Holton v. United States

65 F. Supp. 903, 106 Ct. Cl. 477
CourtUnited States Court of Claims
DecidedJune 3, 1946
Docket45803
StatusPublished
Cited by14 cases

This text of 65 F. Supp. 903 (Holton v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Holton v. United States, 65 F. Supp. 903, 106 Ct. Cl. 477 (cc 1946).

Opinion

LITTLETON, Judge.

Plaintiff brought this suit to recover job and office overhead expense for the periods from March 19 to November 15, 1935, and November 16, 1935, to January 28, 1936, (findings 26-30), for alleged unreasonable delay (findings 9, 22-24), for which he alleges the defendant was responsible and for which it should respond in damages for breach of the contract.

Prior to the making of the contract with plaintiff on November 22, 1934, defendant and the Largura Construction Company had entered into a contract for the construction by the Largura Company of a post office building at Oak Park, Ill. The Government terminated the Largura contract and thereafter, on June 16, 1934, issued an advertisement and an invitation for competitive bids for completion of the unfinished work called for by and in accordance with the Largura contract and specifications and certain supplementary or amended specifications. Plaintiff was the lowest bidder and its bid was accepted and the Standard Contract Form 23 for construction was duly executed by plaintiff and defendant by the Director of Procurement, Treasury Department, as contracting officer.

Plaintiff proceeded with the work under his contract until March 19, 1935, when there was a strike of the lathers employed by plaintiff, which strike continued until November 15, 1935, and operated to delay completion by plaintiff of the contract work. In the invitation for bids and the supplementary specifications for completion of the work defendant advised all bidders of the extent of the work which had been done on the building and furnished them with a list of the names and addresses of all subcontractors of the original contractor, Largura Company, among which was Edw. D. Chouinard, the lathing and plastering subcontractor of the Largura Company. The Largura Company had not fully paid Chouinard for work which he had performed and the union lathers employed by plaintiff’s lathing and plastering subcontractor refused to work on the suspended ceiling hangers in the building until Chouinard was paid the balance of $262 due him for certain lathing work he had performed for the Largura Company (findings 8 and 9). Plaintiff finally paid, through his lathing subcontractor, the balance due Chouinard and the strike ended November 15, 1935.

On March 25, 1935, plaintiff, as required by the contract, submitted to defendant’s architects, White and Weber, at the site, certain samples of wall and floor tile for the lobby of the building, but such samples were not submitted in writing as called for by the specifications. Soon afterwards the architects notified plaintiff that the samples were rejected on account of color, size and the general appearance such tile would give the lobby. Plaintiff did not submit any further samples of lobby tile, but on April 29, May 4 and 6, 1934, wrote defendant that the architects were delaying the work by failing 'to approve samples of tile. May 6, 1935, the contracting officer wired the architects to take immediate action on tile samples and was advised by such architects that plaintiff had not submitted tile samples that could be approved. The samples of tile which had been submitted and rejected were sent to the contracting officer, who *905 also rejected them. Thereupon the contracting officer on June 28 notified plaintiff to submit new samples to the architects, but plaintiff did not do this.

In July 1935 plaintiff was informed that White and Weber were doing preparatory work on contemplated changes which would eliminate the lobby tile provided for in plaintiff’s specifications and restore the more expensive materials specified in the Largura contract. On July 23 White and Weber prepared a schedule of such changes which stated “no samples of additional tile are required.” Change drawings dated September 15 were prepared and were submitted to plaintiff by White and Weber sometime between that date and October 30.

On October 24 plaintiff submitted to defendant a proposal for installing tile and marble in the toilet rooms for an extra price of $4,720, which defendant accepted on October 30, 1935. Also on October 30 plaintiff submitted another proposal for the elimination of the tile flooring, base and wainscoting in the lobby, vestibules and first floor stair halls. Defendant accepted this proposal on November 1. Since this eliminated the lobby tile, there was no longer any occasion for plaintiff to submit or for the architects to approve samples of such material. The completion of the contract was not delayed by the matter of tile samples. Plaintiff substantially completed the principal work on August 18, 1935, and between that date and January 26, 1937, performed certain work involving certain defects and omissions as ordered by defendant. The contract contemplated and provided for final inspection and acceptance by defendant of all work called for by the contract and as might be required thereunder by defendant. The work and the contract were not finally accepted as having been fully completed under and in accordance with all of the terms and provisions of the contract and specifications until the date of final settlement and final payment on March 9, 1937 (finding 25).

Counsel for defendant make the argument that plaintiff’s claim for damages for delay for the periods from March 19 to No- ' vember 15, 1935, and November 16, 1935, to January 28, 1936, accrued for the purpose of suit when the delay occurred and was therefore barred by sec. 156 of the Judicial Code, Sec. 262, U.S.C.A. Tit. 28, when the petition was filed, and that in any event such claim accrued not later than January 26, 1937, when it appears, as matters finally turned out, the contract work as required by defendant and as finally accepted by it was substantially completed.

Neither of these contentions is sustained by the facts in this case and the various provisions of the contract and specifications of November 22, 1934, and the decided cases. Myerle, Executor of Phineas Burgess, v. United States, 33 Ct.Cl. 1, 21, 22; Cohen, Goldman & Co., Inc., v. United States, 77 Ct.Cl. 713; Austin Engineering Co., Inc., v. United States, 88 Ct.Cl. 559; Joplin, et al. v. United States, 89 Ct.Cl. 345, 356, 362-364; Austin Engineering Co., Inc., v. United States, 97 Ct.Cl. 68, 72, 79; Fireman’s Fund Indemnity Co. v. United States, 104 Ct.Cl. 648; B. W. Construction Company, A Corporation, v. United States, 100 Ct.Cl. 227, 235, 236; North Chicago Rolling Mill Co. v. St. Louis Ore & Steel Co., 152 U.S. 596, 613, 614, 617, 14' S.Ct. 710, 38 L.Ed. 565.

We have consistently held that when a claim accrues upon complete performance of work or service or by acceptance of completion of contract work in satisfaction of all requirements of the contract the statute of limitations for bringing suit then begins to run and is not suspended by the continued prosecution of a claim or claims under the contract before the administrative departments. Withers v. United States, 69 Ct.Cl. 584; Cohen, Goldman & Co., Inc. v. United States, supra; John P. Moriarty, Inc., v. United States, 97 Ct.Cl. 338. But this is not such a case. The evidence here does not show an accrual by full completion and acceptance and subsequent prosecution of the claim administratively.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Crown Coat Front Co. v. United States
386 U.S. 503 (Supreme Court, 1967)
Conn v. United States
366 F.2d 1019 (Court of Claims, 1966)
Copco Steel & Engineering Co. v. The United States
341 F.2d 590 (Court of Claims, 1965)
Utah Construction & Mining Co. v. United States
339 F.2d 606 (Court of Claims, 1964)
Kraemer Mills, Inc. v. United States
319 F.2d 535 (Court of Claims, 1963)
KRAEMER MILLS, INCORPORATED v. the UNITED STATES
319 F.2d 535 (Court of Claims, 1963)
L. Balkin Builder, Inc. v. United States
142 F. Supp. 597 (Court of Claims, 1956)
Western Well Drilling Co. v. United States
96 F. Supp. 377 (N.D. California, 1951)
Pennsylvania Coal & Coke Corp. v. United States
70 F. Supp. 136 (Court of Claims, 1947)

Cite This Page — Counsel Stack

Bluebook (online)
65 F. Supp. 903, 106 Ct. Cl. 477, Counsel Stack Legal Research, https://law.counselstack.com/opinion/holton-v-united-states-cc-1946.