpretation of the fact buttressed by additional facts indicating that despite the alleged illegibility of the drawings, plaintiff was able to order steel for the contract only nine days after it acknowledged receipt of the notice of award; plaintiff had been able to commence work fabricating the steel when [238]*238it was delivered; and plaintiff had been able to fabricate a substantial portion of the components of the smaller towers and some of those for the larger towers by the end of 1953. We find damaging to plaintiff’s position the fact that it had been able to erect pre-production models of both the large and medium towers by November 10,1953, at which time the major portion of plaintiff’s order of steel for the contract had either just been delivered or remained undelivered. For these reasons we conclude that plaintiff’s performance was not delayed by the alleged illegibility of the drawings.

Plaintiff attempts an additional argument alleging delay due to its anticipation of possible revisions of the drawings to incorporate structural changes in the towers during the time that the drawings were in the Government’s possession. The bulk of the evidence on which this allegation of possible revision is based, is found in inter-office communications between the various engineers’ offices, which were not available to plaintiff until it gained access to these documents by recourse to discovery procedures at the time this case went to trial. Obviously, due to the chronological sequence, plaintiff cannot contend to have placed reliance on these communications during its performance of the contract inasmuch as it was unaware at that time of the existence of these interoffice communications. While the word “revision” does appear occasionally in the correspondence, we find that it was used to connote revisions of the original drawings to incorporate the clarifications suggested by plaintiff in its letter of July 15, 1953. Finally on this point, the contract contained a “Changes” clause whereby the Government would have been obligated to make equitable adjustment for any revisions of contract specifications initiated by the Government in the course of plaintiff’s performance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wilner v. United States
28 Fed. Cl. 783 (Federal Circuit, 1993)
Delco Electronics Corp. v. United States
35 Cont. Cas. Fed. 75,679 (Court of Claims, 1989)
Dean Construction Co., Inc. v. The United States
411 F.2d 1238 (Court of Claims, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
158 Ct. Cl. 234, 1962 U.S. Ct. Cl. LEXIS 181, 1962 WL 9257, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vulcan-rail-construction-co-v-united-states-cc-1962.