Joseph Pickard's Sons Co. v. United States

532 F.2d 739, 22 Cont. Cas. Fed. 80,210, 209 Ct. Cl. 643, 1976 U.S. Ct. Cl. LEXIS 85
CourtUnited States Court of Claims
DecidedApril 14, 1976
DocketNo. 184-74
StatusPublished
Cited by43 cases

This text of 532 F.2d 739 (Joseph Pickard's Sons Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Joseph Pickard's Sons Co. v. United States, 532 F.2d 739, 22 Cont. Cas. Fed. 80,210, 209 Ct. Cl. 643, 1976 U.S. Ct. Cl. LEXIS 85 (cc 1976).

Opinion

Per Curiam :

This case comes before the court on defendant’s motion, filed January 6, 1976, moving that the court adopt, as the basis for its judgment in this case, the recommended decision of Trial Judge George Willi, filed November 24, 1975, pursuant to Rule 166(c) on plaintiff’s motion and defendant’s cross-motion for summary judgment since plaintiff has failed to file a request for review thereof by the court and the time for so filing under the Rules of the court has expired. Upon consideration thereof, without oral argument, since the court agrees with the trial judge’s recommended decision, as hereinafter set forth, it hereby grants defendant’s said motion and affirms and adopts the recommended decision as the basis for its judgment in this case. Therefore, plaintiff’s motion for summary judgment is denied, defendant’s motion for summary judgment is granted and plaintiff’s petition is dismissed.

OPINION OP TRIAL JUDGE

Willi, Trial Judge:

Plaintiff brings this suit to attack the validity, according to Wunderlich Act1 standards, of one [645]*645facet of an April 24, 1973 decision by the Armed Services Board of Contract Appeals (the Board) denying recovery of costs allegedly attributable to delay caused by the issuance of a change order dealing with welding specifications in a supply contract for an improved type of prefabricated landing mat for aircraft. Joseph Pickard's Sons Co., 73-1 BCA ¶ 10,026. Plaintiff takes no exception to the allowance approved by the Board for the direct costs that it claimed in respect to the change. Similarly, it does not challenge any of the subsidiary factual determinations made by the Board concerning the delay claim; only the Board’s ultimate conclusion that the change was not sufficiently shown to have caused the delay costs for which compensation is sought.

Plaintiff, a first-time Government prime contractor, is otherwise a Philadelphia-based manufacturer of pile wire and brazed die needles used in the fabrication of rugs, carpets, canvas and other heavy textile items.

On September 2,1965, after a period of successful research and experimentation by the Army, the Defense Construction Supply Center issued an invitation for bids on a contract to supply a new type of steel landing mat for aircraft. A major improvement was the elimination of the round perforations that characterized the mats of World War II, permitting particles of surface dirt to rise and contaminate the moving parts of aircraft traversing them.

As the low responsible bidder, plaintiff was awarded a contract on October 19, 1985 for 38,336 13-member bundles of landing mats at a total price of $9,109,783.68. The contract contained standard Disputes and Changes clauses and also extended the Government a 100 percent option quantity at the same unit price. On October 28, 1965, that option was exercised so that the contract to be performed called for 79,762 bundles of mats to be delivered from March through October 1966 at a price of $18,105,326.08.

Plaintiff elected to perform its contract in a separate facility that it appropriated exclusively to that use. Promptly after receiving the award plaintiff set about establishing a high-volume production line in the specialized facility. It experienced various difficulties in perfecting the line and con[646]*646sequently produced no mats for delivery until late March 1966. Production problems persisted so that, as against a contract completion date of October 1966, by December 31, 1966 plaintiff had delivered less than one-third of its total contractual commitment. The completion date was ultimately extended by agreement and performance eventually completed in May of 1968.

As soon as plaintiff’s deliveries began, its mats, together with those of others suppliers, were promptly shipped to Vietnam and put in service there. The overseas using activities shortly notified the procuring authorities that the mats generally, including those supplied by plaintiff, presented so many burrs and sharp edges that excessive aircraft tire wear was resulting.

