Joplin v. United States

89 Ct. Cl. 345, 1939 U.S. Ct. Cl. LEXIS 176, 1939 WL 4228
CourtUnited States Court of Claims
DecidedJune 19, 1939
DocketNo. 43166
StatusPublished
Cited by12 cases

This text of 89 Ct. Cl. 345 (Joplin v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Joplin v. United States, 89 Ct. Cl. 345, 1939 U.S. Ct. Cl. LEXIS 176, 1939 WL 4228 (cc 1939).

Opinion

GkeeN, Judge,

delivered the opinion of the court:

Notwithstanding the case has been tried and submitted on the facts, the defendant has filed a motion to dismiss the petition on the ground that it is based upon an alleged breach of the contract occurring more than six years prior to the time when the action was commenced.

While the petition does allege that in several respects the defendant failed to comply with the contract and that these specific failures occurred more than six years prior to the time when the suit was commenced, less than six years elapsed between the time when the contract was completed and this suit was begun.. If the contention of defendant that plaintiffs’ right of action accrued at the time when the defendant, in the course of work upon the contract, failed [356]*356to comply with its provisions is sustained, then, as said in Myerle v. United States, 31 C. Cls. 105—

* * * any contractor with the Government must, to protect his right, sue upon every item of difference of fact and- every item of difference of interpretation of the contract as each detail of his work is undertaken or completed, as the case may be.

And on every occasion when the Government fails to act in accordance with the contract, the contractor must “forthwith begin the prosecution of his remedy against the Government.”

The holding in the case last cited was adverse to this rule. We think the contractor is not obliged to sue on each item of damage as it arises and that his claim in full does not accrue until the completion of the work called for in the contract, if the contract is completed.

The motion to dismiss must be overruled and the case determined upon the facts and the law applicable thereto..

This action is brought upon an alleged breach of a contract entered into between the plaintiffs and the United States in July 1926. The contract provided for the construe; tion of a pioneer highway for a distance of nine miles up and through an extremely rough section of Mt. Rainier National Park. The work required included clearing, grubbing, excavating, and surfacing, the excavating being the major item of the contract. Plaintiffs entered upon the performance of the contract in August 1926. So much preliminary work was necessary that of the work to be performed under the contract only about $10,000 in value v/as done in 1926. In 1927, work of the value of $101,000 was completed. This was less than should have been accomplished in the time which had elapsed in order to complete the work within the time originally fixed. In the latter part of 1927, defendant’s representatives became apprehensive that the work would not be completed on time and urged that it be expedited, and in January 1928 plaintiffs held a conference with defendant’s representatives follow*-ing which plaintiffs submitted a plan of operation on January 12 which was considered sufficient by defendant’s representatives if maintained. Thereafter the plaintiffs ex[357]*357pedited the work in many ways and the total value of work completed by October 20 was $237,633.44. At this rate it would have been possible for the plaintiffs to complete all the work provided by the contract, with minor exceptions, before January 1, 1929, if the-work had not been suspended on or about October 8,1928.

During 1928 work under existing contracts of the defendant for road building progressed more rapidly and required a greater expenditure of funds than had been anticipated by the defendant with the result that by the latter part of September 1928 it became known to defendant that funds for road building purposes of the character being carried on by plaintiffs were practically exhausted. Accordingly, on October 1, 1928, the defendant advised its representatives in charge of the work to be done by plaintiffs and others that—

Park service has barely sufficient cash to meet September obligations. Additional cash not available until Congress acts probably January earliest. Order all contractors to shut down. Only alternative is for contractors to finance themselves on basis of certified monthly estimates. Canvass contractors and wire' results in each case.

October 4,1928, plaintiffs’ and defendant’s representatives had a conference in which the plaintiffs were told that they would have the option of either suspending operations until further funds were appropriated by Congress or accepting certified estimates on the work as completed and financing themselves until a further appropriation was made. Thereupon the plaintiffs advised defendant’s representatives they would not undertake further work except for cleaning up odds and ends and would shut down operations about October 15, 1928, which decision was carried out. October 8, 1928, defendant’s representative formally authorized the plaintiffs to suspend work. Subsequently by several extensions additional time was allowed for the completion of the contract so that when it was finished on November 20, 1929, no amount was withheld as liquidated damages. Plaintiffs resumed operations about June 21, 1929, and completed the contract as above stated.

[358]*358The record in the case is very long and the evidence voluminous but there is little dispute with reference to the facts in the case and only one question of law involved. Counsel for both parties commend the findings of the commissioner of this court, and the exceptions taken by the respective counsel are few in number. After examining the testimony and- the documentary evidence offered in the case, we have concluded that no change should be made in the commissioner’s findings.

The plaintiffs object specially to that part of Finding 14 which holds the record is insufficient to substantiate plaintiffs’ claim that the defendant has not paid in ivhole or in part for two items of damages, set up by plaintiffs relating to expenditures made in removing branches of trees blown down or fallen across or into the roadbed during the “extra” winter, and “cost of removing the bank ravellings caused by the snpw and frost of the winter” and related work.

While the evidence is sufficient to show the amount of work and expense incurred by plaintiffs in relation to these two matters, we agree with our commissioner that the evidence fails to show that the plaintiffs have not received payment therefor. The evidence shows that the plaintiffs expended on these items the amount claimed but there is no direct testimony that they have not received payment hi the many partial payments made thereafter. The plaintiffs contend that this is shown by the statement of certified monthly estimates offered in evidence, but, in our opinion, these statements are so indefinite that no conclusion can be reached therefrom with reference to this matter.

The defendant especially objects to the finding of the commissioner that the reasonable rental value of plaintiffs’ equipment during the period it was not in use by reason of the suspension order was $34,500. It is true that the nature of the claim upon which the allowance was based is such that the amount thereof cannot be estimated exactly but this does not prevent the plaintiffs from recovering under the circumstances of the case. The commissioner found that the amount above stated was the rental value “for the portion of that period when such equipment could reasonably have been rented.” Transposing this statement, [359]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Northern Helex Co. v. United States
455 F.2d 546 (Court of Claims, 1972)
Ross Construction Corporation v. The United States
392 F.2d 984 (Court of Claims, 1968)
Anthony P. Miller, Inc. v. The United States
348 F.2d 475 (Court of Claims, 1965)
L. Balkin Builder, Inc. v. United States
142 F. Supp. 597 (Court of Claims, 1956)
Reiss & Weinsier, Inc. v. United States
116 F. Supp. 562 (Court of Claims, 1953)
Western Well Drilling Co. v. United States
96 F. Supp. 377 (N.D. California, 1951)
Pennsylvania Coal & Coke Corp. v. United States
70 F. Supp. 136 (Court of Claims, 1947)
Holton v. United States
65 F. Supp. 903 (Court of Claims, 1946)
Brand Inv. Co. v. United States
58 F. Supp. 749 (Court of Claims, 1944)

Cite This Page — Counsel Stack

Bluebook (online)
89 Ct. Cl. 345, 1939 U.S. Ct. Cl. LEXIS 176, 1939 WL 4228, Counsel Stack Legal Research, https://law.counselstack.com/opinion/joplin-v-united-states-cc-1939.