Quality Environment Systems, Inc. v. United States

32 Cont. Cas. Fed. 73,267, 7 Cl. Ct. 428, 1985 U.S. Claims LEXIS 1045
CourtUnited States Court of Claims
DecidedFebruary 21, 1985
DocketNo. 600-80C
StatusPublished
Cited by3 cases

This text of 32 Cont. Cas. Fed. 73,267 (Quality Environment Systems, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Quality Environment Systems, Inc. v. United States, 32 Cont. Cas. Fed. 73,267, 7 Cl. Ct. 428, 1985 U.S. Claims LEXIS 1045 (cc 1985).

Opinion

OPINION

MEROW, Judge.

This case comes before the court on cross-motions for summary judgment. Plaintiff seeks Wunderlich Act review, 41 U.S.C. § 321 et seq., of an Armed Services Board of Contract Appeals (ASBCA) decision, QES, Inc., ASBCA No. 22178, 78-2 BCA ¶ 13,512 (1978). Reply briefs have been filed and oral argument has been held.

Facts

The dispute involves a 1976 energy conservation system design contract between the Savannah District of the Corps of Engineers (District) and Quality Environment Systems, Inc. (QES). The contract was divided into phases. Phase I, the preliminary design, was to be submitted 109 days after contracting. Defendant then had 9 months to instruct QES whether to proceed with Phase II. The design was timely submitted in June 1976. In July 1976, at an on-board review, plaintiff met and discussed the plan with defendant. In September 1976 two major changes, P001 and P002, were made in the design. In October 1976 plaintiff requested a second design conference and a resume of negotiations for the changes. Plaintiff received no response and, in November 1976, made a [430]*430second submission. A meeting was held in December 1976 concerning the second submission. Subsequently, plaintiff submitted two additional design plans. In separate meetings, plaintiff was informed that each submission was deficient in some manner. In June 1977 plaintiff was default terminated.

Plaintiff appealed the default termination to the ASBCA. Plaintiff argued that its design satisfied the contract requirements, that, alternatively, defendant did not cooperate with plaintiffs efforts to satisfy government requirements, and that review of plaintiff’s submissions was improper because the review panels did not include representatives of the user agency. The board determined plaintiff was properly default terminated. QES, Inc., ASBCA No. 22178, 78-2 BCA ¶ 13,512 (1978).

In the present action, plaintiff seeks review of the board decision and seeks remand to the board for additional findings of fact on an issue of bad faith. In its initial summary judgment motion plaintiff alleges that the board’s interpretation of the contractual provision regarding the availability of on-board review was not supported by substantial evidence. In a later submission, plaintiff largely abandons this argument. Instead, plaintiff contends that conflicting instructions rendered its performance impossible and the board should have so ruled. Plaintiff also disputes the validity of the board’s ruling on the required percentage of completion of the design. Finally, plaintiff asserts the board made insufficient findings of fact concerning bad faith allegations. Defendant argues that plaintiff’s allegations are insufficient to withstand Wunderlich Act scrutiny and that plaintiff has failed to exhaust its administrative remedies.

For the reasons stated below it is concluded that, while the board’s decision as to the existence of a default is supported by substantial evidence, the case is remanded to the ASBCA for additional consideration of plaintiff’s bad faith allegations.

Discussion

Under the applicable law, the board’s decision shall be final and conclusive unless the same is fraudulent, capricious or arbitrary, or so grossly erroneous as to imply bad faith, or is not supported by substantial evidence. 41 U.S.C. § 321. Substantial evidence is evidence which could convince an unprejudiced mind of the truth of the facts to which the evidence is directed. Koppers Co. v. United States, 405 F.2d 554, 558, 186 Ct.Cl. 142, 149 (1968).

The plaintiff has the burden to specify the facts and circumstances contained in the board’s record which render the board’s decision lacking in finality. Jet Construction Co. v. United States, 531 F.2d 538, 540, 209 Ct.Cl. 200, 204 (1976); Jefferson Construction Co. v. United States, 368 F.2d 247, 252, 177 Ct.Cl. 581, 589 (1966). With the exception of plaintiff’s allegations regarding bad faith and the so-called “on-board review” of its submissions, plaintiff has not alleged board error with sufficient specificity. Plaintiff merely references the board’s findings. It does not allege or establish specific error. As such, plaintiff fails to meet its burden to maintain a Wunderlich Act review suit.

Plaintiff has also failed to establish a valid claim involving the on-board review requirements. In its initial summary judgment motion, plaintiff engages in a substantial discussion of the board’s conclusions concerning the required on-board review. Plaintiff contends the on-board review was deficient in that the contract required representatives of the using agency, Fort Benning, as well as representatives of the agency in charge of contract performance, Savannah District, should have been present at the meeting.

Although “the interpretation of a contract is a question of law to be decided by the court, * * * if the interpretation of a contract by an agency or board on a question of law is considered to be correct by the court, the court may approve or adopt the decision of the agency or the [431]*431board on the question.” B.D. Click Co. v. United States, 614 F.2d 748, 752, 222 Ct.Cl. 290, 297-98 (1980). The board, applying contract interpretation principles, found that on-board review required “a joint review of the design submitted by the contractor and government personnel who were cognizant of the matter and in a position to comment and give instruction authoritatively.” QES, Inc., ASBCA No. 22178, 78-2 BCA ¶ 13,512, 66,217 (1978). The board concluded that meetings between plaintiff's and District representatives after the first three submissions constituted compliance with the on-board review requirement. 78-2 BCA at 66,220-21. No valid reason has been presented to overturn the board’s reasoned conclusion and it is considered correct.

Bad Faith

Plaintiff maintains the board should have made specific factual findings on the issue of whether bad faith influenced the contracting officer’s decision to default terminate plaintiff. The board stated only in a conclusionary fashion that it considered the bad faith allegations where relevant to contractual relief. 78-2 BCA at 66,222. However, no specific findings were made. In its brief, plaintiff sets forth a number of events which may indicate bad faith. These include a joint boat purchase with the military branch chief, at the chief’s request. The boat’s title was in the branch chief’s name only. In addition, there are allegations concerning requests for plaintiff to invest in the branch chief’s massage parlor or to use the branch chief’s printing company.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SMS Data Products Group, Inc. v. United States
36 Cont. Cas. Fed. 75,820 (Court of Claims, 1990)
Darwin Construction Co., Inc. v. United States
811 F.2d 593 (Federal Circuit, 1987)
Ainsley v. United States
8 Cl. Ct. 394 (Court of Claims, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
32 Cont. Cas. Fed. 73,267, 7 Cl. Ct. 428, 1985 U.S. Claims LEXIS 1045, Counsel Stack Legal Research, https://law.counselstack.com/opinion/quality-environment-systems-inc-v-united-states-cc-1985.