Snare & Triest Co. v. United States

75 Ct. Cl. 326, 1932 U.S. Ct. Cl. LEXIS 349, 1932 WL 2064
CourtUnited States Court of Claims
DecidedJune 6, 1932
DocketNo. E-325
StatusPublished
Cited by6 cases

This text of 75 Ct. Cl. 326 (Snare & Triest Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Snare & Triest Co. v. United States, 75 Ct. Cl. 326, 1932 U.S. Ct. Cl. LEXIS 349, 1932 WL 2064 (cc 1932).

Opinions

Wiluams, Judge,

delivered the opinion;

On April 30,1930, we made special findings of fact in this case and entered a judgment in favor of the plaintiff for $16,503.40.

A new trial was granted on the motion of the plaintiff on November 30, 1930, and an order entered setting aside the former findings of fact, judgment, and opinion, with leave to the respective parties to introduce such further evidence as they might deem advisable.

Neither the plaintiff nor the defendant submitted any additional evidence and the case now comes on for decision on the evidence originally taken and considered at the former hearing. While neither of the parties has submitted further evidence, we have been aided in the reconsideration of the case by able briefs and oral arguments of counsel for the respective parties.

Numerous exceptions have been taken to the special findings of fact heretofore made, and additional findings suggested.

The case arises out of a contract dated November 13,1919, entered into between the plaintiff and the defendant under the act of Congress of July 1, 1918, 40 Stat. 725, for the development of a submarine base at Key West, Florida. The act contained the following provisions:

“Naval station, Key West, Florida: Station improvements, $25,000; for the development of a submarine base, $1,000,000: Provided, That the Secretary of the Navy is [340]*340authorized to enter into contracts or otherwise to gations for this purpose not to exceed $1,500,000 in addition to the appropriations herein made; in all, $1,025,000.”

Under the contract the plaintiff agreed to furnish all labor and materials necessary to construct, and to construct and complete certain water-front improvements in accordance with the provisions of the contract and the plans and specifications incorporated therein.

The contract price of the work exclusive of dredging, filling, and grading was fixed at $751,730.00. The estimated cost of dredging, filling, and grading, at unit prices stipulated in the contract, was $954,000.00, making a total estimated contract price for the work of $1,705,730.00.

The plaintiff began the work shortly after the execution of the contract. .The work was finally completed and accepted on July 25, 1922.

Upon completion of the contract there was a difference of opinion between the plaintiff and the defendant as to the amount due under the contract, and on August 1, 1922, the defendant paid over to the plaintiff the sum of $162,322.55. There was admittedly due to the plaintiff at that time the sum of $165,522.55, but as a condition of the partial settlement the defendant withheld from the plaintiff 2% of the amount admitted to be due, amounting to $3,200. The plaintiff sues to recover this $3,200 so withheld. The plaintiff is clearly entitled to a judgment. The amount was withheld without authority of' law and is due to the plaintiff. McClintic-Marshall Co. v. United States, 59 C. Cls. 817.

In addition to the $3,200 so withheld, the plaintiff sues to recover upon two other items. The first item is the sum of $13,303.40 for a balance claimed to be due on marl furnished upon the work.

When settlement was made on August 1,1922, the plaintiff was paid for the furnishing of 37,079 cubic yards of marl. The plaintiff contends that it should have been paid upon the basis of'49,173 cubic yards, a difference of 12,094 cubic yards. The unit price for marl furnished under the contract was $1.10 per yard.

The question presented upon this branch of the case is one of interpretation of the provisions of the contract covering [341]*341this part of the work. Paragraph 53, of the specifications, provides:

“ It is the intention of the Government- to have that part of breakwater fill indicated as marl on drawings consist of the soft material dredged from basin with at least 2 feet of pure marl on top.
“It is assumed that sufficient marl or equivalent, satisfactory to the officer in charge, will be found in the basin and each bidder shall base his proposal upon that assumption.
“ Each bidder, however, shall also submit a unit price bid, as per item 4 (c), for furnishing and depositing marl in such quantity as may be needed, if any, over and above the material, satisfactory to the officer in charge, excavated from basin.”

Item 4 of paragraph 206 of the specifications provides:

“(a) Unit price for each cubic yard of rock material (measured in original position) excavated and deposited as specified.
“(b) Unit price for each cubic yard of soft material (measured in original position) excavated and deposited as specified.
“(c) Unit price for each cubic yard of marl furnished and placed by dredging contractor in case sufficient marl or its equivalent, satisfactory to the officer in charge, is not available from basin.”

Paragraph 6 of the contract provides:

“ For each cubic yard of rock material excavated and deposited in accordance with item 4 (a), the sum of two dollars and fifteen cents ($2.15);
“For each cubic yard of soft material excavated and deposited in accordance with item 4 (b), the sum of fifty cents ($0.50);
“ For each cubic yard of marl furnished and deposited in accordance with item 4 (c), the sum of one dollar and ten cents ($1.10).”

It will be noted that materials excavated and deposited under items 4 (a) and 4 (b) are to be “ measured in original position.” The clause, “ measured in original position,” is omitted from item 4 (c), clearly indicating that marl furnished and placed under this item was not to be “ measured in original position,” but was to be paid for on the basis of some other measurement. We think the necessary conclusion is that the marl was to be measured in place after it had [342]*342gone into the fill. None of the marl was excavated from the basin, but it was all procured by plaintiff and brought in from other places. It was measured after it had been placed on the fill and the plaintiff was paid for the marl on the basis of that measurement. The plaintiff’s contention is that this method of measurement was not in accordance with the provisions of the contract. Plaintiff’s position on this item of the claim is set forth in its statement to the Navy board, referred to in our findings of fact:

“ Measurement of marl: Paragraph 56 of the specifications as a part of the contract provided that ‘ material to be dredged or excavated shall be measured in its original position.’ Notwithstanding, the department elected to measure marl only in its final position after having dried out.”

The plaintiff’s construction of these contract provisions can not be sustained. It is clear that only such materials as were excavated from the basin were to be measured in original position. Measurement of the marl brought in from the outside in final position on the fill was in accordance with the provisions of the contract.

It appears, however, that without fault on the part of the plaintiff, 2,068 cubic yards of marl placed by the plaintiff was washed away before the outer bulkhead provided in supplemental agreement 3762-Z, hereinafter referred to, was completed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States Steel Corp. v. United States
536 F.2d 921 (Court of Claims, 1976)
Charley v. United States
208 Ct. Cl. 457 (Court of Claims, 1975)
Merrill-Stevens Dry Dock & Repair Co. v. United States
96 F. Supp. 464 (Court of Claims, 1951)
Edward E. Gillen Co. v. United States
88 Ct. Cl. 347 (Court of Claims, 1939)
Nesbit v. Frederick Snare Corp.
96 F.2d 535 (D.C. Circuit, 1938)
Universal Battery Co. v. United States
3 F. Supp. 878 (Court of Claims, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
75 Ct. Cl. 326, 1932 U.S. Ct. Cl. LEXIS 349, 1932 WL 2064, Counsel Stack Legal Research, https://law.counselstack.com/opinion/snare-triest-co-v-united-states-cc-1932.