After study and investigation of the problem, the procuring authorities concluded that faulty welding was a principal source of the difficulties encountered in the field. To remedy the situation they decided to replace the general “good commercial practice” welding workmanship standard of the contract specifications with a set of considerably more detailed requirements, including one that called for a 4,000 pound static pressure test of any coverplates deemed suspect on visual inspection. Promulgation of the new requirements was first attempted by way of an October 14,1966 letter from the Contracting Officer to the plaintiff. The letter characterized the detailed welding criteria spelled out in it as only clarifying rather than enlarging the original contract specifications. When plaintiff received the letter it promptly demurred, insisting that the new welding instructions did indeed increase the stringency of the specifications and adding that compliance with them would consequently entail additional costs. Plaintiff therefore requested that the new directives be instituted by a formal change order rather than by letter. This was done by a contract modification issued October 31, 1966. Plaintiff thereupon requested that the effective date of the modification be deferred until November 21, 1966 so that it could acclimate its personnel and operations to what it regarded as the new and different ground rules defining acceptable welding. Its request was granted and the modification implemented accordingly.

[647]*647Tbe Board agreed with the plaintiff that the supplementary welding requirements changed the contract’s specifications in a manner that increase both the labor and material costs of welding. It therefore awarded plaintiff an equitable adjustment of $124,001.88 on those accounts.

In addition, plaintiff claimed that it was due $851,418.54 to compensate it for decreased productivity (and resultant delay in contract completion) measured by the increase in end-product rejections that it contended must have been attributable to the more demanding welding requirements imposed by the change order. The proposed damage figure consisted of that portion of plaintiff’s total 1967 2 production costs represented by the difference between the percentage relationship of rejects to total production before the change order and after. A representative of the Defense Contract Audit Administration (DCAA) verified the essential correctness of the fact, but not the alleged cause, of the relative increase in average rejection rate and average decrease in weekly production. The Board denied the claim for want of any direct proof associating identifiable added costs with production delays resulting from the new welding requirements. The DCAA audit verification of plaintiff’s production and rejection figures did not, of course, amount to an admission of Government responsibility for decreased productivity. Boyajian v. United States, 191 Ct. Cl. 233, 247, 423 F. 2d 1231, 1239 (1970).

Addressing plaintiff’s statistical presentation, indicating that on an overall average basis its rate of rejections was measurably greater after the change order than before, the Board made several points. First, it called attention to various discrepancies and inconsistencies in the several editions of statistical data proffered by plaintiff to substantiate a post-change order increase in rejection rate.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lockheed Martin Aeronautics Company
Armed Services Board of Contract Appeals, 2022
Electric Boat Corporation
Armed Services Board of Contract Appeals, 2019
TranLogistics LLC
Armed Services Board of Contract Appeals, 2018
Dobyns v. United States
118 Fed. Cl. 289 (Federal Claims, 2014)
SGS-92-X003 v. United States
85 Fed. Cl. 678 (Federal Claims, 2009)
Orlosky Inc. v. United States
68 Fed. Cl. 296 (Federal Claims, 2005)
Bluebonnet Savings Bank FSB v. United States
67 Fed. Cl. 231 (Federal Claims, 2005)
CEMS, Inc. v. United States
59 Fed. Cl. 168 (Federal Claims, 2003)
Datalect Computer Services, Inc. v. United States
56 Fed. Cl. 178 (Federal Claims, 2003)
Hi-Shear Technology Corp. v. United States
53 Fed. Cl. 420 (Federal Claims, 2002)
Cavalier Clothes, Inc. v. United States
51 Fed. Cl. 399 (Federal Claims, 2001)
Doninger Metal Products, Corp. v. United States
50 Fed. Cl. 110 (Federal Claims, 2001)
Hughes Communications Galaxy, Inc. v. United States
47 Fed. Cl. 236 (Federal Claims, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
532 F.2d 739, 22 Cont. Cas. Fed. 80,210, 209 Ct. Cl. 643, 1976 U.S. Ct. Cl. LEXIS 85, Counsel Stack Legal Research, https://law.counselstack.com/opinion/joseph-pickards-sons-co-v-united-states-cc-1976.