Collins v. United States

34 Ct. Cl. 294, 1899 U.S. Ct. Cl. LEXIS 50, 1800 WL 2150
CourtUnited States Court of Claims
DecidedFebruary 27, 1899
DocketNo. 18589
StatusPublished
Cited by8 cases

This text of 34 Ct. Cl. 294 (Collins v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Collins v. United States, 34 Ct. Cl. 294, 1899 U.S. Ct. Cl. LEXIS 50, 1800 WL 2150 (cc 1899).

Opinion

Howry, J.,

delivered the opinion of the court:

This action arises from a contract for the construction of a lock pit for a new lock at St. Marys Falls Canal in the State of Michigan, for the recovery of $101,110.51 as damages for alleged breaches by the defendants of the agreement, and for extra services undertaken and performed and expenses incurred by plaintiffs, either at the instance of the defendants or because of the breaches alleged, whereby plaintiffs were obliged to perform the services and incur said expenses to carry out the contract. The defendants deny the grounds of action aside from retained percentages and some few items, and allege loss and damage to them arising from" breaches of the contract on the part of the plaintiffs, and plead counterclaims amounting to $89,159.50, asserting a general balance due the United States on a full statement of the account of $02,784.43, for which amount judgment is asked against the plaintiffs.

The case is before us by reference from the War Department under the provisions of section 1063 of the Revised Statutes.

The facts pertaining to the several items vary so greatly that they present several distinct causes of action, which is likewise true with respect to the items of the counterclaim. The demands of the plaintiffs are necessary to be considered with those of the defendants as the determination of the claims of the one party will have the effect of disposing of the claims of the other.

The contract and the specifications are set out in full in the findings. By these it appears a great public improvement involving the expenditure of a large sum of money was provided for, rendering necessary the investment of a large sum of money in the plant, appliances, and material, and in the employment of the necessary labor to do the work on the part of the contractors.

[320]*320The first subject of contention is the demand of the contractors for the excavation of 9,262.33 cubic yards of rock at $1.33 per cubic yard, aggregating $12,317.90. This charge is made up by taking the amount of 3,262.58 cubic yards of rock excavation within the slopes and above grade and adding thereto the amount of 5,999.75 cubic yards of rock excavation below grade, the latter amount having been recommended by the defendant’s engineer, who allowed for rock excavated to a depth of 11¿ inches below grade. The recommendation being-rejected, the item must be considered on its merits.

The i>rincipal item of the counterclaim arises on the provision relating to the excavation of rock. This part of the cross action is a charge against the contractors for the cost to the United States in excavating rock alleged to have been shattered by the contractors below the grade and of replacing the same with concrete, which the defendants say amounts to $82,502.04. The issues on these respective demands present wide differences of much import and gravity.

By the contract the plaintiffs agreed to excavate and remove 108,000 cubic yards, more or less, of rock, bank measurement, at the rate of $1.33 per cubic yard. Under the head of “Excavation ” the specification provides that—

“ The lock pit must be excavated to the width and length and depth which the engineer in charge sliall deem necessary. * * * For this work the contractor will be paid by the cubic yard, measured in the bank. Care must be taken to leave the rock in the bottom of the completed pit undisturbed, and it must be dressed in a suitable manner to receive the timber and masonry of the lock. For such dressing the contractor will receive no extra compensation, and should he, by accident or otherwise, shatter the rock intended to be left undisturbed, he will be required to remove the shattered portions and replace them with masonry or concrete, all at his own expense, and subject to the approval of the engineer in charge.”

It is contended that this provision does not carry with it any responsibility to pay the contractors for rock excavated below grade, and if any such excavation was made the grade should be restored to its proper limit and concreted at the cost of the contractors. This defense rests.upon the charge that in blasting the rock of the pit necessary to be excavated the contractors negligently and carelessly used excessive charges of powder and shattered and broke the bed rock of [321]*321the pit below tbe grade as fixed by the engineer in charge of the work, contrary to the provisions of the contract in that they failed and neglected either to remove the rock thus shattered and broken or to replace it with concrete or masonry. This, the defendants say, necessitated the subsequent employment of their own force or subsequent contractors at defendants’ cost to move the shattered rock below grade and replace the same with concrete, the cost of which became a charge against the contractors.

Aside from the charge of negligence and carelessness and the liability of the contractors to replace the excavated pit with concrete, the defendants further insist that upon any excavation below grade, for any cause whatever, the contractors can not recover.

This offset is not sustained by the findings. The excavation below grade was not the result of excessive charges of explosives, and the allegation of negligence and carelessness on the part of the contractors in the work of excavation is not made out. The contractors were without fault. In the final estimate of the amount due them the engineer supervising the work for the defendants allowed for excavating to a certain limit below grade. There were differences between the engineer and the assistant engineers as to the extent of the excavation and in the amount of the. allowance, but their reports and recommendations will not be noticed any further than to say that if the recommendation of the chief engineer should be followed plaintiffs would receive greater benefit than we find on the whole proof they are entitled to have; and while it is true the recommendations of the engineer and agents of the Government in the premises do not bind the United States, the reports of the engineer and his assistants emphasize the correctness of the findings which exclude any imputation of fault on the part of the contractors in excavating below grade, and which allow them fair compensation for such' material as they actually did take out.

There was a seeming necessity in the opinion of the engineer for carrying the excavation below grade owing to the friable nature of the strata and what the engineer styled the bad character of the stone at the bottom of the lock pit. The strata of rock dipped to the southwest, and the ledges not being horizontal and some of them soft and friable, the contractors were [322]*322ordered, to remove rock until better strata were found. The work done under the order below grade was in excess of the 108,000 cubic yards of excavation estimated to the grade limit first fixed by- the engineers. In point of fact, no necessity really existed for excavating below grade, as, when the entire excavation had been made, a more secure foundation was not found. The pit at grade, it turned out, was as solid and in as good a condition to receive the timber and masonry of the lock (the contractors having dressed it) as the bottom below grade was found to be after the excavation.

In any event, if any necessity existed for an excavation below grade, that necessity did not arise from any conduct of the contractors.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wunderlich v. United States
117 Ct. Cl. 92 (Court of Claims, 1950)
English Const. Co. v. United States
43 F. Supp. 313 (D. Delaware, 1942)
W. E. Callahan Construction Co. v. United States
91 Ct. Cl. 538 (Court of Claims, 1940)
Axman v. United States
47 Ct. Cl. 537 (Court of Claims, 1912)
Sanitary District of Chicago v. McMahon & Montgomery Co.
110 Ill. App. 510 (Appellate Court of Illinois, 1903)
Barlow v. United States
35 Ct. Cl. 514 (Court of Claims, 1900)
Collins v. United States
35 Ct. Cl. 122 (Court of Claims, 1900)

Cite This Page — Counsel Stack

Bluebook (online)
34 Ct. Cl. 294, 1899 U.S. Ct. Cl. LEXIS 50, 1800 WL 2150, Counsel Stack Legal Research, https://law.counselstack.com/opinion/collins-v-united-states-cc-1899.