Scherr and McDermott Inc. v. The United States

360 F.2d 966, 175 Ct. Cl. 440, 1966 U.S. Ct. Cl. LEXIS 218
CourtUnited States Court of Claims
DecidedMay 13, 1966
Docket311-64
StatusPublished
Cited by7 cases

This text of 360 F.2d 966 (Scherr and McDermott Inc. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Scherr and McDermott Inc. v. The United States, 360 F.2d 966, 175 Ct. Cl. 440, 1966 U.S. Ct. Cl. LEXIS 218 (cc 1966).

Opinion

COLLINS, Judge.

This action is based upon a contract entered into by the International Cooperation Administration 1 and Smith, Scherr & McDermott, a partnership whose interest was acquired by the present plaintiff. Plaintiff seeks to recover an amount representing overhead which it incurred in performance of the contract, but, regarding which, the Government refused reimbursement. 2 Defendant has moved for summary judgment, and plaintiff has filed a cross-motion for summary judgment.

The contract, No. ICA-W-389, dated August 23, 1957, related to the development of the Korean handicraft industry. Its original term was for 28 months. The services to be performed by plaintiff consisted of the following: establishing a program for the training of Koreans at American schools of industrial design; assisting in the establishment of handicraft courses at Korean colleges; and setting up and operating, in Korea, a handicraft demonstration center. Plaintiff was to receive a fixed fee (originally $35,000) and reimbursement of its costs (base salaries, overseas differential, overhead, etc.). However, the contract stated: “In no event shall the total obligation of ICA to the Contractor under this Contract exceed * * * ($248,-000. 00) without prior written approval of ICA.”

With respect to overhead, the contract set forth a provisional rate of 65 percent of base salaries. This rate, which was “based upon an analysis * * * by ICA of relevant data relating to the Contractor’s overhead cost,” was “subject to revision as at the end of the Contractor’s fiscal year to a rate which will reimburse the Contractor for the actual overhead costs allocable to this Contract on the basis of such annual or other audits as ICA (or other appropriate U.S. Government agency) may make.” The contract went on to provide that:

Promptly following establishment of an actual overhead rate by any such audit, an appropriate adjustment will be made in the billings for the period covered by the audit, and the rate so established shall become the provisional rate for the ensuing fiscal year. The provisional rate and payments for subsequent fiscal years shall be computed and adjusted accordingly.

The meaning of the above provisions is one of the matters now in dispute.

No audit was performed by defendant during the original 28-month term. The overhead payments which plaintiff received were based upon the provisional rate of 65 percent of base salaries. Just prior to expiration of the original term, the parties signed a “letter of intent” which authorized plaintiff to continue its services. In March 1960, the parties executed Amendment No. 6 which extended the term of the contract for 1 year. Also, the amendment increased the maximum obligation to $348,000 and the fee to $50,500. A new overhead clause was added, but it differed from the initial provision only slightly. A maximum limit of 72 percent was placed upon the rate of reimbursement for actual overhead. (Previously, there was no limit upon actual overhead payable.)

Performance of the contract was completed on February 22, 1961. Government reports described plaintiff’s work as “very satisfactory” and its performance as “superior.” The only audit made *968 by defendant took place in 1962, after full completion of the contract. The audit revealed (1) that reimbursements for overhead had totaled $86,782.68 and (2) that plaintiff’s actual overhead had been $102,185.97. 3 By letter of May 15, 1962, the chief of the Contract Audit Branch, Office of the Controller of AID, advised plaintiff it would receive $3,414.-56 of the $15,403.29 difference. The remainder ($11,988.73) could not be recovered, since any payment beyond $3,~ 414.56 would cause total payments to exceed defendant’s maximum obligation ($348,000).

Plaintiff sought to obtain the amount of unreimbursed actual overhead from AID. The chief of the Contract Services Division denied plaintiff’s claim. Plaintiff appealed, under the disputes clause of the contract, to the AID Board of Contract Appeals. That board denied plaintiff’s claim, and the subsequent effort of plaintiff to obtain relief from the General Accounting Office was also unsuccessful. The present suit is for the recovery of the amount of $11,988.73.

As the basis for its motion for summary judgment, defendant relies primarily upon the clause which limited the total obligation of the Government to $348,000. Defendant asserts that, since plaintiff has received that amount, the Government has no duty to make further payments. In support of its position, defendant cites Greenfield Tap & Die Corp. v. United States, 68 Ct.Cl. 61 (1929), cert. denied, 281 U.S. 737, 50 S.Ct. 333, 74 L.Ed. 1152 (1930), which case is clearly distinguishable from this case.

Greenfield Tap & Die Corp. involved two contracts, one of which was a “cost-plus contract.” The court denied recovery with regard to the cost-plus contract. An alternative ground for this holding was the fact that the contractor had received $100,000, the amount stated in the contract to be the maximum payable by the Government. 68 Ct.Cl. at 77. It is imperative to note, however, that the cost-limitation clause in Greenfield differed significantly from the one contained in the ICA contract here. The Greenfield clause provided as follows:

“ * * * the payments due the contractor * * * shall in no event exceed a total of * * * [$100,-000], and in case the entire work contemplated by this contract shall not have been satisfactorily completed when the total payments due have reached the sum of * * * [$100,-000], the contractor shall complete the remaining work without further compensation of any kind.” [68 Ct.Cl. at 75.]

Thus, the maximum stated in the Greenfield contract was, according to the express agreement of the parties, absolute. However, the limit expressed in the ICA contract was not similarly unconditional. The contract stated that the Government’s obligation would not exceed the specified amount “without prior written approval of ICA.” In other words, the parties did envision the possibility that, under certain circumstances, the maximum could be increased. Therefore, the precise ruling in Greenfield Tap & Die Corp. v. United States does not control the present case. 4 The mere existence of the cost-limitation clause is not determinative here.

It appears that defendant is correct in asserting that plaintiff never informed ICA that total costs would exceed $348,-000. However, under the circumstances of this case, this is not a decisive fact. *969 We have concluded, for reasons to be explained, (1) that conduct on the part of the -Government excused the requirement of prior approval for an increase in the maximum and (2) that plaintiff is entitled to summary judgment in its favor.

Plaintiff argues that the Government had a contractual duty to conduct at least one audit of plaintiff’s books per year. We agree with plaintiff’s contention.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Utley-James, Inc. v. United States
34 Cont. Cas. Fed. 75,478 (Court of Claims, 1988)
C & L Construction Co. v. United States
32 Cont. Cas. Fed. 73,102 (Court of Claims, 1984)
Gulf & Western Industries, Inc. v. United States
32 Cont. Cas. Fed. 73,100 (Court of Claims, 1984)
Ross Construction Corporation v. The United States
392 F.2d 984 (Court of Claims, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
360 F.2d 966, 175 Ct. Cl. 440, 1966 U.S. Ct. Cl. LEXIS 218, Counsel Stack Legal Research, https://law.counselstack.com/opinion/scherr-and-mcdermott-inc-v-the-united-states-cc-1966.