Callahan Construction Co. v. United States

47 Ct. Cl. 177, 1912 U.S. Ct. Cl. LEXIS 128, 1911 WL 1344
CourtUnited States Court of Claims
DecidedJanuary 8, 1912
DocketNo. 28771
StatusPublished
Cited by7 cases

This text of 47 Ct. Cl. 177 (Callahan Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Callahan Construction Co. v. United States, 47 Ct. Cl. 177, 1912 U.S. Ct. Cl. LEXIS 128, 1911 WL 1344 (cc 1912).

Opinion

Barney, J.,

delivered the opinion of the court:

This suit grows out of a contract for the construction of earthwork along 9 miles of the feeder of the Illinois & Mississippi Canal under the Engineering Department of the Army. A copy of this contract and the specifications thereto belonging, together with a copy of a paper giving information to bidders, entitled “Available quantities of material for embankment,” are attached to the petition and made a part- thereof.

This “ earthwork,” according to the terms of the contract, called for excavation in some places and the building of embankments in others; while the price for this work varied on the different miles, in each instance the same price was paid both for excavation and for earth placed in the embankment.

[180]*180Earth required to be excavated was disposed of in one of two ways: (1) It was placed in the embankments required by the plans to be constructed, or (2) it was “ wasted ”; that is, disposed of in some way not connected with the general plan of the work. If it was used in the required embankments, it was twice paid for, once as an excavation and once as an embankment. Earth required to be placed in embankment was obtained in one of three ways: (1) From excavations required within the limits of the canal prism; (2) from “ borrrow pits ” dug on the right of way belonging to the Government outside of the canal prism; (8) from “borrow pits” outside the right of way dug on land which the claimant was under the necessity of purchasing for that purpose. The largest part of the plaintiff’s claim grows out of the last-mentioned manner of obtaining earth for such embankment, and its determination depends largely upon the construction of the contract relating to that feature of the work.

In the advertisements for proposals to do this work bidders were notified to apply to Asst. Engineer L. L. Wheeler for information relating to the same, and the findings show that up'on such application by the plaintiff before making its bid he handed them the paper above referred to, entitled “Available quantities of material for • embankment.” The findings show': (1) That the available quantities of material for embankment were not as great in quantity as represented in this paper, and (2) that the engineer officer in charge of the work refused to allow the plaintiff to use much of the material therein represented to be available, in consequence of which the plaintiff was compelled to purchase more land outside of the right of way from which to “ borrow ” such material than otherwise would have been necessary.

I. It is contended by the plaintiff that by thus furnishing it with this statement of “Available quantities of material for embankment ” the Government thereby warranted that the quantities therein mentioned would be available for such use and would be allowed to be used for that purpose. It is unnecessary to quote authorities to the general rule that when false representations are made as to the subject matter [181]*181of a contract, or as to any material matter concerning the same, such representations ordinarily amount to a warranty (Norrington v. Wright, 115 U. S., 203); or, as has been said: “ No doubt by a representation a party may bind himself just as much as by an express covenant.” (Smith v. Richards, 3 Pet., 26, 36.) If the representations contained in the paper above referred to had been made a part of the written contract, and had not been modified by any other provision contained therein, there might be room for the application of the rule of law above referred to, a question, however, which it is unnecessary to decide in this case. The paper containing the statement of “Available quantities of material for embankment” was given to the plaintiff as information to form a basis upon which to make its bid, and after this was done the contract was entered into with specifications attached which were made a part of the same. This is the contract we are authorized to construe and no other.

The rule that all prior negotiations are merged in the written contract, and that such contract is presumed in law to express the final understanding of the parties, and that prior transactions can only be referred to for the purpose of explaining and construing uncertain terms of the contract, is elementary. (Brawley v. United States, 96 U. S., 168, 173; Simpson v. United States, 172 U. S., 372, 379; Griefen v. United States, 43 C. Cls., 107, 113.)

Without reviewing the cases cited by the plaintiff upon this subject, it is sufficient to say that in all of them prior transactions were referred to only for the purpose of explaining and construing the language of the contract as afterwards executed, and the contract as thus explained and construed was enforced. In the case at bar it is sought by the plaintiff to refer to information given it prior to the execution of the contract for the purpose of adding conditions not contained in the instrument itself.

We find nothing in the contract or specifications in this case making any representation whatever as to the materials available for embankments, much less any statement which can be regarded as a warranty regarding the same. On the contrary, the plaintiff was therein told in the most [182]*182positive manner to make its own investigations relating to all the circumstances regarding the work to be done, as the following extracts from the specifications show :

“ 3. Maps of the localities may be seen at this office. Bidders or their authorized agents are expected to visit the place and to make their own estimates of the facilities and difficulties attending the execution of the work, including the uncertainty of weather and all other contingencies.
“ 38. It is understood and agreed that the quantities given are approximate only, and it must be understood that no claim shall be made against the United States on account of any excess or deficiency, absolute or relative, in the same. Bidders are expected to examine the drawings and are invited to make the estimate of quantities for themselves.
“ 38. The material throughout the canal is believed to be loam, clay, sand, and gravel, but bidders must satisfy themselves as to the nature of the material to be encountered.
“ 84. Bidders are notified that under these specifications suitable material in sufficient amounts for the canal embankments on several of the miles can not probably be procured on the canal right of way but must necessarily be purchased. In other cases, if procured on the right of way, long hauls will be necessary. All persons bidding shouid first visi t and carefully consider local conditions, character, quality, and amount of materials available, and the facilities for the work.
“ Proposals are not desired from parties who do not properly inform themselves nor from those not prepared for a rigid compliance with all of the conditions of any contracts that may be awarded them under these specifications.”

It will thus be seen that even if we consider the information given as to the available material suitable for embankments to be a part of the contract, the plaintiff was clearly advised not to regard such information as a warranty.

It should also be remarked that the findings show that in the bid submitted for the work the plaintiff made the following statement:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fink v. Denbeck
293 N.W.2d 398 (Nebraska Supreme Court, 1980)
Anthony M. Meyerstein, Inc. v. United States
137 F. Supp. 427 (Court of Claims, 1956)
Dubois Const. Corp. v. United States
98 F. Supp. 590 (Court of Claims, 1951)
Manufacturers Casualty Ins. Co. v. United States
63 F. Supp. 759 (Court of Claims, 1946)
Southern Surety Co. v. United States
75 Ct. Cl. 47 (Court of Claims, 1932)
California Bridge & Construction Co. v. United States
50 Ct. Cl. 40 (Court of Claims, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
47 Ct. Cl. 177, 1912 U.S. Ct. Cl. LEXIS 128, 1911 WL 1344, Counsel Stack Legal Research, https://law.counselstack.com/opinion/callahan-construction-co-v-united-states-cc-1912.