Hampton v. United States

82 Ct. Cl. 162, 1935 U.S. Ct. Cl. LEXIS 177, 1935 WL 2276
CourtUnited States Court of Claims
DecidedDecember 2, 1935
DocketNo. L-501
StatusPublished
Cited by3 cases

This text of 82 Ct. Cl. 162 (Hampton v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hampton v. United States, 82 Ct. Cl. 162, 1935 U.S. Ct. Cl. LEXIS 177, 1935 WL 2276 (cc 1935).

Opinion

Booth, Chief Justice,

delivered the opinion of the court:

The plaintiff, as executor of the estate of J. D. Young, deceased, brings this suit to recover the various sums hereinafter mentioned, predicating the legal right to do so upon the decedent’s relationship with the United States during the periods involved.

September 10, 1924, J. D. Young contracted in writing with the United States to dredge the channel of 'an old canal between Moss Bluff Bridge and the mouth of Silver Springs Bun, in Florida. The consideration to be paid Young was $50,000, and the work was to be performed in accord with the terms of the contract and detailed specifications.

A portion of paragraph 15 of the specifications, upon which plaintiff relies as to the first item in suit, is as follows:

* * * The quantity of material to be removed from within the finished channel lines, as shown on the drawing referred to in paragraph 16 post, is estimated to be 216,000 cubic yards, but the United States does not guarantee the accuracy of this estimate, nor the accuracy of the drawing-in respect of the depth and location of the cuts, and, should [172]*172it develop in the course of the work that the estimate or the drawing, either or both, are not entirely accurate, neither party to the contract will make a claim against the other on account of any such inaccuracies, but both parties to the contract will be bound by the intent and purpose of the specifications as above described.

The specification estimate of 216,000 cubic yards was admittedly a mistake upon the part of representatives of the War Department, they having made an error with respect to levels to be followed, which imposed upon the contractor the necessity of excavating 297,081 cubic yards of material, or an excess quantity of 81,081 cubic yards over the estimate.

Plaintiff proves that the reasonable value for dredging the above quantity of material is $26,351.32, i. e., at the rate of 32% cents per cubic yard, and for this sum judgment is sought, upon an alleged implied contract to pay for the same on the basis of quantum meruit.

The first important question is whether such a cause of action is available to plaintiff. The petition contains no allegation of breach of contract, no charge of misrepresentation or the withholding of information upon the part of the defendant. All that is alleged and established by the record is the fact that an error was made in the drawings of and by the defendants to which the contractor was entitled, and which when corrected caused the contractor to excavate under the contract a large quantity of material in excess of what he otherwise would have had to do.

The subject matter of the contract involved was manifestly dredging. The area to be dredged, and the depth, width, and length of the channel were approximately specified, and the contractor not only entered upon performance, but continued work under the contract and the supervision of defendant’s officials acting as inspectors and contracting-officers. The fixed consideration for the contract was paid the contractor, less the retained percentages, and accepted. To now insist that the contractor’s rights are determinable as though no express written contract for the work claimed for existed, is, we think, untenable. Pharr v. United States, 62 C. Cls. 445; Klebe v. United States, 263 U. S. 188; Hawkins v. United States, 96 U.S. 689; Ceballos & Co. v. United [173]*173States, 214 U. S. 47; Keystone Structural Co. v. Link-Belt Co., 270 Fed. 705.s

The remaining vital issue is whether the plaintiff may recover for this item under the written contract set forth in the findings. We might well assume, in view of the allegations of the petition and plaintiff’s contentions thereunder, that defendant’s liability under the written contract is nonexistent. However, our rules of pleading exact consideration of the facts as established and alleged in the petition, irrespective of plaintiff’s application of the same.

Plaintiff seeks to escape the legal consequences of assenting to paragraph 15 of the contract by attributing to the words therein “are not entirely accurate” the limitations usually ascribed to the use of the phrase “more or less”, and contends that a deviation from the estimated quantity of material tó be dredged, extending to five or six per cent of the same, is all that is allowable or intended.

The argument is not convincing from a purely legal aspect. Obviously if the estimated quantity of material to be dredged had greatly exceeded the quantity essential to conform to the drawings and grades therein given, the contractor would nevertheless have been entitled to the $50,000 consideration for the undertaking.

The contract in suit was let to plaintiff’s decedent when he submitted his bid therefor in pursuance of a public advertisement soliciting bids for performing the specified work. The advertisement estimated the quantity of material to be dredged at 260,840 cubic yards. The written contract contained the following express provisions:

3. Quantities approximate. — It is understood and agreed that the quantities given in these specifications are approximate only, and that no claim shall be made against the United States on account of any excess or deficiency, absolute or relative, in the same. No allowance will be made for the failure of a bidder or of the contractor to estimate correctly the difficulties attending the execution of the work.
4. Errors and omissions. — The contractor will not be allowed to take advantage of any error or omission in these specifications, as full instructions will always be given should such error or omission be discovered.

[174]*174Paragraphs 15 and 16 are parts of “Detailed specifications.” Paragraph 16 reads as follows:

16. Drawing's. — The work shall conform to drawing marked “Oklawaha River, Florida, Survey made Jan. 31st to Feb. 15th, 1924, for estimate of material to' be removed to provide 5-feet water from Moss Bluff to Silver Springs Run” file marked 6298-114. The lines and grades to be followed are shown on the profile and sections on this drawing by broken lines marked “Grade line B.” This drawing forms a part of these specifications and is filed in the TJ. S. Engineer Office at Jacksonville, Florida.

So far as the quantity of material to be dredged is concerned, the contractor was advised three times that it was only estimated, and no guarantee as to accuracy or as to quantity obtained, and, in addition, positive provisions of the contract warned the contractor that the United States would not be responsible for errors, omissions, or the entire accuracy of the drawings setting forth the work to be performed. The language of the contract in this respect could not be more explicit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Needles ex rel. Needles v. United States
101 Ct. Cl. 535 (Court of Claims, 1944)
Sternberg v. United States
87 Ct. Cl. 332 (Court of Claims, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
82 Ct. Cl. 162, 1935 U.S. Ct. Cl. LEXIS 177, 1935 WL 2276, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hampton-v-united-states-cc-1935.