Standard Steel Car Co. v. United States

67 Ct. Cl. 445, 1929 U.S. Ct. Cl. LEXIS 309, 1929 WL 2457
CourtUnited States Court of Claims
DecidedMay 6, 1929
DocketNo. A-307
StatusPublished
Cited by14 cases

This text of 67 Ct. Cl. 445 (Standard Steel Car Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Standard Steel Car Co. v. United States, 67 Ct. Cl. 445, 1929 U.S. Ct. Cl. LEXIS 309, 1929 WL 2457 (cc 1929).

Opinion

Green, Judge,

delivered the opinion of the court:

It appears from the evidence without dispute that during the period of the war between the United States and the Imperial German Government the defendant entered into certain contracts with the plaintiff for the manufacture of 1,199 gun carriages on a cost-plus-fixed-profit basis. These contracts contained a provision whereby they might be terminated by the defendant, and after the active prosecution of the war had ceased the defendant exercised this right in accordance with the provisions of the contract, but authorized the plaintiff to proceed with the contract work to the extent of manufacturing a total of 601 of the gun carriages. This number of the gun carriages was completed by plaintiff and delivered to defendant but a controversy arose as to the amount due and owing to plaintiff. The parties having failed to come to any agreement as to the amount due the plaintiff under the provisions of the contract and the law as applied to such cases wherfe the contract had been terminated by the Government, the plaintiff now brings this suit to recover $703,043.28, which it claims is due under the provisions of the contract and the law as applicable thereto.

The defendant not only denies that plaintiff is entitled to recover anything herein, but under the counterclaims which it has pleaded alleges there is a net balance due to it of $164,326.78, for which it asks judgment.

Of the items for which the plaintiff asks judgment in its petition, the following are uncontested:

(®) Vouchered items_$74, 902. 05
(6) Balance paid Crofoot Gear Works_ 15,473.12.
(c) Erroneous deduction on account of Sharon Iron and Metal Co_ 973. 91
[469]*469id) Balance due Strong Steel Foundry Co., on accepted material--- $ 3,912. ¿O
(e) Balance due Strong Steel Foundry Co., on account of defective eastings_ 4, 968. 09
(†) Storage rental_ 4,529.31
(ff) Bonus to salaried employees — ^_l_ 14, 614.77
<h) Premium on bond_ 5, 200. 00
Total uncontested__ 124, 573. 35

The following items of plaintiff’s claim are contested:

(i) Redistribution of overhead_$27, 726.17
O') Overhead on rehabilitation cost_I_ 57,523.50
ik) Or, in the alternative, as allowed in the award-$17,194.72
(Z) Interest on materials purchased'for increased facili-ties_ 11,437.38
(to) Interest on material vouchers, paid after delay_ 7, 111. 16
in) Interest on material vouchers not paid_ 3, 000.00
<o) Losses by delay:
(1) Damages due to prevention by Government of contractor’s earning profits fixed by contract- 539,100.00
(2) Or, in the alternative, compensation for delayed occupancy, $107,266.86.
(p) Profit items : ,-
(1) Retained percentage upon profits paid_ 54, 090.00
(2) 10% profit on total cost, including cost of facilities, $99,532.00, claimed only in the alternative in case the allowance of $539,100 is not made as damages for delay.
(3) Or, in the alternative, profit on restoration costs, $10,739.68.
iq) Occupation of plant after completion_'_ 23,296.17
■(»■) Accountants’ cost of preparing claim_ 3,"860. 02

The items of defendant’s counterclaims and set-offs are as follows:

(a) Property transferred to the plaintiff_$144,145.16
(1) Interest thereon to January 1, 1928_ 73,514.03
(5) Liquidated damages___ 48,197.80
(o) Increased facilities not returned to defendant_ 268. 73
(d) Profit paid to plaintiff in excess of that allowable under termination clause of Article IX of contract _ 22, 774. 41
288, 900.13

Of these items, Items (a) and (e) are undisputed.

[470]*470Plainttef’s Claim; for $54,090.00, Unpaid Portion of Fixed Profit [Item (P) (1)]

The contract between the plaintiff and the defendant provided for the payment by the Government of a fixed profit of $900.00 for each unit (gun carriage) delivered, 90 per cent of which was to be paid upon the certificate of the contracting officer showing delivery and acceptance, and the remainder upon the completion of the contract. This fixed profit was subject to addition or deduction as further j)ro-vided in the contract; and if the contractor was in default he was made liable for liquidated damages and provision was made as to the method of computing the amount thereof which should be deducted from the payments made to plaintiff.

Ninety per cent of the fixed profit on the price of the gun carriages which plaintiff completed and delivered was paid to plaintiff by the defendant, and the remainder, $54,090.00, was withheld, is still unpaid, and plaintiff seeks to recover it. It is conceded by defendant in argument that if plaintiff was not in default this would be a proper item to be considered .and allowed; but defendant insists that plaintiff was in default by reason of failure to deliver the gun carriages in accordance with the terms of the contract.

The contract read:

Delivery to begin about April 1, 1918, and to continue at an approximate rate of seven (7) carriages per day, contract to be completed not later than October 1, 1918.”

The first supplemental agreement for the manufacture of additional carriages extended the date of completion of the main contract to October 15, 1918, and subsequent extensions made by defendant allowed the plaintiff 78 days after the time prescribed in the contract. As the last delivery was made June 12, 1919, it is evident that delivery was not made as specified in the contract, even when all extensions are considered. The plaintiff, however, insists that this delay was the fault of the defendant, and even claims that the defendant caused it to lose a total of 527 days in addition to the extensions granted. At this point it becomes [471]*471necessary to consider the evidence and certain provisions of the contract bearing on these conflicting claims.

The testimony taken in the case fills nearly two thousand printed pages, the greater portion of which relates to the matter of delays alleged to have been caused by the respective parties. This evidence is so conflicting, indefinite, and uncertain, that as to many important points we are able only to come to a negative conclusion that-the evidence is insufficient to form the basis of a finding.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Travelers Casualty & Surety of America v. United States
74 Fed. Cl. 75 (Federal Claims, 2006)
W.G. Yates & Sons Construction Co. v. United States
53 Fed. Cl. 83 (Federal Claims, 2002)
John McShain, Inc. v. United States
412 F.2d 1281 (Court of Claims, 1969)
J. L. Simmons Company, Inc. v. The United States
412 F.2d 1360 (Court of Claims, 1969)
McClure v. United States
110 F. Supp. 603 (Court of Claims, 1953)
Potashnick v. United States
105 F. Supp. 837 (Court of Claims, 1952)
Houston Ready-Cut House Co. v. United States
96 F. Supp. 629 (Court of Claims, 1951)
Needles ex rel. Needles v. United States
101 Ct. Cl. 535 (Court of Claims, 1944)
Bethlehem Steel Co. v. United States
75 Ct. Cl. 845 (Court of Claims, 1932)
Snare & Triest Co. v. United States
75 Ct. Cl. 326 (Court of Claims, 1932)
Carroll v. United States
68 Ct. Cl. 500 (Court of Claims, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
67 Ct. Cl. 445, 1929 U.S. Ct. Cl. LEXIS 309, 1929 WL 2457, Counsel Stack Legal Research, https://law.counselstack.com/opinion/standard-steel-car-co-v-united-states-cc-1929.