Needles ex rel. Needles v. United States

101 Ct. Cl. 535, 1944 U.S. Ct. Cl. LEXIS 68, 1944 WL 3698
CourtUnited States Court of Claims
DecidedMay 1, 1944
DocketNo. 44994
StatusPublished
Cited by36 cases

This text of 101 Ct. Cl. 535 (Needles ex rel. Needles v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Needles ex rel. Needles v. United States, 101 Ct. Cl. 535, 1944 U.S. Ct. Cl. LEXIS 68, 1944 WL 3698 (cc 1944).

Opinions

Littleton, Judge,

delivered the opinion of the court:

June 27, 1986, the defendant, acting by and through the United States Engineer Corps, U. S. Army, War Department, issued through certain officers at Honolulu, T. H., an invitation for bids accompanied by a standard printed contract form and detailed specifications prepared by defendant for the rental of tunnel shovels, to be operated by the contractor, and mine cars of a specified capacity, to be operated or trammed by defendant, together with associated equipment, such as tracks, etc., for use in connection with the project outlined in finding 1.

Plaintiff, James Garfield Needles, submitted a bid for rental on an hourly basis of two 80 hp. standard tunnel shovels, mine cars for hauling the excavated material out of the tunnels, and all other necessary equipment. Plaintiff prepared and submitted to the contracting officer through his authorized representative, who wrote the specifications, a [581]*581blue print of a drawing showing the design and size of the mine cars to be made and furnished, and this drawing was examined, appro^d, and retained by the Government. Thereafter plaintiff constructed the mine cars in accordance with this drawing. Plaintiff was the only bidder, and his bid for rental of this equipment at an hourly rate of $13.10 was accepted. He was notified by the contracting officer of such acceptance on July IT, 1936, and this notice was received by plaintiff on July 21.

The bid form furnished by defendant required plaintiff to state the number of calendar days! after date of receipt of notice of award of the contract within which he would be “ready to operate at full capacity under the provisions of the attached specifications,” and plaintiff stated in his bid that he would be operating at full capacity within 32 calendar days after receipt of notice of award. The defendant’s notice of award and Article 1 of the contract fixed the period of 32 calendar days after July 21, 1936, within which plaintiff should have the equipment operating at full capacity, as contemplated by the specifications. Under the contract plaintiff was entitled, with the consent of defendant, to commence operations at any time after July 21, 1936, the date of the contract and date of receipt of notice, but plaintiff had until August 22, 1936, within which to get the shovels and associated equipment, such as mine cars, tracks, turntables, etc., operating at full capacity. He commenced operations with the consent of the contracting officer on August 15, 1936.

The evidence in this case shows without contradiction that it is recognized and understood by everyone that in a project of the character here involved it takes several days from the time operations are first commenced to get all the equipment and the organization engaged in operating and handling it in smooth working order and operating at normal and full capacity.

A few days prior to Saturday, August 15, 1936, the defendant had blasted certain material at the portal of a certain gallery or tunnel, and on Friday, August 14, with the consent of the Government, plaintiff arranged to commence operating one of the tunnel shovels and the mine cars for receiving and [582]*582hauling away the excavated material on Saturday, August 15, at 3 p. m. At that time the second tunnel shovel, or mucking machine, had not been completely assembled, and the operation of the second shovel was to commence on Monday morning, August 17. As shown in the findings and by the provisions of the contract quoted therein plaintiff was to furnish the equipment described and the operators for the shovels, and defendant was to do all the work of drilling and blasting, and the handling, tramming, and dumping of the mine cars as loaded by the shovels.

