Electric Boat Corporation

CourtArmed Services Board of Contract Appeals
DecidedJanuary 28, 2019
DocketASBCA No. 58672
StatusPublished

This text of Electric Boat Corporation (Electric Boat Corporation) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Electric Boat Corporation, (asbca 2019).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Electric Boat Corporation ) ASBCA No. 58672 ) Under Contract No. N00024-03-C-2101 )

APPEARANCES FOR THE APPELLANT: Stephen J. McBrady, Esq. Skye Mathieson, Esq. Michelle D. Coleman, Esq. Crowell & Moring LLP Washington, DC

APPEARANCES FOR THE GOVERNMENT: Craig D. Jensen, Esq. Navy Chief Trial Attorney Russell A. Shultis, Esq. David B. Stinson, Esq. David M. Marquez, Esq. Alana M. Sitterly, Esq. Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE D'ALESSANDRIS ON THE GOVERNMENT'S MOTION FOR SUMMARY JUDGMENT REGARDING ENTITLEMENT

Pending before the Board is the motion for summary judgment regarding entitlement filed by respondent, the Department of the Navy (government or Navy). The Navy seeks entry of summary judgment holding that appellant, Electric Boat Corporation (Electric Boat or EB), and its subcontractor Huntington Ingalls, Inc. (HII), cannot establish economic injury directly caused by a change in federal law, and requests dismissal of the appeal.

On December 10, 2018, we granted, in part, the Navy's earlier-filed motion for summary judgment, dismissing Electric Boat's claim for its own costs based upon the statute of limitations, but denying the motion with regard to the costs of its subcontractor HII. Electric Boat Corporation, ASBCA No. 58672, slip op. (December 10, 2018). Thus, despite the fact that the vast majority of the parties' briefing pertains to Electric Boat's costs, only HII's costs are at issue in this opinion. For the reasons stated below, we deny the Navy's motion. STATEMENT OFF ACTS FOR PURPOSES OF THE MOTION

This appeal pertains to Contract No. N00024-03-C-2101 (the contract) for the construction of six Block II Virginia Class submarines (R4, tab 52). Familiarity with our prior opinion is assumed, and only facts relevant to the current motion are included here. The contract was primarily firm-fixed-price, but with some cost-reimbursement line items. Construction of each submarine was a fixed-price line item with cost sharing of costs above or below the target cost. (R4, tab 52 at 280-96) The contract included Clause H-9, NAVSEA 5252.233-9103, DOCUMENTATION OF REQUESTS FOR EQUITABLE ADJUSTMENT (AT)-ALTERNATE I (APR 1999), which stated:

(a) For the purposes of this requirement, the term "change" includes not only a change that is made pursuant to a written order designated as a "change order" but also (i) an engineering change proposed by the Government or the Contractor pursuant to the "Other Change Proposals" or other requirements of this contract and (ii) any act or omission to act on the part of the Government in respect of which a request is made for equitable adjustment under the "CHANGES" clause or any other article or requirement of this contract.

(b) Whenever the Contractor requests or proposes an equitable adjustment of $100,000 or more per vessel in respect of a change made pursuant to a written order designated as a "change order" or in respect of a proposed engineering change and whenever the Contractor requests an equitable adjustment in any amount in respect of any other act or omission to act on the part of the Government, the proposal supporting such request shall include the following information for each individual item or element of the request:

(3) Description of work which is substituted or added by the change. A list of identifiable components and equipment (not bulk materials or items) involved, should be included. Separate descriptions are to be furnished for design work and production work;

2 (4) Description of interference and inefficiencies in performing the change;

(c) Each proposal submitted in accordance with this requirement shall include a copy of the Contractor's ship's labor budget at the cost level in effect as of the date the event began, the cost incurred at the cost level as of the same date, and the proposed effect of the change at the cost class level.

( d) It is recognized that individual claims for equitable adjustment may not include all of the factors listed in subparagraphs (b) ( 1) through (b) (8) above, or that the Contractor may not reasonably be able to furnish complete information on all of the factors listed in subparagraph (b) ( 1) through (b) (8) above. Accordingly, the Contractor is only required to set forth in its request for equitable adjustment information with respect to those factors which are relevant to the individual request for equitable adjustment, or in the level of detail which is reasonably available to the Contractor.

( e) In addition to any information required under paragraph (b) above, each proposal submitted in support of a claim for equitable adjustment, under any requirement of this contract, in an amount which requires certified cost or pricing data, shall contain such cost or pricing data as the Contracting Officer shall require with respect to each individual claim item, and shall be in sufficient detail to permit the Contracting Officer to cross-reference the claimed increased costs, or delay in delivery, or both, as appropriate, with the information submitted pursuant to subparagraphs (b) ( 1) through (b) (8) hereof.

(R4, tab 52 at 428-30) The contract does not contain FAR 52.243-6, CHANGE ORDER ACCOUNTING, permitting the contracting officer to require a contractor to maintain separate accounts "of all incurred segregable, direct costs (less allocable credits) of work, both changed and not changed, allocable to the change."

As described in more detail in our previous opinion, the Occupational Health and Safety Administration (OSHA) promulgated a new regulation, referred to as Subpart P, Fire Protection in Shipyard Employment (29 C.F.R. § 1915.501 et seq.), that became effective on December 14, 2004 (Fire Protection in Shipyard Employment, Final Rule, 69 Fed. Reg. 55,667-708, OSHA (Sept. 15, 2004)). Electric Boat contends that compliance with Subpart P, which modified the regulations requiring a fire watch during "hot work," increased its cost of performance by an amount sufficient to qualify for an adjustment, pursuant to Clause H-30 of the contract, to the firm-fixed-price contract line item for construction of the submarines.

Relevant to this motion, on January 30, 2006, HII submitted its Estimate of Cost Summary to Electric Boat, setting forth its "[a]dditional costs associated with complying with the increased requirements invoked by OSHA 29 C.F.R. 1915 SUBPART P" totaling $27,524,878 (gov't mot., ex. 17). HII's claimed amount was based on an estimate of 392,520 additional labor hours (id.).

HII' s estimated cost impact was developed by determining which of its departments had a high percentage of fire watch qualified personnel (gov't mot., ex. 101 at 3172-73). HII used its Labor Resources Plan from 2005 as a baseline for labor to complete the submarines. HII then estimated, on a department-by-department basis, the percentage of fire watch work performed before the effective date of Subpart P and an estimate of the percentage increase in fire watch performed after the effective date of Subpart P, with the exception of one department that estimated a set number of fire watch hours per week for grinding, rather than welding, activity. (Id. at 3174, 3204)

Mr. James Myers, HII's executive in charge of cost and financing issues provided deposition testimony to the effect that it would be impractical to separately account for OSHA Subpart P costs. Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Pure Gold, Inc. v. Syntex (u.s.a.), Inc.
739 F.2d 624 (Federal Circuit, 1984)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
The Ravens Group, Inc. v. United States
112 Fed. Cl. 39 (Federal Claims, 2013)
Orlosky Inc. v. United States
68 Fed. Cl. 296 (Federal Claims, 2005)
Joseph Pickard's Sons Co. v. United States
532 F.2d 739 (Court of Claims, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
Electric Boat Corporation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/electric-boat-corporation-asbca-2019.