Jefferson Construction Company v. The United States

368 F.2d 247, 177 Ct. Cl. 581, 1966 U.S. Ct. Cl. LEXIS 100
CourtUnited States Court of Claims
DecidedNovember 10, 1966
Docket218-64
StatusPublished
Cited by21 cases

This text of 368 F.2d 247 (Jefferson Construction Company v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jefferson Construction Company v. The United States, 368 F.2d 247, 177 Ct. Cl. 581, 1966 U.S. Ct. Cl. LEXIS 100 (cc 1966).

Opinion

OPINION

PER CURIAM:

This case was referred to Trial Commissioner Roald A. Hogenson with directions to make his recommendation for conclusions of law on plaintiff’s motion and defendant’s cross-motion for summary judgment. The commissioner has done so in an opinion filed February 2i, 1966. Plaintiff sought review of the commissioner’s opinion and recommendation for conclusions of law to which defendailt filed a response and the case was submitted to the court on oral argument *249 by counsel. Since the court is in agreement with the opinion and recommendation of the trial commissioner with a minor modification, as hereinafter set forth, it hereby adopts the same as modified as the basis for its judgment in this case. The court emphasizes that in reviewing a trial commissioner’s opinion passing upon a factual determination of a Board of Contract Appeals (or similar contractual agency) the court will not, except in exceptional circumstances, consider points and record references which should have been presented to the trial commissioner but were not. Therefore, without prejudice to the administrative payment of the amount awarded to plaintiff by the Board, plaintiff’s motion for summary judgment is denied, defendant’s cross-motion for summary judgment is granted and plaintiff’s petition is dismissed.

OPINION OP COMMISSIONER *

HOGENSON, Commissioner:

This is a suit on a bid contract awarded by the Department of the Air Force to plaintiff, dated June 30, 1960, designated AF 19(617)-1888, pursuant to which plaintiff, a Massachusetts corporation engaged in the construction business, undertook for the contract price of $343,000 to furnish all labor, equipment, and materials and to perform all work required to remodel and rehabilitate 10 airmen dormitories at Westover Air Force Base, Massachusetts, in strict accordance with the provisions, specifications, schedules, drawings, and conditions of the contract.

This case is before the court on cross-motions for summary judgment, with supporting briefs, 1 based solely on the record of proceedings (filed herein) of the Armed Services Board of Contract Appeals (ASBCA No. 8247) on plaintiff’s appeal from the adverse decision of defendant’s contracting officer on plaintiff’s claim. After hearing the testimony of witnesses for the parties, receiving in evidence proffered exhibits, and considering the briefs of the parties, the Board in a written decision, dated March 31, 1964, allowed a minor part but otherwise denied plaintiff’s appeal, as hereinafter related.

The contract required plaintiff to commence work on July 11, 1960, and to complete on November 2, 1960. The contract work was not completed until January 23, 1961. Plaintiff was allowed extensions of time and was not assessed liquidated damages for late performance.

Count One of plaintiff’s petition herein alleges that defendant breached the contract :

* * * by its failure to make the job site available to petitioner, by its failure to vacate the dormitories on or before the date for commencement of work, by its unreasonable delay in ordering changes in the work, by its unreasonable delay in issuing clarifications of contract documents, by its unreasonable delay in issuing change orders, by its unreasonable delay in approving samples of materials submitted to respondent by petitioner for approval, by respondent’s interruption of the orderly sequence of petitioner’s work and by respondent’s failure to occupy the dormitories and accept the work in a timely fashion.

and that because of such breaches, plaintiff was unable to complete the contract work until January 23, 1961, and that such breaches caused plaintiff to incur extra costs and damages in the sum of $32,590.

Count Two of the petition alleges with respect to the same contract performance that defendant unreasonably delayed plaintiff in the following respects:

* * * making the job site available, vacating the dormitories, order *250 ing changes in the work, issuing clarifications of the contract documents, issuing change orders, approving samples of materials, and occupying the building. Petitioner says that the cumulative effect of these delays interrupted the orderly sequence of its work and caused petitioner to incur substantial costs.

