Charles Nelson Co. v. United States

261 U.S. 17, 43 S. Ct. 301, 67 L. Ed. 513, 1923 U.S. LEXIS 2525
Supreme Court of the United States·Decided February 19, 1923·No. 287·Published·Cited by 11 cases

Opinion

Mr. Chief Justice Taft

delivered the opinion of the Court.

This is an appear from a judgment of the Court of Claims dismissing the petition of the plaintiff, the Charles Nelson Company, after a hearing of the evidence and upon findings made. The plaintiff was the lowest and accepted bidder upon advertised solicitation of the Navy *18 Department fdr the furnishing ■ and delivery of lumber at the Puget S'ound Navy Yard for a period ending December 31, 1917. This suit is to recover the sum of $20,321.33, the'amount with interest of the difference between the market value and the price bid upon what the plaintiff claims was an unjust excess over and above the amount of lumber it should have delivered and that which at the insistence of the Navy Department it did deliver.

The bids were opened January 3, 1917. The contract was signed February 23, 1917. Thereby the plaintiff agreed to furnish and deliver f. o. b. alongside wharf, navy yard, Puget Sound, lumber of certain kinds in such quantities and at such times during the period ending December 31, 1917, as the supply officer of the Navy might direct. “All deliveries to be made promptly and orders of 50,000 ft. b. m. or less of assorted sizes, not more than 10,000 ft. b. m¡ of any one size, except with the consent of the contractor, must be delivered within 10 days after receipt of order. All other órders must be delivered within 25 daygi after date of receipt of order from the supply officer.'-'. The contract contained this provision which was evidently taken from the form of bids solicited:

“ It shall be distinctly understood and agreed that it is the intention óf the contract that the contractor shall furnish and deliver any quantities of Douglas fir which may be ordered for the naval service at the place named during the period ending Dec. 31, 1917, irrespective of the estimated quantity named, the Government not being obligated to oider any specific quantity of Douglas fir contracted for.''.’
Then follows/.
Class 5 — Continued.
Stock Classification No. 39.
Fir, Douglas,’ as follows:
1. 1,675,000 feet b. m. (about), of such sizes or.grades as may be ordered — per M feet.”

*19 The Navy Department on orders placed by it before December 31, 1917, received from the plaintiff 3,688,259 feet b. m. of Douglas fir. The amount furnished above 1,675,000 feet was worth at market price, delivered at the navy yard, $18,310.21 more than the plaintiff was paid therefor at the prices bid and accepted.

After the execution of the contract and as a development of the World War the Government entered upon the building of submarine chasers at this navy yard, a type of vessel never before built there, and much of the lumber required of the plaintiff under its contract was used in the construction of these vessels.

The plaintiff denies that the writing signed by it was a binding contract, because there was no mutuality of obligation. The Government answers this by citing the case, of United States v. Purcell Envelope Co., 249 U. S. 313. In that case the Post Office Department invited bids “ for furnishing stamped envelopes and newspaper wrappers in such quantities as may be called for by the department during a period of four years, beginning on the first day of October, 1898.” The bid of the Purcell Company was accepted. The formal contract was signed by the Company and bond given. Subsequently the Postmaster General refused to sign this contract, and bought the envelopes and wrappers elsewhere. This Court held that the acceptance of the bid made the contract, that the words above quoted must be construed 'to mean that the Company should furnish all the envelopes and wrappers of the specified sizes which the Department would need during the four years’ period, and that the Government was as much bound to take the envelopes and wrappers as the bidder was bound to furnish them. Heavy damages for the breach of the contract were awarded against the United States. But it is to be observed that there was in the contract or invitation for bids no express denial of the obligation of the Post Office. *20 Department to take the envelopes in that case, so that the question of a lack of mutuality did not arise in the Purcell Case as it does here.

But we are not obliged definitely to pass upon the question whether the instrument relied on by the Government constituted a contract binding on the plaintiff for the whole amount ordered at the price bid, because under the findings of the Court of Claims, the plaintiff must be held to have waived any right to claim more than the price it bid for any part of the lumber it furnished.

Free access — add to your briefcase to read the full text and ask questions with AI

Charles Nelson Co. v. United States, 261 U.S. 17, 43 S. Ct. 301, 67 L. Ed. 513, 1923 U.S. LEXIS 2525 (1923).

261 U.S. 17 (Charles Nelson Co. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Hampton v. United States
82 Ct. Cl. 162 (Court of Claims, 1935)
Kingsbury v. United States
68 Ct. Cl. 680 (Court of Claims, 1930)
Yale & Towne Manufacturing Co. v. United States
67 Ct. Cl. 618 (Court of Claims, 1929)
William C. Atwater & Co. v. United States
65 Ct. Cl. 621 (Court of Claims, 1928)
Penn Chemical Co. v. United States
63 Ct. Cl. 15 (Court of Claims, 1927)
Early & Daniel Co. v. United States
271 U.S. 140 (Supreme Court, 1926)
American Rolling Mill Co. v. United States
61 Ct. Cl. 882 (Court of Claims, 1926)
Huron Navigation Corp. v. United States
60 Ct. Cl. 770 (Court of Claims, 1925)
Early & Daniel Co. v. United States
59 Ct. Cl. 932 (Court of Claims, 1924)
Atchison v. United States
58 Ct. Cl. 583 (Court of Claims, 1923)
Willard, Sutherland & Co. v. United States
262 U.S. 489 (Supreme Court, 1923)