Curtis v. United States

2 Ct. Cl. 144
CourtUnited States Court of Claims
DecidedDecember 15, 1866
StatusPublished
Cited by16 cases

This text of 2 Ct. Cl. 144 (Curtis v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Curtis v. United States, 2 Ct. Cl. 144 (cc 1866).

Opinion

Nott, J.,

delivered the opinion of the court:

This is an action brought to recover $27,333 41 upon certain contracts for the building and machinery of the branch mint in San Francisco. The case was once tried before three judges, but no judgment was rendered by reason of the disagreement of the. court upon the amount of damages to be awarded. It now comes before us on the following facts:

In the year 1853 Mr. Guthrie, Secretary of the Treasury, invited proposals for the construction of a branch mint at San Francisco, to which one William A. Barton, among others, responded. His bid was deemed the best and his proposals were accepted. These proposals with their acceptance were then, with the, assent of the Secretary, transferred to the claimant. Two contracts were subsequently executed, which departed somewhat from the tenor and provisions of the proposals; but the agreement to depart was mutual and no question was ever raised as to its legality, and the mint upon its completion was accepted fey the government. Shortly after the execution of the contracts the Secretary appointed two commissioners to superintend the work, and Mr. George Eckfeldt, an experienced machinist in the mint at Philadelphia, was sent out as a " commissioner for the building of-machinery.” During the progress of the work various alterations and additions were ordered and allowed by Mr. Eckfeldt and the commissioner, and out of these alterations and additions this suit arises. It involves chiefly matters of fact and .questions pertaining only to the construction of this particular contract, but there is one question of general importance also involved, which will be first considered.

The first section of the act of July 3, 1852, (10 Stat. L., p. 11,) provides “ that a branch of the mint of the United States be established in California” “for the coinage of gold and silver.” The tenth section limits the expenditures as follows, viz: “ That before the Secretary of the Treasury shall procure or erect the buildings provided for in the second section of this act, or commence operations under any of the provisions of the same, at San Francisco, State of California, it shall first be his duty to make a contract or contracts for the erection of said buildings, and procuring the machinery necessary for the opera[151]*151tions of said mint, at a sum or sums which shall not, in the whole, exceed the sum of $300,000.” The original or written eontraet between the parties contemplated only the coinage of gold. It was not necessary that the contract should embrace both. The end might be obtained by one or by many contracts, only they would be subject to the limitation of the statute. This .limitation in clear terms bound the contracts for the coinage of gold and of silver — for the coinage of both or of either.

The aggregate consideration of the formal or written contracts of April 15 and July 6 was $283,809 10. By a subsequent agreement with the director of the mint the claimant agreed to furnish additional apparatus at the stipulated price of $14,000, whieh for the present we assume to be for the coinage of silver. During the progress of the work a number of alterations were made by the direction of the government agent, and these alterations the court find to be extra work of the value of $8,680, so that the moneys which the claimant has received, ($297,929 10,) with those which he has expended to the use of the government in the cost of the alterations, ($8,680,) amount in the aggregate to $306,609 10, or $6,609 10 more than the amount to which the expenditures were limited by Congress. The chief legal question in the case is, “ can the claimant recover for this excess ?”

The difficulty is not one of appropriation. Contracts in excess of an appropriation are held void ordinarily to that extent. That difficulty, however, so far as it relates to cases in this court, Congress has bridged by the general appropriation to meet its judgments. If this were not so we should be constantly stopped by that obstacle. The Court of Claims was established to meet those cases where a man came before Congress and said, “ I have expended money for, or rendered service to, the government, for which I could recover in a court of justice if the party with whom I dealt were a citizen or a body corporate. I ask a like remedy and a like liability on the part of the government.” Hence, there are claims properly and legally rejected by the departments for want of appropriations, yet properly and legally sustained here by virtue of the general appropriation to meet our judgments.

The proviso in this statute was not an appropriation, but a condition or limitation. It says, in effect: “ The cost of the branch mint in California, with all its appurtenances and apparatus, shall not exceed $300,000; and if it should, the government shall not be liable for the excess.” To all intents and purposes the government wrote this limitation upon the face of the contract. Is there any way by which the claimant can escape from it ?

[152]*152The rule and principle adopted by this court for the administration of justice between a claimant and the government is simply to give that measure of relief which the law would award were the action between man and man. The court never gives greater and never gives discretionary relief. Sometimes this rule is modified by holding parties to greater care and vigilance than if they had dealt with private persons ; but the liability of the government in these actions on contract, express or implied, has been held generally to be simply that which the claimant might pursue against another defendant in another tribunal.

What, then, can the claimant here recover, if the government be re- • garded simply as the principal and its officers as its agents ? At the beginning of the transaction the principal gave to the contractor the plainest and the clearest notice that all of its expenditures and liabilities should not exceed a fixed and certain sum. The statute became to the claimant notice in law and in fact that the expenditures could not be'earried beyond certain bounds; and it was, moreover, by direct reference, stamped upon and made a part of the contract which is the foundation of the claimant’s rights. This condition the law-making power never relinquished, nor by any act waived, nor at any time authorized the executive officers to exceed. The law-making power was here the government, and the executive officers were its agents, and no acts of theirs could bind their principal for a greater sum than had been consented to and agreed upon.

Yiewed as a transaction between private persons, the claimant must be deemed to have gone beyond the fixed limit of his agreement at his own risk, trusting for recompense to the liberality of the party with whom he dealt — a liberality which courts of justice cannot enforce. Yiewed as a transaction between a contractor and the government, the claimant must be held to abide by the conditions which the statute imposed, both upon him and upon the officers who directed his expenditures. Were such statutory provisions to be disregarded, and were judgment to be given whenever a claimant shall prove that he has done work or rendered service under the direction of an executive officer, it would enable the executive branch of the government, with the aid of this court, to annul a law of Congress, and to throw down any limitation which Congress might impose upon the cost of our public works.

It remains to speak of the items which make up the claimant’s demand.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brunner v. United States
70 Fed. Cl. 623 (Federal Claims, 2006)
American Telephone & Telegraph Co. v. United States
40 Cont. Cas. Fed. 76,754 (Federal Claims, 1995)
Ross Construction Corporation v. The United States
392 F.2d 984 (Court of Claims, 1968)
Anthony P. Miller, Inc. v. The United States
348 F.2d 475 (Court of Claims, 1965)
Lovett v. United States
66 F. Supp. 142 (Court of Claims, 1945)
Fort Worth Cavalry Club, Inc. v. Sheppard
83 S.W.2d 660 (Texas Supreme Court, 1935)
Sutton v. United States
55 Ct. Cl. 193 (Court of Claims, 1920)
Leavitt v. United States
34 F. 623 (S.D. New York, 1888)
United States v. Cosgrove
26 F. 908 (D. Kansas, 1886)
Briggs v. United States
15 Ct. Cl. 48 (Court of Claims, 1879)
Grant v. United States
5 Ct. Cl. 71 (Court of Claims, 1869)

Cite This Page — Counsel Stack

Bluebook (online)
2 Ct. Cl. 144, Counsel Stack Legal Research, https://law.counselstack.com/opinion/curtis-v-united-states-cc-1866.