Count Two further alleges that plaintiff gave timely notice of all delays to the contracting officer, that the contracting officer extended the contract completion date until January 23, 1961, but by decision, dated April 30, 1962, denied plaintiff’s claim for extra costs as a result of the delays in the sum of $32,590, that plaintiff took a timely appeal to the Armed Services Board of Contract Appeals, and that such Board by decision, dated March 31,1964, ruled that plaintiff was entitled to an allowance for unreasonable delay because of defendant’s failure to make the buildings available on July 11, 1960, but otherwise denied plaintiff’s claim. Plaintiff’s petition alleges in Count Two that the Board’s decision is not supported by substantial evidence and is erroneous as a matter of law. Regarding the assertion of lack of substantial evidence, the petition wholly fails to allege any particulars in support thereof.

In addition to standard Changes and Disputes articles, the contract contained a Suspension of Work article as follows:

SP 1-12 Suspension of work

The Contracting Officer may order the Contractor to suspend all or any part of the work for such period of time as may be determined by him to be necessary or desirable for the convenience of the Government. Unless such suspension unreasonably delays the progress of the work and causes additional expense or loss to the Contractor, no increase in contract price will be allowed. In the case of suspension of all or any part of the work for an unreasonable length of time, causing additional expense or loss, not due to the fault or negligence of the Contractor, the Contracting Officer shall make an equitable adjustment in the contract price and modify the contract accordingly.
An equitable extension of time for the completion of the work in the event of any such suspension will be allowed the Contractor: Provided, however, That the suspension was not due to the fault or negligence of the Contractor.

Before the Board, both parties presented their evidence and contentions in their briefs, covering every facet of plaintiff’s delay-damage claim asserted in either count of the petition herein, and the Board rendered its decision on the merits, all on the theory that an equitable adjustment in the contract price would be made if it were established that actionable delays by the defendant caused increased costs in plaintiff’s contract performance. No other theory of entitlement to recovery was presented to the Board.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Safety Training Systems, Inc.
Armed Services Board of Contract Appeals, 2014
Spehr v. United States
49 F. App'x 303 (Federal Circuit, 2002)
Round Place, Inc. v. United States
39 Cont. Cas. Fed. 76,699 (Federal Claims, 1994)
Darwin Construction Co., Inc. v. United States
811 F.2d 593 (Federal Circuit, 1987)
Gevyn Construction Corp. v. United States
33 Cont. Cas. Fed. 74,851 (Court of Claims, 1986)
Quality Environment Systems, Inc. v. United States
32 Cont. Cas. Fed. 73,267 (Court of Claims, 1985)
Roflan Co. v. United States
32 Cont. Cas. Fed. 73,207 (Court of Claims, 1985)
Entwistle Co. v. United States
32 Cont. Cas. Fed. 72,807 (Court of Claims, 1984)
Mel Williamson, Inc. v. United States
29 Cont. Cas. Fed. 82,195 (Court of Claims, 1982)
Fruehauf Corp. v. United States
587 F.2d 486 (Court of Claims, 1978)
Jet Construction Co. v. United States
531 F.2d 538 (Court of Claims, 1976)
Merritt-Chapman & Scott Corp. v. United States
528 F.2d 1392 (Court of Claims, 1976)
ITT Arctic Services, Inc. v. United States
524 F.2d 680 (Court of Claims, 1975)
Arundel Corp. v. United States
515 F.2d 1116 (Court of Claims, 1975)
Gross v. United States
505 F.2d 1271 (Court of Claims, 1974)
Teitelbaum v. United States
458 F.2d 72 (Court of Claims, 1972)
Law v. United States
195 Ct. Cl. 370 (Court of Claims, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
368 F.2d 247, 177 Ct. Cl. 581, 1966 U.S. Ct. Cl. LEXIS 100, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jefferson-construction-company-v-the-united-states-cc-1966.