Highland Al Hujaz Co., Ltd.

CourtArmed Services Board of Contract Appeals
DecidedMarch 30, 2016
DocketASBCA No. 58243
StatusPublished

This text of Highland Al Hujaz Co., Ltd. (Highland Al Hujaz Co., Ltd.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Highland Al Hujaz Co., Ltd., (asbca 2016).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Highland Al Hujaz Co., Ltd. ) ASBCA No. 58243 ) Under Contract No. W917PM-09-C-0049 )

APPEARANCES FOR THE APPELLANT: Herman M. Braude, Esq. Edward D. Manchester, Esq. Braude Law Group, P.C. Washington, DC

APPEARANCES FOR THE GOVERNMENT: Thomas H. Gourlay, Jr., Esq. Engineer Chief Trial Attorney Daniel B. McConnell, Esq. James A. Wallace, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Middle East Winchester, VA

OPINION BY ADMINISTRATIVE JUDGE THRASHER

This appeal arises out of a contract between the U.S. Army Corps of Engineers (Corps or government) and Highland Al Hujaz Co., Ltd. (Highland or appellant) to design and build an Afghan National Army (ANA) installation on Camp Hero in Kandahar, Afghanistan. Highland appeals from the government's decision to terminate the contract for default. Only the propriety of the Corps' default decision is before us in this appeal. 1 We have jurisdiction to adjudicate this appeal pursuant to the Contract Disputes Act, 41 U.S.C. §§ 7101-7109. Because the Corps has shown that it properly terminated the contract for default and Highland has not shown that its default was excusable, the appeal is denied.

1 Post-hearing; the government asserted government claims for excess reprocurement costs, overpayments during performance, and liquidated damages under this contract. Appellant appealed all these claims and all have been set for hearing: reprocurement costs and overpayments, ASBCA Nos. 59746, 59818, 60134; and liquidated damages, ASBCA No. 60385. On 26 February 2016, the files in these associated appeals were consolidated with Highland Al Hujaz Co., Ltd., ASBCA No. 58243. However, this decision only addresses appellant's appeal of the government's termination of Contract No. W917PM-09-C-0049 for default. FINDINGS OF FACT

A. Background

1. Solicitation and Contract Requirements

1. In February 2009, the Corps issued a solicitation for a firm-fixed-price contract for the design and construction of an ANA Corps Support Battalion (CSB) installation to be located adjacent to the ANA Garrison at Camp Hero in Kandahar, Afghanistan (R4, tab 3 at 1, 3, 60).

2. While the project required the CSB to be master planned so that it could ultimately accommodate 1,640 soldiers, the site initially would host about 700 soldiers (R4, tab 3 at 3, 60-61). Accordingly, the solicitation stated that the soldiers' barracks, the dining facility (DFAC), and several priority life-support systems were to be completed by 1 September 2009. If they were not completed by that date, the contractor would be responsible for providing temporary facilities or systems to support 700 soldiers until the permanent facilities or systems were in place. (Id. at 67, 70, 74, 75) The site electrical distribution system, or power system, was one such system. The solicitation stated in red lettering: "If the power system is not completed by September 01, 2009 the contractor will be required to supply temporary power to the compound" (id. at 67).

3. The solicitation set forth in full text local clause 2.2, "ATTACKS FROM HOSTILE ENTITIES," which stated in pertinent part:

This contract is firm fixed-price. Costs incurred in the performance of project execution that arise from the attacks of hostile entities, such as costs arising from damage to or destruction of contractor equipment and facilities, and damage to or destruction of project prior to Government acceptance, are the sole responsibility of the contractor. The Government makes no guarantee to provide the contractor with security, and bears no obligation to reimburse the contractor for costs arising from the attacks of hostile entities. When appropriate, the Contracting Officer may provide the contractor with an equitable adjustment with respect to time - but not cost - in accordance with clause 52.249-10[.]

