Sanger v. United States

40 Ct. Cl. 47, 1904 U.S. Ct. Cl. LEXIS 18, 1904 WL 852
CourtUnited States Court of Claims
DecidedDecember 5, 1904
DocketNo. 18920
StatusPublished
Cited by6 cases

This text of 40 Ct. Cl. 47 (Sanger v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sanger v. United States, 40 Ct. Cl. 47, 1904 U.S. Ct. Cl. LEXIS 18, 1904 WL 852 (cc 1904).

Opinion

Peelle,J.,

delivered the opinion of the court:

This action is for the reformation of a contract and damages for alleged breaches thereof. The facts are these: In March, 1883, the United States, through Major Benyuard, Corps of Engineers, U. S. Army, advertised for proposals for furnishing stone for the construction of two locks in the Illinois River near Lagrange and Kampsville, Ill. Accompanying the advertisement were the general instructions to bidders and specifications as to quality and dimensions of stone required.

In response to the advertisement the claimants made a bid offering to furnish the stone required for the two locks at the bids named by them, as set forth in finding i. The claimants’ bid being the lowest the same was submitted to the Chief of Engineers, United States Army, who accepted the [62]*62same, if, in the opinion of the engineer officer in charge, the bid was a reasonable one. The Chief of Engineers, however, in the same letter, directed “ that the contract should not be entered into until the title to the land required for the site of the locks had been secured by the United States and approved by the Attornej^-General.” The contents of the letter' were made known to the claimants on its receipt and they made no objections thereto.

As soon as the title to the land had been acquired the claimants and the United States, through the engineer officer in charge, entered into the contract of August 29, 1883, in which was included only the stone for the Lagrange lock, whereas the claimants in their amended petition aver that the entire stone required for the two locks should have been included in said contract in conformity with the advertisement for proposals, the specifications, and the claimants’ bid, and for that reason it is averred in said amended petition, inter alia, that they are “ entitled to have said contract of August 29, 1883, reformed, so as to make it conform to the intention and agreement of the parties thereto, as expressed in the said invitation for proposals, the bid of claimants submitted in response thereto, and the acceptance thereof as communicated to the defendants or their agents, and to have the same judgment and relief as if the said contract had conformed to the said preliminary agreement and had contained the necessary provisions for all the stone required for the Kampsville lock as well as for the Lagrange lock.”

The facts found fail to disclose any mistake on the part of the United States in thus entering into the contract, while on the part of the claimants the facts set forth in finding hi show that neither “ at the time the first ’contract named above (August 29, 1883) was entered into, nor at any subsequent period, did the claimants' claim or demand the right to contract for the entire work of both locks in the same contract.”

The mere fact that said contract of August 29, 1883, embraced only the stone for the Legrange lock, when the bid accepted covered the stone for both locks, can not be held to have been a mutual mistake, especially when the claimants [63]*63knew that such was the course of the Government in making contracts for such works, and no demand or claim otherwise was made at the time of signing said contract. This being so, we need not consider the question raised by the defendants as to whether the court, under its general jurisdiction, has the equitable power to enter a decree re-forming the contract..

The claimants, however, further contend, by the averments in their original petition and in their brief, that -when their bid was accepted in response to the advertisement for proposals, a contract was thereby formed for the entire work and that therefore the several contracts subsequently entered into should be considered as one document or instrument embodying the whole work so covered by their bid, and this contention, they claim, finds support in the cases of Garfielde v. United States (93 U. S., 242, 244); Hawkins v. United States (96 U. S., 689, 694), and Harvey v. United States (105 U. S., 671).

In the first of the cases cited, which was a contract made through the Post-Office Department for conveying the mails, the court, respecting the contract, said: “ The Court of Claims holds that the proposal on the part of Garfielde, and the acceptance of the proposal by the Department, created a contract of the same force and effect as if a formal contract had been written out and signed by the parties. Many authorities are cited to sustain the proposition. We believe it to be sound, and that it should be so held in the present case.”

In the Hawkins case, which arose under a contract made by the Secretary of the Treasury under a special act of Congress (17 Stat. L., 390), the court said: “Aid in the construction of the contract may be derived from the advertisement under which the bids were received, as the advertisement is expressly referred to in the written contract.”

In the Iiaroey ease, which was a contract made through the War Department for the construction of a bridge at Rock Island, Ill., a claim for which, was referred to the court under a special act (19 Stat. L., 490), the court said: “ The written bid in connection with the advertisement, and [64]*64the acceptance of that bid, constituted the contract between the parties so far as regards the question whether the contract prices embraced the cofferdam work.”

In the case of South Boston Iron Co. v. United States (118 U. S., 37-42) a letter had been addressed to the Secretary of the Navy proposing to construct new boilers for certain vessels of the Navy, which offer was accepted by the Navy Department by letter and the proposed contractor was informed that drawings and specifications would be furnished as soon as possible. But a few days later he was notified to discontinue all work contracted for by him Avith the Department. The action Avas sought to be founded upon the letters as constituting a contract, but in respect thereto the court, speaking by Chief Justice Waite, said: “In Clark v. The United States (95 U. S., 539) it Avas decided that, to bind the United States, contracts by the Navy Department must be in writing and signed by the contracting parties. Such, in the opinion of the court, was the effect of the act of June 2, 1862 (12 Stat., 411, ch. 93), uoav in force as sections 3744-3747 and sections 512-515 of the BeAdsed Statutes. An effort has been made in this case to sIioav a contract in Avriting, but Ave agree entirely with the Court of Claims (hat the papers relied on for that purpose are nothing more in laAv or in fact than the preliminary memoranda made by the parties for use in preparing a contract for execution m the form required by law. This Avas never done, and therefore the United States never became bound. Within a A^eiy feAv days after the memoranda were made the Avhole matter was abandoned bjr the Department, and the iron company has neither performed any of the Avork Avhich Avas referred to, nor has it eA^er been called on to do so.” Such also Avas the decision of this court in the case of Chapter of Calvary Cathedral v. United States (29 C. Cls. R., 269).

Undoubtedly the first element essential to the formation of a contract is a distinct communication between the parties — i. e., an offer by one and acceptance thereof by the other. This done the question is as to the form and con-, sideration of the contract the parties have outwardly con[65]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pennsylvania Coal & Coke Corp. v. United States
70 F. Supp. 136 (Court of Claims, 1947)
Snare & Triest Co. v. United States
75 Ct. Cl. 326 (Court of Claims, 1932)
Sutton v. United States
55 Ct. Cl. 193 (Court of Claims, 1920)
Spearin v. United States
51 Ct. Cl. 155 (Court of Claims, 1916)
Pacific Hardware & Steel Co. v. United States
49 Ct. Cl. 327 (Court of Claims, 1914)
New Jersey Foundry & Machine Co. v. United States
44 Ct. Cl. 178 (Court of Claims, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
40 Ct. Cl. 47, 1904 U.S. Ct. Cl. LEXIS 18, 1904 WL 852, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sanger-v-united-states-cc-1904.