Sanders Associates, Inc. v. The United States

423 F.2d 291, 191 Ct. Cl. 157, 1970 U.S. Ct. Cl. LEXIS 21
CourtUnited States Court of Claims
DecidedMarch 20, 1970
Docket119-69
StatusPublished
Cited by3 cases

This text of 423 F.2d 291 (Sanders Associates, Inc. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sanders Associates, Inc. v. The United States, 423 F.2d 291, 191 Ct. Cl. 157, 1970 U.S. Ct. Cl. LEXIS 21 (cc 1970).

Opinions

ON DEFENDANT’S MOTION FOR SUMMARY JUDGMENT

COLLINS, Judge.

This is an action by plaintiff, Sanders Associates, Inc., to recover either in quantum meruit the reasonable value of the goods and services delivered to and accepted by the Navy Department or for breach of contract because defendant failed to definitize the Letter Contract (Count I); or, in the alternative, to recover the cost of the goods and services delivered to and accepted by the Navy under the Memorandum of Agreement of September 12, 1968, which plaintiff claims is a binding contract (Count II). The case is now before this court on defendant’s motion for summary judgment and plaintiff’s opposition thereto. For reasons hereinafter stated, defendant’s motion for summary judgment is denied, and the case is remanded to the commissioner for a trial to make findings of fact and a recommended conclusion of law.

Plaintiff is a corporation organized and existing under the laws of the State of Delaware, and it maintains its principal offices at Nashua, New Hampshire. On January 27, 1966, plaintiff entered into Letter Contract NOw(A) 66-0356 with what is now the Naval Air Systems Command (NAVAIR) for the production of electronic countermeasures equipment. The Letter Contract provided that, within 180 days or not later than the completion of 50 percent of the supplies, the contract was to be definitized along the lines of a cost-plus-award-fee contract. If the contract was not definitized within the prescribed period, the contracting officer was to give notice that the Letter Contract was terminated, and plaintiff would then be paid in accordance with the provisions of the termination clause.1

[293]*293On June 20, 1966, plaintiff submitted its first definitization proposal to the Navy in accordance with the requirements of the Letter Contract. In October 1966, this proposal was rejected by defendant, but no action was taken by the contracting officer to terminate the contract.2 In June 1967, plaintiff submitted a second definitization proposal, which again was rejected by defendant. On January 26, 1968, at the Navy’s request, plaintiff submitted a third cost-plus-award-fee definitization proposal. In response to this last proposal, the contracting officer advised plaintiff that the Navy wished to definitize the Letter Contract along the lines of a firm-fixed-price contract rather than the cost-plus-award-fee contract, as originally provided, for in the Letter Contract. Plaintiff agreed to this request, and negotiations commenced between the parties on this basis.

Early in the negotiations, the parties were able to agree on the approximate amount of $105,000,000 as the cost basis for the basic units under production or to be produced, but they were unable to agree on the level of profit which plaintiff was entitled to receive. On July 31, 1968, plaintiff made a firm-fixed-priee offér of $142,875,193, which covered the basic units, some additional equipment ordered by defendant, and plaintiff’s profit. One month later, defendant responded with an offer of $140,536,263, which was intended to yield a profit of $13,161,047 or 9.99 percent of negotiated costs. Plaintiff at first rejected this proposal, but after being assured by Admiral Townsend, Commander of the Naval Air Systems Command, that the terms of the offer were agreeable to him,3 plaintiff went ahead and accepted the offer. Accordingly, on September 12, 1968, plaintiff and defendant entered into a Memorandum of Agreement providing for a firm fixed price of $140,536,-263.4

On December 18, 1968, plaintiff was orally advised that the Chief of Naval Material had refused to accept the terms of the September 12th Memorandum of Agreement, and that the agreement could not, therefore, be implemented. The parties again entered into a series of negotiations, but their efforts again proved unsuccessful. On January 23, 1969, plaintiff requested the Navy to supply it with a written position statement, but defendant refused to do so.5 [294]*294Finally the parties, on February 14, 1969, entered into an agreement whereby plaintiff would perform the contract to completion in return for a fee payment of $7,680,000.6 It was expressly stipulated that this agreement would not in any way prejudice the rights of either party in subsequent litigation. Since this agreement, performance under the contract has been substantially completed by plaintiff.7 As of December 15, 1969, plaintiff had been paid $129,347,000 8 for reimbursement of costs plus $7,680,000 as a fee or profit.

Plaintiff’s petition is divided into two counts. In the first count, plaintiff is seeking to recover, under the theory of quantum meruit, the reasonable value of the goods and services delivered to and accepted by the Navy, which plaintiff alleges to be $144,380,000, plus the reasonable value of the goods and services covered by additional orders which amounts to $10,500,000, together with interest and costs. In Count II, plaintiff alternatively seeks to recover the amount due and owing by defendant as the result of the September 12th Memorandum of Agreement, which plaintiff alleges is a valid and binding contract. Under this count, plaintiff is claiming $140,536,263, plus $10,000,000 for goods and services covered by additional orders, together with interest and costs.

In support of its motion for summary judgment, defendant presents two basic arguments. In respect to Count I, defendant contends that plaintiff failed to exhaust its administrative remedies in that there were several questions of fact redressable under the disputes clause of the Letter Contract which should have been presented first to the Armed Services Board of Contract Appeals (ASBCA). In regard to Count II, defendant argues that the September 12th Memorandum of Agreement was not a binding contract because it had not been approved by the Office of Naval Material and because the Government contracting officer, A. Kevin Fahey, did not have authority to bind the Government without such approval.

COUNT I

Defendant claims there are three different issues, arising under the Letter Contract, which should have been carried by plaintiff to the ASBCA. The first such issue is the main issue of this case, namely, the dispute over the determination of plaintiff’s fee. Defendant’s argument is that the fee should have been determined in accordance with the termination clause of the contract. Defendant claims that since the Letter Contract was never definitized by the parties, as required by the contract, therefore the contract was terminated for convenience by the Government. Defendant relies on the doctrine of “constructive”9 termination which provides [295]*295that the Government can pay costs based on the termination-for-convenience clause even though the Government does not actually invoke such clause. Warren Bros. Roads Co. v. United States, 355 F.2d 612, 173 Ct.Cl. 714 (1965); Brown & Son Elec. Co. v. United States, 325 F.2d 446, 163 Ct.Cl. 465 (1963); John Reiner & Co. v. United States, 325 F.2d 438, 163 Ct.Cl. 381 (1963), cert.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brager v. Missouri
367 F. Supp. 752 (W.D. Missouri, 1973)
Southwestern Engineering Co.
196 Ct. Cl. 782 (Court of Claims, 1971)
Sanders Associates, Inc. v. The United States
423 F.2d 291 (Court of Claims, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
423 F.2d 291, 191 Ct. Cl. 157, 1970 U.S. Ct. Cl. LEXIS 21, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sanders-associates-inc-v-the-united-states-cc-1970.