John McShain, Inc. v. United States

412 F.2d 1281, 188 Ct. Cl. 830, 1969 U.S. Ct. Cl. LEXIS 49
United States Court of Claims·Decided July 16, 1969·No. 173-63·Published·Cited by 19 cases

Opinion

OPINION

PER CURIAM:

This case was referred to Trial Commissioner Lloyd Fletcher with directions to make findings of fact and recommendation for conclusions of law under the order of reference and Rule 57(a). The commissioner has done so in an opinion and report filed on September 4, 1968. Exceptions to the commissioner’s opinion, findings and recommended conclusion of law were taken by both parties and the case has been submitted to the court on oral argument of counsel and the briefs of the parties. Since the court agrees with the commissioner’s opinion, findings, and recommended conclusion of law, as hereinafter set forth, it hereby adopts the same as the basis for its judgment in this case. Therefore, judgment is entered for plaintiff in the sum of $117,600.06.

OPINION OF COMMISSIONER

FLETCHER, Commissioner:

The plaintiff, John MeShain, Inc., seeks to recover damages in its own behalf and in behalf of several of its subcontractors for an alleged breach of warranty by defendant in connection with a construction contract for an extension of the State Department Building entered into between the plaintiff and defendant, acting through the General Services Administration (GSA). The damages claimed by plaintiff arise solely out of alleged Government-caused delays. 1 The dispute was the subject of *1283 administrative proceedings before the GSA Board of Contract Appeals for an equitable adjustment under the contract. However, the Board properly denied plaintiff’s appeal for relief on the ground that it lacked jurisdiction over the subject matter. See, United States v. Utah Construction & Mining Co., 384 U.S. 394, at 412, 86 S.Ct. 1545, 16 L.Ed.2d 642 (1966). In view of the Board’s action, and by mutual consent of the parties, a trial was held here to determine fully all questions of liability and damages. See, Stein Bros. Mfg. Co. v. United States, 337 F.2d 861, 162 Ct.Cl. 802 (1963), partially overruled on other grounds in United States v. Anthony Grace & Sons, Inc., 384 U.S. 424, ftn. 5, 86 S.Ct. 1539, 16 L.Ed.2d 662 (1966); George Bennett v. United States, 371 F.2d 859, 178 Ct.Cl. 61 (1967). In light of the detailed findings of fact below, it has been concluded that plaintiff is entitled to recover for a breach of warranty by defendant and, further, that plaintiff’s damages should be computed on the basis of three months’ delay for a total amount of $69,195.28. 2 In addition, since defendant has not shown that plaintiff bears no liability to its subcontractors for an equivalent delay suffered by them, plaintiff is entitled to recover the further sum of $48,404.78. 3 Blount Bros. Constr. Co. v. United States, 346 F.2d 962, 965, 171 Ct.Cl. 478, 483 (1965) and Morrison-Knudsen Company, Inc. v. United States, 397 F.2d 826, 852, 184 Ct.Cl. 661, 703 (1968). Cf. Severin v. United States, 99 Ct.Cl. 435 (1943), cert. denied, 322 U.S. 733, 64 S.Ct. 1045, 88 L.Ed. 1567 (1944).

It is a well established rule of law that when the Government issues detailed drawings and specifications for a contractor to follow, there is an implied warranty that conformance with such drawings and specifications will result in satisfactory completion of the work. See, for example, United States v. Spearin, 248 U.S. 132, 39 S.Ct. 59, 63 L.Ed. 166 (1918), and Hoi-Gar Mfg. Co. v. United States, 360 F.2d 634, 175 Ct.Cl. 518 (1966). Although Government-furnished plans need not be perfect, they must be adequate for the task or “reasonably accurate.” Standard Steel Car Co. v. United States, 67 Ct.Cl. 445, 472 (1929). Here, the defendant, in its haste to meet a fiscal year deadline, failed to have the drawings prepared with ordinary care, and they were issued before necessary checking was accomplished. Such “failure to be reasonably careful in the preparation of the plans” is basis for a breach claim. Jefferson Construction Company v. United States, 392 F.2d 1006, 1012, 183 Ct.Cl. 720, 729-730 (1968). The evidence clearly demonstrates that the drawings and addenda originally provided by the defendant were not sufficiently legible or coordinated to permit satisfactory construction of the desired building. Thus, defendant is liable for breach of warranty in the furnishing to plaintiff of defective drawings. Laburnum Construction Corp. v. United States, 325 F.2d 451, 163 Ct.Cl. 339 (1963).

The defendant has taken a two-pronged and somewhat inconsistent position. First, it says that the drawings were so obviously deficient that plaintiff should have recognized the defects and anticipated resulting delay. Almost in the same breath, however, it contends that the drawings were in fact adequate and *1284 sufficient for plaintiff as an experienced contractor to have constructed the building as planned.

Defendant’s first position, of course, is intended to charge plaintiff with actual or constructive knowledge of defects in the original plans so as to preclude plaintiff from relying upon defendant’s implied warranty that the drawings were adequate. See, for example, Wunderlich Contracting Co. v. United States, 351 F.2d 956, 173 Ct.Cl. 180 (1965), and cases cited therein.

Free access — add to your briefcase to read the full text and ask questions with AI

John McShain, Inc. v. United States, 412 F.2d 1281, 188 Ct. Cl. 830, 1969 U.S. Ct. Cl. LEXIS 49 (cc 1969).

412 F.2d 1281 (John McShain, Inc. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

BAE Systems San Francisco Ship Repair
Armed Services Board of Contract Appeals, 2016
Scott Timber Co. v. United States
97 Fed. Cl. 685 (Federal Claims, 2011)
Travelers Casualty & Surety of America v. United States
74 Fed. Cl. 75 (Federal Claims, 2006)
ACE Constructors, Inc. v. United States
70 Fed. Cl. 253 (Federal Claims, 2006)
W.G. Yates & Sons Construction Co. v. United States
53 Fed. Cl. 83 (Federal Claims, 2002)
Willamette Crushing Co. v. State
932 P.2d 1350 (Court of Appeals of Arizona, 1997)
Neal & Co. v. United States
41 Cont. Cas. Fed. 77,003 (Federal Claims, 1996)
T.L. Roof & Associates Construction Co. v. United States
38 Cont. Cas. Fed. 76,534 (Federal Claims, 1993)
Servidone Construction Corp. v. United States
36 Cont. Cas. Fed. 75,797 (Court of Claims, 1990)
Beauchamp Construction Co. v. United States
34 Cont. Cas. Fed. 75,453 (Court of Claims, 1988)
Kordick & Son, Inc. v. United States
34 Cont. Cas. Fed. 75,328 (Court of Claims, 1987)
Cedar Lumber, Inc. v. United States
32 Cont. Cas. Fed. 72,561 (Court of Claims, 1984)
Arthur L. Sachs, Inc. v. City of Oceanside
151 Cal. App. 3d 315 (California Court of Appeal, 1984)
Folk Construction Co. v. United States
31 Cont. Cas. Fed. 71,247 (Court of Claims, 1983)
Broome Construction, Inc. v. United States
492 F.2d 829 (Court of Claims, 1974)
Law v. United States
195 Ct. Cl. 370 (Court of Claims, 1971)
Whittaker Corporation v. The United States
443 F.2d 1373 (Court of Claims, 1971)
Warner Construction Corp. v. City of Los Angeles
466 P.2d 996 (California Supreme Court, 1970)