Bethlehem Steel Co. v. United States

75 Ct. Cl. 845, 1932 U.S. Ct. Cl. LEXIS 282, 1932 WL 2210
CourtUnited States Court of Claims
DecidedNovember 14, 1932
DocketNo. E-454
StatusPublished
Cited by9 cases

This text of 75 Ct. Cl. 845 (Bethlehem Steel Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bethlehem Steel Co. v. United States, 75 Ct. Cl. 845, 1932 U.S. Ct. Cl. LEXIS 282, 1932 WL 2210 (cc 1932).

Opinion

Williams, Judge,

delivered the opinion of the court:

The plaintiff sues to recover $133,099.20, an amount withheld by the defendant as liquidated damages because of alleged delays in the delivery of certain shell manufactured and furnished by the plaintiff to the Ordnance Department of the United States Army, under a contract entered into between the parties on October 24, 1916.

The defendant has interposed a counterclaim alleging there is a balance due from the plaintiff to the defendant under other and different contracts entered into between them.

The contract, which is made a part of the findings of fact by reference, provided that the plaintiff manufacture and deliver to the Ordnance Department of the Army, f. o. b. plaintiff’s works, one thousand seven hundred and fifty 12-inch armor-piercing shell (designated and hereinafter referred to as A. P. shell) at $325 each; and eight thousand five hundred 12-inch deck-piercing shell (designated as D. P. shell) at $242 each, making a total contract price for all the shell, $2,625,750.

The contract provided that deliveries of the A. P. shell should commence one year after the date of the execution of the contract and continue thereafter at the rate of 300 shell per month until complete delivery of the 1,750 shell had been made; that deliveries of the D. P. shell should commence one year after the date of the execution of the contract, 500 shell per month to be delivered during the first four months, and thereafter deliveries to be made at the rate of 1,000 per month until complete delivery of the D. P. shell had been made.

The contract further provided that, in the event of failure on the part of plaintiff to make deliveries of the shell within the date or dates specified for delivery, a deduction as liquidated damages might be made by the defendant for each and every day of delay beyond the date or dates on which deliveries were due, one thirtieth of 1 per cent of the contract price of all due and undelivered material.

The plaintiff manufactured and delivered, and the defendant accepted, the entire lot of 8,500 D. P. shell, and was paid the contract price therefor, less $10,672.20, which the defendant deducted and withheld as liquidated damages on account of delays in the deliveries of certain lots of the shell.

[861]*861The plaintiff manufactured and tendered to the defendant for acceptance the 1,750 A. P. shell covered in the contract. The defendant accepted 1,617 of the shell and paid plaintiff the contract price for the same less $117,818.84, which amount was withheld as liquidated damages because of delays in deliveries of the shell. The remaining 133 A. P. shell were rejected as defective.

Subsequent to the rejection of the 133 A. P. shell, and after the rest of the shell covered in the contract had been delivered and accepted, the plaintiff and defendant entered into a supplemental contract wherein the 133 defective shell were canceled from the original contract, and it was provided that they should be accepted by the defendant at the rate of $122 per shell, in lieu of the original contract price of $325 per shell. Pursuant to the terms of the supplemental contract the defendant accepted delivery of the 133 defective A. P. shell and paid to plaintiff the agreed price of $122 per shell, less $4,608.16, withheld as liquidated damages because of alleged delays in deliveries of the shell, making the total amount withheld as liquidated damages, $133,099.20.

In computing the delays in deliveries, upon which liquidated damages were withheld in respect to both the D. P. shell and the A. P. shell, the time consumed by the Inspectors of Ordnance in making ballistic tests was included. There was also included in the delays charged in deliveries of the A. P. shell, 200 days during which the production of the shell was interrupted by the suspension order of the Chief of Ordnance.

Article 16 of the Instructions to Bidders, which constitutes a part of the contract, provides:

“ In reckoning liquidated damages for delays in delivery, a lot of projectiles, if accepted, shall be considered as delivered on the day on which the lot is turned over to the inspector, the boxing and marking of the entire lot having been completed; the time from the date of selection by the inspector of projectiles from the lot for ballistic test until notification is received by the contractor of the result of this test will not be considered.”

It is conceded that the number of days consumed by the Government in making ballistic tests was erroneously in-[862]*862eluded in computing the delays upon which liquidated damages were assessed. The parties have entered into a stipulation that the liability of the plaintiff for liquidated damages on account of delays in deliveries of the D. P. shell was $1,911.80, instead of $10,672.20, the amount withheld by the defendant.

The parties have also stipulated the number of days consumed by the Government in making ballistic tests of the A. P. shell, and the defendant concedes that because of the erroneous inclusion of this time in the computation of the delays in delivery of these shell, and because of the inclusion of the 200 days during which production of the shell was interrupted by the suspension order of the Chief of Ordnance, liquidated damages in the amount of $48,341.68 were erroneously withheld in respect to the A. P. shell.

The parties are, therefore, in agreement that the plaintiff is entitled to a refund of $57,102.08 of the amount withheld by the Government, and the controversy between them, as it relates to the plaintiff’s claim, is confined to two items, viz: (1) $4,608.16 withheld because of delays in delivery of the 133 defective A. P. shell, and (2) $69,477.16, the balance of the amount withheld because of delays in deliveries of the 1,617 A. P. shell.

The 133 defective A. P. shell. — On June 25, 1920, after all the shell covered in the contract had been delivered to the defendant, and had been accepted by it, except the 133 defective A. P. shell, the parties entered into the supplemental contract heretofore referred to. The supplemental contract after referring to the original contract providing for the manufacture of 1,750, more or less, 12-inch A. P. shell recites:

“Article I. The number of 12// A. P. shell model of 1912 called for in the original contract shall be reduced from 1,750 to 1,617 of such shell;
“ That by reason of said reduction in quantity there shall be deducted from the contract price the sum of $325 for each of the 133 shell hereby cancelled from said contract.
“Article II. The contractor agrees to deliver and the United States agrees to accept 133 defective 12" A. P. shell model of 1912.
[863]*863“The United States agrees to pay the contractor for said 133 defective 12" A. P. shell the sum of $122 each, f. o. b. contractor’s plant.”

There is no provision in the supplemental contract as to the date of delivery of the defective shell, and no provision as to liquidated damages. Delivery of the shell was made on August 10, 1920.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

B. D. Click Co. v. United States
614 F.2d 748 (Court of Claims, 1980)
Thompson Ramo Wooldridge Inc. v. The United States
361 F.2d 222 (Court of Claims, 1966)
Hol-Gar Manufacturing Corp. v. The United States
351 F.2d 972 (Court of Claims, 1965)
MacLaren Sportswear Co. v. United States
101 F. Supp. 885 (Court of Claims, 1952)
Loftis v. United States
76 F. Supp. 816 (Court of Claims, 1948)
Germain Lumber Co. v. United States
56 F. Supp. 1001 (W.D. Pennsylvania, 1944)
H. W. Zweig Co. v. United States
92 Ct. Cl. 472 (Court of Claims, 1941)
Phoenix Bridge Co. v. United States
85 Ct. Cl. 603 (Court of Claims, 1937)

Cite This Page — Counsel Stack

Bluebook (online)
75 Ct. Cl. 845, 1932 U.S. Ct. Cl. LEXIS 282, 1932 WL 2210, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bethlehem-steel-co-v-united-states-cc-1932.