Axman v. United States

47 Ct. Cl. 537, 1912 U.S. Ct. Cl. LEXIS 122, 1911 WL 1379
CourtUnited States Court of Claims
DecidedFebruary 12, 1912
DocketNo. 28707
StatusPublished
Cited by3 cases

This text of 47 Ct. Cl. 537 (Axman v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Axman v. United States, 47 Ct. Cl. 537, 1912 U.S. Ct. Cl. LEXIS 122, 1911 WL 1379 (cc 1912).

Opinion

Booth, J.,

delivered the opinion of the court:

Congress by an act approved March 3, 1889 (30 Stat. L., 1132), authorized the removal of certain impediments to navigation in San Francisco Harbor, Cal. On June 7, 1899, Col. W. H. Heuer, a district engineer of the United States Army, publicly elicited bids for the performance of the work, and in response thereto claimant submitted his proposal, which, being the lowest, was accepted. The written contract annexed to the petition and made a part thereof, was executed by the parties and duly approved as provided therein by the Chief of Engineers on September 29, 1899. On October 4, 1899, claimant was notified of the approval of the contract, and commenced work thereunder on December 3, 1899.

The contract and specifications constituted one instrument, and required the removal of three comparatively large rocks, almost totally submerged, known as Shag Bock No. 1, Shag-Bock No. 2, and Arch Bock. The manner of their removal was left to the discretion of the claimant, subject to the approval of the Engineer officer in charge, the claimant being expressly obligated to remove each of the rocks to a depth of 30 feet below mean low water. Very soon after the commencement of the work differences arose between Col. Heuer and the claimant, resulting finally in the commencement of this suit. The respective items of the claim can best be treated [549]*549separately. They aggregate the total sum of $101,222.13, made up of separate and distinct complaints and necessarily segregated by counsel in their briefs and arguments.

Item 1: The claim arises under Finding YI. Specification 39 provided as follows: “ The smaller rocks (the Shag Rocks) will be removed first; work on Arch Rock need not be commenced until further appropriation shall be made.” The Engineer officer in construing this Specification construed it strictly, refusing the contractor permission to work conjointly on the two Shag Rocks, holding that all work, including dredging of material blasted, must be entirely completed on one before anything could be done upon the other. The language of the specification is clearly susceptible of two constructions, the one interposed by the engineer and the one contended for by the contractor. No specific direction as to Shag Rock No. 1 or Shag Rock No. 2 was given as to the order of their removal; the plural is used, “the smaller rocks.” The contractor elected to -commence work on No. 1, but by so doing it, can not be reasonably asserted he precluded himself from joint operations if the organization of his force and his interests, as well as the interests of the defendants, would be advanced thereby. His plans for the removal of both Shag Rocks had been submitted and approved by the engineer, and if the circumstances of the case and the situation of the parties at the time characterize the rulings of the engineer as an arbitrary and unreasonable exercise of his discretionary power under the contract the consequential loss is recoverable. (Collins and Farrel v. United States, 34 C. Cls., 294.) Taking specification 39 as a whole, and construing it in conjunction with the act of March 3, 1899, supra, it is clearly designed as precautionary rather than mandatory, its evident intent being to bring the contract within the terms of the enabling act, for the preliminary appropriation was not sufficient, to cover the entire undertaking, and the defendants were justly concerned in keeping the completed work within the limits of available funds to pay therefor. It is obvious that no particular order of removal of the rocks was indispensable; they were not contiguous; the language as to the removal of Arch Rock is clearly directory; the whole specification preceding, [550]*550as it necessarily did, the execution of the contract, was intended to comply with the intent of the Congress as expressed in the act of March 3, 1889, wherein it provided for supplemental appropriations from time to time as the work progressed. If the appropriation was available work might have commenced on Arch Eock without violating the contract. The contractor’s worldng organization included the employment, of skilled workmen, experts in the handling of drilling machines, and the employment of high explosives; to be compelled to use these men at ordinary labor at advanced wages when they could have been profitably employed occasioned loss. It was impracticable to discharge them after each blast and thus disorganize a systematic working force. The Engineer officer in charge can find no safe refuge in making this ruling by ascribing'it to a belated performance of the work on the part of the contractor, and a conjectural increase in price and additional difficulties in performance if the contractor failed in his undertaking, for he was manifestly requiring extra work of the contractor in the matter of depth of excavation and had unjustly and arbitrarily prejudiced the contractor’s ability to do the work before he had even commenced operations. The United States was in no position to suffer, but on the contrary to benefit by a contrary ruling. Not one dollar had at this time been paid the contractor, and none was asked for. One thousand cubic yards of rock were required to be removed monthly; the engineer officer knew this, and instead of facilitating operations and enabling the contractor to execute the contract by having blasted material immediately available for removal he compelled him to confine operations to the single rock until every vestige had been removed. The contractor was limited as to time and was entitled to some consideration, especially when he had exhibited a degree of industry and faithfulness not always manifest in contracts of this character. The defendants were amply protected from any failure of performance by a surety bond equal in amount to the first appropriation under the act of Congress. The amount claimed for the delay preceding work on Arch Eock must be disallowed. The refusal of the Engineer officer [551]*551having been ignored, the work proceeded and contractor suffered no loss thereby. Item 1 is allowed for $735.

Item 2: The claim under this item is found in Finding IX. Paragraph 44 of the specifications provided a means of making survey of the completed work upon which estimates were to be predicated. The claimant knew this was indispensable, and while the drilling was not done from scows or boats, he can not relieve himself from the obligation to furnish the same by the approval of a different plan prepared by himself and assented to by the engineer, in which no provision was made for a fixed point for surveys. The specification did not provide in detail as to manner and is clearly susceptible to the construction placed upon it by the engineer in charge. The specification was intended to provide for a fixed point for a survey of the work done at the expense of the contractor, and because' he did not elect to pursue the methods permitted by the specification, which he could have done, he can not now complain that in doing the work in a different manner he incurred additional expense. The item is disallowed.

Item 3: Finding X discloses the facts. This item will be allowed. It is inconceivable how it could be disallowed. The work required of the contractor was not included in the contract, specifications, or the contour lines of the blue prints. The existence of this rock, a separate and distinct formation, 80 feet distant from Arch Rock, was not known to any official or any other person concerned in the subject matter of the contract, and was never intended to be included in the contract price.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hampton v. United States
82 Ct. Cl. 162 (Court of Claims, 1935)
Bush v. United States
55 Ct. Cl. 485 (Court of Claims, 1920)
Axman v. United States
48 Ct. Cl. 376 (Court of Claims, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
47 Ct. Cl. 537, 1912 U.S. Ct. Cl. LEXIS 122, 1911 WL 1379, Counsel Stack Legal Research, https://law.counselstack.com/opinion/axman-v-united-states-cc-1912.