Southern Surety Co. v. United States

75 Ct. Cl. 47, 1932 U.S. Ct. Cl. LEXIS 389, 1932 WL 2136
CourtUnited States Court of Claims
DecidedMay 31, 1932
DocketNo. H-417
StatusPublished
Cited by1 cases

This text of 75 Ct. Cl. 47 (Southern Surety Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Surety Co. v. United States, 75 Ct. Cl. 47, 1932 U.S. Ct. Cl. LEXIS 389, 1932 WL 2136 (cc 1932).

Opinion

Littleton, Judge,

delivered the opinion:

In this case the plaintiff seeks to repudiate the provisions of the contract and sues for recovery as upon a quantum meruit for the value of the work performed and asks judgment for $304,547.59, computed as follows:

Money expended by plaintiff in tbe completion of the project_$403, 005.98
Reasonable cost of work performed by ITuqua & Gonzales prior to assignment of the contract to plaintiff- 45,-493. 00
Overhead expense and contractor’s profit- 32, 000. 00
Reasonable value of use of machinery and equipment- 40,000.00
Total_ 520, 498. 98
Less amount paid to contractor and plaintiff_ 215,951.39
Balance_ 304,547.59

Fuqua & Gonzales, general contractors, after receiving notice of the call for bids for the construction of a road described in the findings, sent a member of the firm to investigate the site of the work, the nature and the extent thereof. After a very cursory examination of the site and upon being furnished a bidding sheet by the district engineer’s office, upon which was shown certain figures as to the approximate amount of rock and common to be excavated, and with the contract form, maps, plans, specifications, and estimates of [63]*63quantities of material shown on the plan and cross sections prepared by the Government engineers, the firm submitted a written proposal to perform the work at the price of 45 cents a cubic yard for common and $1.80 a cubic yard for rock excavation, and also submitted an alternative proposal to perform the work at the price of $1.01 a cubic yard for, all excavation regardless of classification. The alternative bid was accepted by the Government; the formal contract and surety bond were executed, and the contractor commenced work. After about five months the contractor was informed by the district engineer that if greater progress in the work should not be made, it would be necessary to annul the contract. This advice was also forwarded to the plaintiff company, surety on the contractor’s bond. The firm of Fuqua & Gonzales had not completed any portion of the road and the work which was performed consisted only of the excavation of common material.

The plaintiff surety company, after receiving an assignment of the contract from Fuqua & Gonzales, took over the contractor’s equipment, added thereto certain new equipment, and entered upon completion of the contract. It subsequently completed the work which was accepted by the Government, and payment in full at the prices specified in the contract was made with the exception of the last voucher for $25,707.15 tendered by the Government but refused by the plaintiff.

Plaintiff’s contentions are (1) misrepresentation by the Government in the figure submitted on the bidding sheet which disclosed a lesser amount of rock excavation than was actually disclosed by the Government engineer’s investigation and estimates, such discrepancy being such as to entitle the contractor and plaintiff to rescind the contract upon learning the facts and to recover the reasonable value of the cost of the work, whether the misrepresentation was innocent or otherwise; (2) that a resurvey of the road after the contract had been executed, of which no notice was given to the contractor or plaintiff, was made by the defendant’s engineer by which a material change was made in the line of the road which entitled plaintiff to rescind the contract [64]*64upon discovery of the facts; and (3) tbat failure of the district engineer to disclose to plaintiff and inform it of certain facts at the time it took over the contract, i. e., the alleged misrepresentations contained in the bidding sheet in respect to the respective amounts of rock and common, the material change in the location of the road, and the great increase in the amount of rock and decrease in the amount of common to be removed in the new location as compared to the old, entitled plaintiff upon discovery thereof to rescind the contract.

It appears that there was a discrepancy in the figures contained in the bidding sheet submitted to the contractor as to the approximate number of cubic yards of rock and common to be excavated as compared to the total of the approximate estimates shown on the plan and cross sections prepared by the defendant’s engineer; but the estimates and figures arrived at by the investigation of the engineers were only approximate and were not intended to be final. The instructions to bidders contained the statements that “ bidders are cautioned that the estimate of quantities attached hereto will serve, so far as .this project is concerned, only for the purpose of comparing bids. * * * Bidders are required before submitting bids to examine carefully the site of the proposed work * * *. Professions of ignorance regarding the requirements for the work will in no way serve to modify the provisions of the contract.” Having been thus put upon notice the contractor made only a very casual inspection of the site at both ends thereof without attempting to examine the character of the material to be excavated. While the route of the road was over a rugged country, it could be traversed and the contractor could have made a much closer examination.- The contractor in submitting its bid certified therein that it had carefully examined the plans, specifications, and form of contract, and also “personally examined the site of the work,” and that it understood that the “ quantities mentioned below are approximate only and are subject either to increase or decrease and hereby proposes to perform all kinds of work, either decreased or increased, in accordance with the provisions of the specifications at the unit prices bid.”

[65]*65' The ’ bid accepted by the Government was .at a specified amount per cubic yard for all excavation without classification. The basis of the plaintiff’s claim, therefore, is not for' additional sums because of erroneous classification, but by reason of the unclassified bid of $1.01 a cubic yard the contractor and plaintiff were put to greater expense in excavating more rock than the approximate estimate shown on the bidding sheet led them to believe would be encountered. ' Had the plaintiff believed that it was being compelled to do work not contemplated by the contract which would greatly increase its cost, it had the choice of abandoning the work and suing for damages, or of proceeding under the contract at the contract price. It elected the latter course and accepted without protest from time to time all monies due, except that it refused to receive the final voucher.

Upon the facts in this case we are of opinion that plaintiff may not repudiate the provisions of the contract and sue for recovery as upon a quantum merwit for the value of the work performed. Monad Engineering Company v. United States, 53 C. Cls. 179. A review of the leading cases demonstrates that the courts are generally agreed on the question as to the nature of a representation amounting to a warranty.

In the cases where the plaintiff has prevailed, the alleged misrepresentations involved the quality of material rather than the approximate quantity. In Burgwyn v. United States, 34 C. Cls. 348, the specifications carried a provision similar to the one involved in the present case, and in that case plaintiff contended that there was a warranty of certain quantities.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dubois Const. Corp. v. United States
98 F. Supp. 590 (Court of Claims, 1951)

Cite This Page — Counsel Stack

Bluebook (online)
75 Ct. Cl. 47, 1932 U.S. Ct. Cl. LEXIS 389, 1932 WL 2136, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-surety-co-v-united-states-cc-1932.