Pennsylvania Coal & Coke Corp. v. United States

70 F. Supp. 136, 108 Ct. Cl. 236, 1947 U.S. Ct. Cl. LEXIS 15
CourtUnited States Court of Claims
DecidedMarch 3, 1947
DocketNo. 46367
StatusPublished
Cited by8 cases

This text of 70 F. Supp. 136 (Pennsylvania Coal & Coke Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pennsylvania Coal & Coke Corp. v. United States, 70 F. Supp. 136, 108 Ct. Cl. 236, 1947 U.S. Ct. Cl. LEXIS 15 (cc 1947).

Opinion

Jones, Judge,

delivered the opinion of the court:

Plaintiff’s claim arises out of the sale and delivery by it to defendant of certain quantities of coal in 1939, for which it contends it has not been paid in full. By virtue of a stip[242]*242ulation entered into between the parties subsequent to the filing of plaintiff’s petition it is agreed that judgment in the amount of $22,000 may be entered in favor of plaintiff, in full settlement of all matters involved in this case, provided plaintiff’s claim is not barred by the statute of limitations applicable to claims filed in this court. The sole issue for our determination, therefore, is whether plaintiff’s petition was filed within six years after the claim first accrued, as required by section 156 of the Judicial Code.

Under date of June 80,1938, plaintiff entered into contract No. TPS-23545 with defendant whereby plaintiff agreed to sell and deliver coal to the Procurement Division of the United States Treasury Department, in accordance with a written schedule which set out in detail the quantity and kind of coal to be delivered each month during a 12-month period beginning in July 1938 and ending the following June. The contract initially ran for a period of 30 days beginning July 1, 1938, but there was reserved to defendant the right to renew the contract for successive 30-day periods during the remainder of the fiscal year ending June 30,1939, and plaintiff executed a performance bond covering all coal to be delivered by it during said year in accordance with said schedule. From time to time throughout the fiscal year ending June 30, 1939, by written notification to plaintiff prior to the expiration' of each particular 30-day period, defendant renewed the contract for successive 30-day periods. Thus, under date of February 20, 1939, defendant notified plaintiff of the amendment of that portion of its contract covering run-of-mine coal (previously extended through February 25, 1939), by letter containing the following language:

The above purchase order is hereby further amended to increase the number of units from approximately 34,000 tons to 39,000 net tons of coal at $4,468 per ton, and the extension amount from $151,912.00 to $174,252.00.
The expiration date notice on the order is to be changed to read as follows: “Expiration date of ninth 30-day contract period is March 27,1939, and contract may be further extended in accordance with paragraph 9 of Schedule No. 1 of Invitation No. 13748-C-5-5-38, opened May 5, 1938.”

[243]*243Similar notices were given to plaintiff on the same date, with reference to the other types of coal it had agreed to furnish pursuant to the terms of Schedule No. 1 of the contract. Ultimately the twelfth or final renewal of the contract extended the expiration date to June 25, 1939. The last shipment of coal was on September 29, 1939, and the last remittance from defendant was received by plaintiff on October 24, 1939.

Upon making each shipment of coal plaintiff sent an invoice to defendant giving the details of shipment, the quantity, grade and price of the coal covered by the invoice, and the amount of money due thereunder. Contract No. TPS-23545 contains the following provision With reference to payment for coal delivered by plaintiff:

Payments: The contractor shall be paid upon the submission of properly certified invoices or vouchers at prices stipulated herein for coal delivered and accepted. Unless otherwise specified, payments will be made on deliveries accepted by the Government when the amount due on such deliveries so warrants: Provided, That when requested by the contractor payments for accepted partial deliveries shall be made whenever such payments would equal or exceed either $1,000 or 50 percent of the total amount of the contract. When samples are taken, as provided in paragraph 16, 10 percent of the amount due may be withheld pending the outcome of the analyses of the samples.

By March 11, 1939, plaintiff had made some hundreds of different shipments of coal to defendant, and had received from defendant a considerable number of remittances of varying amounts, aggregating many thousands of dollars. A comparison of the dates and amounts of each shipment made by plaintiff with the dates and amounts of each payment received by plaintiff (finding 12) fails to indicate any regular pattern of payment employed by defendant based either upon the dates of the shipments from plaintiff, or the amounts thereof, or otherwise. There is no evidence that any settling of accounts between the parties, periodic or otherwise, had occurred prior to March 11, 1939. On that date the coal delivered by plaintiff to defendant in accordance with the contract, for which plaintiff had not then been paid, amounted to $116,807.05.

[244]*244Some time not later than March 21,1989 (the proofs submitted do not permit finding a more exact date) plaintiff received from defendant a check for $9,122.30, dated March 11,1939, and issued pursuant to Public Voucher No. S35322. Attached to this voucher, and listed thereon for payment were nineteen of plaintiff’s invoices, aggregating in amount $33,662.32, for a portion of the coal which plaintiff had delivered to defendant during the period from February 6,1939, to February 22,1939. The figure of $9,122.30 was computed on the Government voucher by deducting from the amount representing plantiff’s invoices the sum of $24,540.02, to cover certain payments made to plaintiff in 1938 under a previous contract, which payments defendant in the meantime had concluded were unauthorized and hence sought to recoup.

Defendant does not attempt in the present proceeding to obtain a judicial determination of the propriety of such deductions, but concedes that, if plaintiff’s claim has been timely filed, judgment may be entered against defendant for $22,000.

Whether or not any previous discussion had occurred between plaintiff and defendant concerning the repayment of such amounts prior to defendant’s action in March 1939 does not appear in the record. So far as the evidence shows, the charging of plaintiff’s account was a purely unilateral act on the part of defendant, accomplished by the taking of a deduction on the face of the voucher, with a memorandum on the reverse side thereof that the deduction was “for overpayment in accordance with Comptroller General’s Decisions A-93507 and A-93379 dated April 25, 1938, $24,540.02.” On March 21, 1939, plaintiff wrote defendant that “we do not assent to the correctness of the deductions nor do we accept the check as full payment,” to which defendant shortly thereafter replied that

* * * the acceptance of the check * * * issued in connection with the settlement will in no way jeopardize any future claim that you may wish to present.

On April 4,1939, plaintiff presented its claim for $24,540.02 to the Comptroller General, who denied the claim on September 14, 1939. Plaintiff, having received payment for all coal shipped under the contract except for the $24,540.02 so [245]*245retained, filed its original petition in this court for such sum on March 16,1945. It follows that if plaintiff is to prevail in this proceeding its claim must not appear to have first accrued prior to March 16, 1939. Kendall v. United States, 14 C. Cls. 122.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Highland Al Hujaz Co., Ltd.
Armed Services Board of Contract Appeals, 2016
Enron Federal Solutions, Inc. v. United States
80 Fed. Cl. 382 (Federal Claims, 2008)
Aptus Co. v. United States
62 Fed. Cl. 808 (Federal Claims, 2004)
Copco Steel & Engineering Co. v. The United States
341 F.2d 590 (Court of Claims, 1965)
L. Balkin Builder, Inc. v. United States
142 F. Supp. 597 (Court of Claims, 1956)
Pacific Maritime Ass'n v. United States
108 F. Supp. 603 (Court of Claims, 1952)

Cite This Page — Counsel Stack

Bluebook (online)
70 F. Supp. 136, 108 Ct. Cl. 236, 1947 U.S. Ct. Cl. LEXIS 15, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pennsylvania-coal-coke-corp-v-united-states-cc-1947.