(R4, tab 3 at 175) The solicitation also set forth in full text an "AI Other Changes in Contract Performance" clause which stated:

2 It is recognized by the parties entering into this contract that performance of the contemplated project will take place in Afghanistan. Afghanistan has been designated by the President of the United States as an area in which Armed Forces of the United States are and have been engaged in combat. As such, circumstances may cause the contemplated project to be [a]ffected during said performance. Examples of such circumstances include but are not limited to: Outbreak of hostilities in or near the project site; changes in contemplated project site (ownership of the project); U.S. Government and Afghanistan Government policy changes; site access denials; and other unforeseeable changes in the conditions of the project site that prevent the completion of the project as originally contemplated. Such circumstances may require the contract to be terminated, relocated, redesigned, etc[.], or a combination of factors. The aforementioned possibly [sic] remedy to unforeseen circumstances is meant to be illustrative and not all inclusive. In the event the Contractor is UNABLE to perform the project on the site set forth and described in the contract for any of the circumstances set forth above, the Contractor shall be entitled to an equitable adjustment to the [a]ffected terms and conditions of the contract. [Italics added]

(Id. at 54) Similarly, the solicitation recognizes that: "Construction delays due to full or partial base closures due to incidents such as demonstrations, civil unrest and outright attacks will be examined on an individual basis for consideration of time extensions" (R4, tab 3, § 01060, special clauses, 1.22.3).

4. On 26 February 2009, the Corps amended its solicitation, extending the move-in date for the barracks and priority life-support systems from 1 September 2009 to 1 January 2010 (R4, tab 4 at 1). Additionally, several "Questions and Answers" were incorporated into the solicitation by the 26 February 2009 amendment (id. at 6-9). One of the questions was whether a contract line item number (CLIN) would be added for CSB temporary facilities in the event the contractor was unable to have the barracks and or the priority life-support systems completed by the move-in date. The Corps' response was:

NO. The contractor should bid appropriately according to the contractor's ability to complete the permanent facilities and utilities within the required schedule. If the contractor believes he will not have the life support facilities

3 completed by the Soldier move-in date, then he should include the temporary facilities cost into his bid proposal.

(Id. at 7) Additionally, the Corps confirmed that the number of soldiers to be supported initially would be 700 and that the battalion of ANA soldiers was expected to actually move in and occupy the barracks by the revised move-in date, 1 January 2010 (id. at 7).

5. On 27 March 2009, the government amended the solicitation to incorporate additional "Questions and Answers" (R4, tab 8 at 1, 5-19). Referring to the solicitation's Attacks from Hostile Entities clause (see findiµg 3), and noting the "rise of terrorist incidents and the deterioriation [sic] of security conditions throughout Afghanistan," one prospective offeror "respectfully requested" that the Attacks from Hostile Entities clause be replaced by a "War Risk" clause that shifted the risk of loss of equipment and materials resulting from such attacks to the government (id. at 9). The Corps declined to make such a change, insisting instead that:

THE CONTRACTOR MUST BID UPON THIS PROJECT KNOWING ALL RISKS ASSOCIATED WITH CONSTRUCTION IN AFGHANISTAN.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Amber Resources Co. v. United States
538 F.3d 1358 (Federal Circuit, 2008)
Tgc Contracting Corporation v. United States
736 F.2d 1512 (Federal Circuit, 1984)
Darwin Construction Co., Inc. v. United States
811 F.2d 593 (Federal Circuit, 1987)
Lisbon Contractors, Inc. v. The United States
828 F.2d 759 (Federal Circuit, 1987)
Dcx, Inc. v. William J. Perry, Secretary of Defense
79 F.3d 132 (Federal Circuit, 1996)
Morganti National, Inc. v. United States
49 Fed. Cl. 110 (Federal Claims, 2001)
Aptus Co. v. United States
62 Fed. Cl. 808 (Federal Claims, 2004)
Pigeon v. United States
27 Ct. Cl. 167 (Court of Claims, 1892)
Pennsylvania Coal & Coke Corp. v. United States
70 F. Supp. 136 (Court of Claims, 1947)
Willems Industries, Inc. v. United States
295 F.2d 822 (Court of Claims, 1961)
United States Fidelity & Guaranty Co. v. United States
676 F.2d 622 (Court of Claims, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
Highland Al Hujaz Co., Ltd., Counsel Stack Legal Research, https://law.counselstack.com/opinion/highland-al-hujaz-co-ltd-asbca-2016.