Myerle v. United States

31 Ct. Cl. 105, 1896 U.S. Ct. Cl. LEXIS 151, 1800 WL 1930
CourtUnited States Court of Claims
DecidedJanuary 27, 1896
DocketNos. 14547, 14548
StatusPublished
Cited by6 cases

This text of 31 Ct. Cl. 105 (Myerle v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Myerle v. United States, 31 Ct. Cl. 105, 1896 U.S. Ct. Cl. LEXIS 151, 1800 WL 1930 (cc 1896).

Opinion

Davis, J.,

delivered the opinion of the court:

Plaintiff’s intestate made with the Government two contracts in relation to the monitor M'onadnock; these contracts provided for building the framework and hull and for all ironwork except the armor. It was in one contract provided, substantially, that the Government should furnish the plans and specifications and deliver all materials, freight paid, at Yallejo, Cal., where the vessel was to be built.

The other contract was for the ironwork (except armor), and construction thereunder was to be begun so soon as the first contract had been completed; to be finished within nine months, there being a penalty for delay. This second contract is not important to this action.

Work on the vessel should have been finished by November, 1876. Through delays caused by defendants this became impossible; plans and specifications were not promptly furnished to the contractor, were often changed, and were often defective, all of which involved delay in the vessel and expense to the contractor; while materials were delayed in delivery, were often delivered out of regular order, and were delivered in such defective form as to make alteration necessary, always at expense to the contractor.

[132]*132Iu July, 1876, the Department of the Navy ordered all work on the vessel suspended until further order; this suspension was indefinite as to time; therefore the contractor felt himself obliged to remain in readiness to go on with the work when called uxion, and did not deem it wise to disperse his force of trained and skilled mechanics.

In December, 1876, work was resumed and proceeded (with interruptions and delays, all caused by defendants), for about a year, when it was again stopped because of defendants’ failure to deliver materials as in duty bound. The contractor could not again proceed until May, 1883, and the work was not finished until the following November, more than seven years after the date first contemplated by the parties.

There does not appear in the findings of fact anything tending to show neglect or default upon the part of the contractor; on the contrary, the very unusual delay was due to the defendants’ fault alone and was caused, as appears, by lack of money in the Navy Department.

As early as November, 1878, this claim was presented to the Department of the Navy, where it was held under consideration until February 17, 1885, when the Secretary of the Navy referred the case to this court under section 1063 of the Devised Statutes.

It is urged by defendants that the claims for damage under the contract of October 21, 1875, are barred by virtue of the limitation prescribed by section 1069 of the Devised Statutes, unless the Secretary of the Navy had authority to refer them, as he did, under section 1063 of the Devised Statutes; that section 1063 does not contemplate the reference of claims for unliquidated damages, but only of such claims as are within the jurisdiction of the Executive Department to settle; that claims for unliquidated damage not being within that jurisdiction this claim was not presented to a competent tribunal within six years from the date when it accrued. The work upon the vessel required of plaintiff’s testator was not entirely completed until 1883, but the cause of several items of claim herein occurred more than six years before the petition was filed in this court, and it is contended that the statute of limitations bars those items.

If this contention by defendants be correct, then any contractor with the Government must, to protect his right, sue [133]*133upon every item of difference of fact and every item of difference of interpretation of tbe contract as each, detail of his work is undertaken or completed, as the case may be.

There is no more complicated engine known than a completed vessel of war with its massive hull and armor, its many varied and ingenious engines, its guns with their ammunition and appliances, and its provision for comfortably lodging and feeding a large body of men under all the possible conditions of weather and combat. In the construction of such a vessel it would be strange if there were not daily presented matters of detail involving dispute between the inspecting officer and the contractor, and requiring an immediate final and, indeed, arbitrary decision of points of detail, as to which difference of opinion may well exist. If each time such a point arises and is decided adversely to the contractor he must forthwith begin the prosecution of his remedy against the Government, the parties as well as the courts would be subject to great and unnecessary labor and expense in adjusting j>etty difference, which could more economically and advantageously be settled in a single action brought after completion of the work. Further than this, if an action be brought before all items of damage have occurred, damages thereafter happening in the prosecution of the same work under the same contract would be held barred. The work in this case was in fact not completed until more than seven years after the contract period, and this not by reason of any fault of the contractor; for most of the time he was held in anxious readiness to proceed, being ignorant of the moment when an order to complete the vessel might be received. The contractor was not lacking in diligence, and if, under these circumstances, defendants’ argument as to the statute of limitations be correct great hardship to the contractor will result.

The claim was presented to the Secretary of the Navy in. November, 1878, and afterwards was referred to this court. The Secretary had jurisdiction to settle the amounts due under these contracts and the claim made for extra expenses and work agreed upon and incurred because of' defendants’ action and of which defendants have received the benefit. Possibly, because of' Government’s repeated and long-continued delays, plaintiff might have elected to terminate his contract, but he was not forced to do so, as he was guiltless of fault or neglect [134]*134in the matter and was free t© go on, finish the work, and then sue.

We hold that Burgess had a right to wait until his contract was completed; that he was not forced to sue in 1877 and thus risk greater loss, and that the right of action herein became complete, as to the items herein allowed, when the work was finished, to wit, in 1883. This being so, and the claim having-been presented to the Navy Department in 1878 and filed in this court April 10,1886, the action is not barred by the statute of limitations. (Dubois v. Del. and H. Canal, 4 Wend., 285; Allamon v. The Mayor, etc., 43 Barbour, 33; Bendemagle v. Codes, 19 Wend., 207; Badger v. Libcombe, 15 Pick., 409.)

When a Department transmits a case to this court involving controverted questions of fact and law arising upon a claim under a contract which the Department might have settled, and, on the trial, claims for unliquidated damages on either side which the Department had no authority to settle are set up, this court may adjudicate upon all such claims the same as though they had been presented here on voluntary petition.

Was there a contract? In this case there was an advertisement and Burgess was the lowest bidder.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pennsylvania Coal & Coke Corp. v. United States
70 F. Supp. 136 (Court of Claims, 1947)
Joplin v. United States
89 Ct. Cl. 345 (Court of Claims, 1939)
United States v. Gordin
287 F. 565 (S.D. Ohio, 1922)
Axman v. United States
47 Ct. Cl. 537 (Court of Claims, 1912)
William Clamp & Sons Ship v. United States
41 Ct. Cl. 164 (Court of Claims, 1906)

Cite This Page — Counsel Stack

Bluebook (online)
31 Ct. Cl. 105, 1896 U.S. Ct. Cl. LEXIS 151, 1800 WL 1930, Counsel Stack Legal Research, https://law.counselstack.com/opinion/myerle-v-united-states-cc-1896.