Sometime before 8 a. m., August 15, plaintiff instructed his men that operations with one of the shovels would commence that afternoon at three o’clock, whereupon he went to Honolulu, a distance of about three or four miles, on business. While plaintiff was absent defendant’s contracting officer came to the site of the work about 8 a. m. and remained there not more than half an hour. During the time he was there the tunnel shovel was not operated, but some mine cars were being loaded with blasted material by hand apparently in a sort of cleaning-up process preparatory to commencing operations with the shovel as had theretofore been planned. During the half-hour the contracting officer was there he observed defendant’s laborers tram and dump one mine car.. It is apparent from the record that during the time the contracting officer was at the site the men on the job did not consider that operations were actually underway. Plaintiff’s superintendent, a man of long experience in tunneling operations and in the operation of tunnel shovels and mine cars of the character to be used on this project as called for by the contract, was present while the contracting officer was at the site of the work, but the defendant’s Superintendent, who was to have charge of operations for the Government, was not present. The contracting officer states in his testimony that when this loaded mine car was trammed, dumped, and brought back while he was present the men furnished by defendant for the handling and dumping of mine cars spent nearly fifteen minutes in the operation and that, while he did not go to the point where the car was being dumped, they seemed to him to be having some trouble dumping it, but that he did not examine the car, the dumping arrangement [583]*583thereon, or the tipple, or inquire of the men as to the trouble they were having, if any, or why it should have taken them several minutes to dump and return the car. Whatever time may have been consumed by defendant’s employees in tramming, dumping, and returning the first loaded mine car was due, as the evidence shows, entirely to the inexperience or slowness of defendant’s men and was not due to any mechanical defect or inefficiency of equipment. Operations were not then under way and the men were familiarizing themselves with the handling of the mine cars, the operation of the dumping arrangement thereon, and the tipple. The evidence shows conclusively that due to their lack of experience it was necessary to proper handling of the cars that they become familiar with these matters. At this point the contracting officer left the site of the work and did not at any time return thereto until long after the use of mine cars had been abandoned, as hereinafter set forth. Soon thereafter the defendant’s superintendent arrived.

The contracting officer, a Lieutenant Colonel in the Engineer Corps, U. S. Army, had had no experience in tunneling operations or in the operation and handling of equipment, including mine cars, such as called for by the contract and furnished by plaintiff. Defendant’s superintendent, a civilian, was also without previous experience in the operation of tunnel shovels or in tramming and dumping of mine cars in tunneling operations. Soon after defendant’s superintendent arrived he started operations with one of the tunnel shovels and mine cars. Plaintiff’s superintendent advised plaintiff at Honolulu by telephone that operations had commenced, and plaintiff returned to the site of the work as soon as he could and arrived there at about 10 a. m.

The evidence of record establishes that all the equipment furnished by plaintiff, including the mine cars, tracks, and tipple, fully conformed to and met all the requirements of the contract and specifications, and was fully capable of operating in accordance with and as contemplated by the specifications as written.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Eden Isle Marina, Inc. v. the United States 0
113 Fed. Cl. 372 (Federal Claims, 2013)
ACE Constructors, Inc. v. United States
70 Fed. Cl. 253 (Federal Claims, 2006)
Tecom, Inc. v. United States
66 Fed. Cl. 736 (Federal Claims, 2005)
American Line Builders, Inc. v. United States
38 Cont. Cas. Fed. 76,406 (Court of Claims, 1992)
Joseph Pickard's Sons Co. v. United States
532 F.2d 739 (Court of Claims, 1976)
S&E Contractors, Inc. v. United States
406 U.S. 1 (Supreme Court, 1972)
Wilco Floor Service, Inc. v. United States
197 Ct. Cl. 902 (Court of Claims, 1972)
Sanders Associates, Inc. v. The United States
423 F.2d 291 (Court of Claims, 1970)
Luria Brothers & Company, Inc. v. The United States
369 F.2d 701 (Court of Claims, 1966)
Luria Bros. & Co. v. United States
369 F.2d 701 (Court of Claims, 1966)
United States v. Carlo Bianchi & Co.
373 U.S. 709 (Supreme Court, 1963)
Dale Construction Co. v. United States
161 Ct. Cl. 825 (Court of Claims, 1963)
G. L. Christian and Associates v. The United States
312 F.2d 418 (Court of Claims, 1963)
G. L. Christian & Associates v. United States
160 Ct. Cl. 1 (Court of Claims, 1963)
River Construction Corp. v. United States
159 Ct. Cl. 254 (Court of Claims, 1962)
Harvey Ward Locke v. United States
283 F.2d 521 (Court of Claims, 1960)
Oliver-Finnie Company v. United States
279 F.2d 498 (Court of Claims, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
101 Ct. Cl. 535, 1944 U.S. Ct. Cl. LEXIS 68, 1944 WL 3698, Counsel Stack Legal Research, https://law.counselstack.com/opinion/needles-ex-rel-needles-v-united-states-cc-1944.