Monad Engineering Co. v. United States

53 Ct. Cl. 179, 1918 U.S. Ct. Cl. LEXIS 199, 1918 WL 1017
CourtUnited States Court of Claims
DecidedFebruary 25, 1918
DocketNo. 30809
StatusPublished
Cited by2 cases

This text of 53 Ct. Cl. 179 (Monad Engineering Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Monad Engineering Co. v. United States, 53 Ct. Cl. 179, 1918 U.S. Ct. Cl. LEXIS 199, 1918 WL 1017 (cc 1918).

Opinion

DowNex, Judge,

reviewing the facts found to be established, delivered the opinion of the court.

The plaintiff company, on the 14fch day of June, 1907, contracted with the United States, represented by Maj. C. A. F. Flagler, Corps of Engineers, as the contracting officer, for the erection of a foundation for a lighthouse on the Elbow of Cross Ledge, in Delaware Bay, by the erection, sinking, and filling with concrete of a metal caisson, for the sum of $44,000, the work to be completed on or before November 1, 1907. •

The metal plates, braces, beams, etc., entering into the construction of the caisson were to be furnished by the United States at Christiana Light Station, or some other point mutually agreed on, where the contractors were to assemble the caisson to the top of the sixth row of plates, launch it, tow it to the site, sink it to a depth of about 6 feet 3 inches below the surface of the shoal, excavate the working chamber and fill it with concrete, assemble the additional courses of plates, fill the caisson with concrete, and otherwise complete the work as required by the drawings and specifi[185]*185cations. The structure and size of the caisson, a full understanding of which is necessary to a proper conception of the case, is described in detail in the findings of fact, and reference may be had thereto, so that it need not be repeated here. There are many other matters of important detail set out in the findings with which we will not burden this opinion except as reference to them may be found necessary during the discussion of the case.

The specifications provided for the sinking of the caisson at a site to be selected by the agent of the lighthouse engineer in charge but to be upon the shoal known as “ Cross Ledge” and upon that part of the ledge known as the “ Elbow of the Ledge,” and stated that—

“In 1904, when a test boring was made, the top of the shoal was found to consist of a very hard stratum of sand. In this stratum of sand the foundation is to be sunk about 6 feet 3 inches.”

The Elbow of Cross Ledge was somewhat irregular in shape but was approximately three-eighths by three-quarters of a mile in its dimensions. A boring had been made in 1904 for the purpose of locating this lighthouse and marked by a buoy and a plat thereof made, but for some reason the lighthouse was not then built. When, in 1907, it was determined to proceed with its construction, agents of the engineer in charge were sent to locate the selected site, but. the buoy had disappeared and the pipe used in making the boring, could not be located by sweeping the ledge. The site was then located as nearly as could be by taking bearings with instruments on other points, but the site thus selected varied somewhat from the location of the boring in 1904. Because of the fact that in sinking the caisson the pipe used in 1904 was not encountered it was concluded that the circumference of the selected site did not include the former boring, and, on the other hand, the engineers were of the opinion that maximum allowances for errors in turning their angles indicated that the selected site could not be more than 70 feet from the former boring.

■ But whatever distance the selected site may have been from the boring of 1904 — and the exact distance does not seem to be at all material — it developed soon after the selec[186]*186tion of tbis site that the materials composing the ledge at the selected site were different from those indicated when the 1904 boring was made. Suspicions were first aroused when the plaintiff’s engineer and superintendent, in July, 1907, began driving piling at the selected site for the erection of a working platform. Suspicions were so confirmed by the driving of additional piles that, after conferences between the plaintiff’s engineer and the representative of the defendants’ engineer in charge, the facts were, by the former, communicated to the proper officers of the plaintiff company and, by the latter, to Maj. Flagler, who ordered another boring to be made. This boring, of which the plaintiff’s representative had knowledge, and the details of which are shown in the findings and not repeated here, developed materials different from those shown by the boring of 1904.

It was also demonstrated afterwards, during the sinking of the caisson and the excavating of the work chamber, that the materials were different from those indicated by the boring of 1904, but they were then found to be substantially as indicated by the second boring made in the early part of August, 1907, by direction of Major Flagler.

When the report of this latter boring was received by Maj or Flagler he wrote the plaintiff, on the 28th day of August, before the caisson had left the point of assembly, stating that the recent boring showed a much harder material at a depth of about 8 feet 6 inches than at a depth of 6 feet 3 inches, that this might prove to be entirely local, that if the entire foundation at 6 feet 3 inches should be found soft he would likely call on them to sink the caisson to a greater depth, that he would probably be able to make an inspection and decide the point when a depth of 6 feet 3 inches was reached, but that their agent in charge should be instructed to go deeper if directed by him or one of his agents. There was correspondence, referred to in the findings, in which the plaintiff requested to be informed as to additional compensation for going to a greater depth “ if you instruct us to do so,” but there was no agreement reached as to the compensation in that event and no instruction given,to go deeper. After the caisson had been placed in position and loaded, and within a few days had'sunk from 2 to 3 feet, there was another conference, sought by the plaintiff, with Major Flagler, the [187]*187details of which are to be found in the findings and need not be repeated here, but which resulted in no agreement as to compensation for sinking below contract depth and in no instruction so to sink.

The plaintiffs seek recovery in a considerable sum upon the ground, generally stated, that the conditions encountered in sinking the caisson were different from those represented in the specifications and that by reason thereof they were put to additional expense in the amount claimed, and they seek also recovery of $720.83 deducted on final settlement, by the United States, as expense of superintendence, etc., during the period of delay after the time provided for the completion of the contract. They allege in their petition in support of their right to recover that the caisson could not be stopped at the contract depth, and that it had to be sunk to a greater depth to insure a stable foundation, and that it was so sunk under the supervision and direction of the agents of the United States, and that it was sunk to a greater depth by direction of the engineer officer in charge, and that no suitable foundation was found until it had been sunk to a depth of 9 feet 8 inches.

A careful reading of the findings in all their details, together with a fairly adequate conception of the character of the contract undertaking, would seem necessarily to indicate the basis of the conclusion reached and to preclude any necessity for discussion, but it is perhaps best to remove any possibility of doubt by stating, as briefly as may be, the view taken of the case.

The statement in the specifications as to the character of the shoal, as indicated by the boring made in 1904, has been set out.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hampton v. United States
82 Ct. Cl. 162 (Court of Claims, 1935)
Southern Surety Co. v. United States
75 Ct. Cl. 47 (Court of Claims, 1932)

Cite This Page — Counsel Stack

Bluebook (online)
53 Ct. Cl. 179, 1918 U.S. Ct. Cl. LEXIS 199, 1918 WL 1017, Counsel Stack Legal Research, https://law.counselstack.com/opinion/monad-engineering-co-v-united-states-cc-1918.