Reiss & Weinsier, Inc. v. United States

116 F. Supp. 562, 126 Ct. Cl. 713, 1953 U.S. Ct. Cl. LEXIS 128
CourtUnited States Court of Claims
DecidedDecember 1, 1953
Docket49490
StatusPublished
Cited by9 cases

This text of 116 F. Supp. 562 (Reiss & Weinsier, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reiss & Weinsier, Inc. v. United States, 116 F. Supp. 562, 126 Ct. Cl. 713, 1953 U.S. Ct. Cl. LEXIS 128 (cc 1953).

Opinion

WHITAKER, Judge.

In December 1945 the defendant, through the instrumentality of the Housing Authority, embarked on a program to furnish emergency housing for veterans of World War II. The general plan was to demount and separate into their component parts, called panelizing, the housing units constructed for war workers, and to transport them to various locations where there was a shortage of private housing facilities for veterans, and there to erect them as temporary houses for their use. On December 28, 1945, plaintiff entered into such a contract with the defendant, under which the plaintiff was to demount and panelize 1500 housing units “as shall be assigned from time to time by the contracting officer” at various military posts and to transport and to erect them as family dwelling units in various other locations.

Proceed orders were issued for 1049 of these units. The work on 515 of the units was completed. The proceed orders as to 211 of the units were canceled before any work was done. Further work on 205 of the units was canceled after these units had been demounted and panelized. The work on 85 of the units was suspended for a time and then later canceled.

The following table sets out the action taken with respect to each proceed order:

Plaintiff’s suit is for damages for the failure to issue proceed orders as to the 451 units not covered by proceed orders, and for damages for the cancellation of the proceed orders, which were issued, and for cancellation of further work on some of the uncompleted units, and the suspension of work and final termination of the contract as to others.

Its first cause of action is for the suspension of the work on 85 units prior to completion, and for the final cancella *565 tion of plaintiff’s contract as to them.

The contract provided that the consideration to be received by the contractor was reimbursement for its costs and a fixed fee plus a fixed overhead.

The principal issue in the case is whether the defendant is liable for damages resulting from suspending operations on the contract and the subsequent cancellation of the contract.

In December 1946 defendant notified plaintiff and other contractors that it might be necessary to stop the program, of which plaintiff’s contract was a part, on account of the shortage of funds, until the passage of a deficiency bill by Congress, and then on January 14, 1947, defendant sent the plaintiff the following telegram:

“Pending Readjustment Of Funds Required To Complete Our Temporary Housing Program For Veterans You Are Instructed To Suspend Work Immediately On 15 Dwelling Units NJV-28232-2 New Brunswick; 7 Dwelling Units NJV-28217-1 Highland Park; 16 Dwelling Units NJV-28231 — 2-3 Kearny; 46 Dwelling Units NJV-28171-7-8-9 Newark. Expect This Suspension Will Be Temporary.”

Plaintiff stopped work as directed.

On March 18, 1947, the defendant sent plaintiff another telegram, which reads as follows:

“ ■■ * * The Funds Provided For Cost Incurred On Suspended Units Prior To Suspension Take Into Consideration Probable Credits On Subcontracts Which Would Be Effected If No Further Work Was Performed. It Is Not Intended At This Time That You Should Cancel Subcontracts And Effect These Credits. It Is Desired That These Units Be Held In Suspension And Not Canceled Pending The Outcome Of Proposed Legislation To Provide Additional Funds For Their Completion.”

And on April 16, 1947, defendant telegraphed plaintiff again as follows:

“Regret Unable Return Your Telephone Call Yesterday. Additional Funds To Your Concern For Veterans Emergency Projects Must Await Passage Deficiency Appropriation Bill. We Have Reason To Believe This Bill Will Be Approved Soon.”

On July 29, 1947, Congress passed a deficiency appropriation bill which permitted the Housing Authority to continue with the program. However, prior to its passage defendant decided, and so notified plaintiff and other contractors, that it would not continue with the program on the basis previously contracted for, but would let lump-sum contracts for the completion of the work on a competitive basis. Plaintiff was not interested in bidding on such a contract and declined the defendant’s invitation of September 15, 1947, to do so. Accordingly, on October 23, 1947, plaintiff’s contract for the 85 units was canceled and a lump-sum contract for the completion of these buildings was let to another company.

Until April 25, 1947, plaintiff was engaged in the completion of other units, work on which was not canceled or suspended, but after that time it did no further work on any of the 1,500 units involved. It alleges, however, that it kept a number of employees on its payroll thereafter and until formal cancellation of its contract as to these 85 units, in anticipation of resumption of work on the uncompleted buildings, and it sues for their salaries and for a portion of its home office overhead.

The suspension of the work on these 85 units was of course a breach of contract, and it was a breach of contract for which defendant is not to be excused, although the reason for the suspension was a shortage of funds. A man cannot be excused from performance of his contract because he runs short of the money necessary to perform it. The other party enters into it on the promise that the money will be paid. If it is not paid, the promise is broken. So it is with the Government. See Jop *566 lin v. United States, 89 Ct.Cl. 345, 359-361; Johnson v. City of New York, 191 App.Div. 205, 181 N.Y.S. 137, affirmed 231 N.Y. 564, 132 N.E. 890. Defendant does not seriously dispute this.

Plaintiff is entitled to recover whatever damages it may have suffered by reason of this breach.

Plaintiff says that during the period that the work was in suspension it kept a number of employees on its payroll in anticipation of resumption of the work, and it sues to recover their wages, together with a portion of its home office overhead.

We think defendant’s conduct was a sufficient inducement for plaintiff to keep some, if not all, of these employees on its payroll, and that it was justified in doing so. Its initial telegram of January 14, 1947, suspending the work, concluded with this statement: “Expect this suspension will be temporary.” Then, about two months later, on March 18, 1947, it wired plaintiff in part:

“ * * * It is not intended at this time that you should cancel subcontracts and effect these credits [that is, credits on the subcontracts]. It is desired that these units be held in suspension and not canceled pending the outcome of proposed legislation to provide additional funds for their completion.”

Again, a month later, on April 16, 1947, defendant said:

“Additional funds to your concern for Veterans’ emergency projects must await passage deficiency appropriation bill. We have reason to believe this bill will be approved soon.” [Italics ours.]

In short, defendant held out to plaintiff the hope that at almost any time it would have the money to go ahead with the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

White v. United States
68 A.3d 271 (District of Columbia Court of Appeals, 2013)
Wilco Floor Service, Inc. v. United States
197 Ct. Cl. 902 (Court of Claims, 1972)
Dale Construction Co. v. United States
161 Ct. Cl. 825 (Court of Claims, 1963)
Oliver-Finnie Company v. United States
279 F.2d 498 (Court of Claims, 1960)
Oliver-Finnie Co. v. United States
150 Ct. Cl. 189 (Court of Claims, 1960)
F. H. McGraw & Co. v. United States
130 F. Supp. 394 (Court of Claims, 1955)
FH McGraw and Company v. United States
130 F. Supp. 394 (Court of Claims, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
116 F. Supp. 562, 126 Ct. Cl. 713, 1953 U.S. Ct. Cl. LEXIS 128, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reiss-weinsier-inc-v-united-states-cc-1953.