Ross Construction Corporation v. The United States

392 F.2d 984, 183 Ct. Cl. 694, 1968 U.S. Ct. Cl. LEXIS 86
CourtUnited States Court of Claims
DecidedApril 19, 1968
Docket49-65
StatusPublished
Cited by2 cases

This text of 392 F.2d 984 (Ross Construction Corporation v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ross Construction Corporation v. The United States, 392 F.2d 984, 183 Ct. Cl. 694, 1968 U.S. Ct. Cl. LEXIS 86 (cc 1968).

Opinion

ON PLAINTIFF’S MOTION AND DEFENDANT’S CROSS-MOTION FOR SUMMARY JUDGMENT

DAVIS, Judge.

We held in Anthony P. Miller, Inc. v. United States, 348 F.2d 475, 172 Ct.Cl. 60 (1965), that the Congressional limits on federal mortgage insurance for Cape-hart Act projects did not prevent a contractor from recovering for losses or expenses incurred as a result of defective government plans or specifications, or for unforeseen conditions falling within the “changed conditions” clause, or on account of Government errors in interpreting the specifications. That case (and *985 those following it) involved “on-site” construction of residential housing authorized by the Capehart Act. Now we have to decide whether the same rules are to be applied to “off-site” construction and facilities, ancillary to Capehart Act housing but governed by a different statutory limitation. This is entirely a legal question. The relevant facts are undisputed and both sides ask for summary judgment.

The Air Force built a Capehart Act housing project at McGuire Air Force Base in New Jersey. Plaintiff contracted to do the off-site work necessary to connect the streets and utilities of the project to the streets and utilities of the rest of the Base. Performance of the contract led plaintiff to submit various claims to the Government, of which only five remain pertinent. Three of these concerned changed conditions, one an error in the government drawings, and the other an incorrect interpretation of the specifications by the contracting officer. All were appropriately raised under the contract, and as to the last claim due protest was made before the work was done as the defendant ordered. The Armed Services Board of Contract Appeals allowed the five demands in the amount of $125,712.87, but the contractor has been paid only $73,-611.58. This suit is for the remaining $52,101.29.

The barrier interposed by the defendant to full payment is 12 U.S.C. § 1748i (1964), authorizing appropriated funds for land acquisition and installation of outside utilities for Cape-hart Act housing projects, and restricting such expenditures to “an average of $1,500 per housing unit in respect of any housing project” and “an average of $1,000 per housing unit in respect of all housing projects for which expenditures are approved under” the Capehart Act. 1 Since there were 1,450 units in the McGuire Air Force Base housing project, the statutory limitation, as applied to plaintiff’s contract, was $2,175,-000. The ASBCA found that only $73,-611.58 was left out of this maximum, and indicated that that was all plaintiff could receive even though the Board held $125,712.87 would be due on the five granted claims if the statutory limit had not been exceeded. After this administrative decision the parties made a supplemental agreement providing for payment of the $73,611.58, stipulating “that the contractor would be entitled to the entire $125,712.87 if payment is not subject to restrictions under 12 U.S.C. 1748i”, and releasing the Government from all claims on this contract “except the contractor’s claim in the amount of $52,101.29, which the parties agree is due the contractor if the limitation of 12 U.S.C. § 1748i does not apply.”

There are, of course, differences between the limitation provisions of the Capehart Act and that of 12 U.S.C. § 1748i, the major one being that off-site contracts under the latter are paid di *986 rectly out of appropriated funds. But Anthony Miller made it very plain that the holding in that case was not grounded on the system by which appropriations were used only ultimately, but not immediately, to pay the costs of Capehart Act work. On the contrary, the decision treated the Capehart Act, in this respect, as if appropriations were much involved. 348 F.2d at 479-481, 172 Ct.Cl. at 67-69. The court placed its ruling squarely on the general proposition that, absent the most explicit of statutory language, a Congressional limitation on expenditures should not be read as excluding recovery for circumstances over which the contractor could have no control and which were not its fault.

We said that it is “difficult to conclude that Congress meant that the contractor would remain without a remedy” for over-limitation expenses “for additional work caused by errors or defects in the Government’s plans and specifications or required by changed conditions encountered in the performance of the contract”, and we refused to “attribute to Congress an intention that would produce an impractical, unjust, and unworkable result unless that intention appears clearly on the face of the statute or in the supporting record.” 348 F.2d at 480, 172 Ct.Cl. at 68. 2 Later, we pointed out that Anthony Miller “stand [s] for the general proposition that maximum contract provisions do not ordinarily. control where the contractors suffer additional costs because of the Government’s fault.” Scherr & McDermott, Inc. v. United States, 360 F.2d 966, 971, 175 Ct.Cl. 440, 450 (1966).

These considerations apply just as much to 12 U.S.C. § 1748i as to the Cape-hart Act restrictions. As this case shows, off-site contractors can also suffer losses or increased expenses because of unforeseen changed conditions, defective government specifications, or improper demands by contracting officers for more expensive work. With respect to the limitation, there is no meaningful distinction favoring the on-site builder over the off-site contractor. 3

If anything, the balance swings the other way because it is more likely that a number of contractors, not just one, will be engaged in the off-site work; it appears here, for instance, that some twelve contracts were awarded for off-site work (governed by § 1748i) at McGuire Air Force Base. We gather that this is not unique. For years this court has made a distinction between contractors paid out of a general appropriation and those contracts for which a specific and limited appropriation is made by Congress. The former have been held not barred at all by exhaustion of the appropriation, on the theory that “a contractor who is one of several persons to be paid out of an appropriation is not chargeable with knowledge of its administration, nor can his legal rights be affected or impaired by its malad *987 ministration or by its diversion, legal or illegal, to other objects.” Ferris v. United States, 27 Ct.Cl. 542, 546 (1892). See, also, Dougherty, for Use of Slavens v. United States, 18 Ct.Cl. 496, 508 (1883); Myerle v. United States, 33 Ct.Cl. 1, 25 (1897); Schuler & McDonald, Inc. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
392 F.2d 984, 183 Ct. Cl. 694, 1968 U.S. Ct. Cl. LEXIS 86, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ross-construction-corporation-v-the-united-states-cc-1968.