Martin J. Simko Construction, Inc. v. United States

33 Cont. Cas. Fed. 74,888, 11 Cl. Ct. 257, 55 U.S.L.W. 2400, 1986 U.S. Claims LEXIS 764
CourtUnited States Court of Claims
DecidedNovember 25, 1986
DocketNos. 687-81C, 694-83C
StatusPublished
Cited by17 cases

This text of 33 Cont. Cas. Fed. 74,888 (Martin J. Simko Construction, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Martin J. Simko Construction, Inc. v. United States, 33 Cont. Cas. Fed. 74,888, 11 Cl. Ct. 257, 55 U.S.L.W. 2400, 1986 U.S. Claims LEXIS 764 (cc 1986).

Opinion

OPINION

MOODY R. TIDWELL, III, Judge:

This proceeding was originally brought before our predecessor court, the United States Court of Claims, in 1981 by Petition No. 687-81C. Plaintiff subsequently filed Complaint No. 694-83C in this court in 1983. The gravamen of the action is that on July 7, 1978 defendant, by the United States Air Force, entered into contract No. F27604-78-C0036 for the construction of a jet fuel loading facility at Pease Air Force Base, New Hampshire, which contract was [262]*262terminated for default on November 28, 1980. Plaintiff seeks to have the termination for default converted to a termination for the convenience of the government as provided in the disputes clause of the contract (clause No. 5 of the General Provisions, incorporated by reference), thereby negating defendant’s assessment of liquidated damages and reprocurement costs. Plaintiff also seeks reimbursement of time and money for separate claims under the changes clause of the contract (clause No. 3 of the General Provisions of the contract, also incorporated by reference). In its Amended Answer defendant filed counterclaims of fraud in eight of plaintiff’s claims. Trial was conducted at Pease Air Force Base, Portsmouth, New Hampshire, on the issue of liability.

After observing the witnesses, careful review of the record, including transcripts, documentary evidence, briefs, and proposed findings of fact, the court finds that notwithstanding plaintiff’s inability to complete the contract, the termination for default was improper, liquidated damages should be assessed, plaintiff is entitled to several equitable adjustments to the contract price and time for performance, and defendant’s counterclaims are not properly before the court.

GENERAL FACTS

On July 7, 1978, Martin J. Simko Construction, Inc. was determined by defendant to be the successful bidder under a formally advertised procurement, and was awarded contract No. F27604-78-C0036.1 The contract was for the construction of a fuel storage facility at Pease Air Force Base, New Hampshire at a fixed price of $52,000. A fuel storage facility was at the site but it had been designed to store and pump methyl alcohol. This contract was intended to change and upgrade the facility to handle JPTS fuel. Defendant described JPTS as an “exotic” fuel which reacts chemically with a range of other methyls, including carbon, steel and zinc. In addition, the contractor was to repair a large leaky underground steel storage tank. The storage tank itself and other pieces of equipment were to be sandblasted clean and coated with several coats of epoxy to prevent chemical interaction between the steel walls of the tank and the fuel. To aid in periodic maintenance thereafter, plaintiff was to fit the tank with an interior aluminum ladder. The contract also called for plaintiff to supply a totally-enclosed, weather-protected pump mounted partially in and partially on top of the tank. The purpose of the pump was to move the fuel through an above-ground pipeline, to be fabricated by plaintiff from aluminum or stainless steel at plaintiff’s option, to a government-furnished separator which would remove water in the fuel. From the separator, the fuel would be pumped through more above-ground pipes to tank trucks parked on a concrete pad, also to be fabricated by the contractor.

The contract specified that plaintiff was to submit certain materials and items, identified at Special Condition § 2-06, to the contracting officer for approval prior to installation with the caveat that if the contractor installed the materials or items before approval, it did so at its own peril. If rejected, the materials or items would have to be removed and replaced with approved materials or items, at no cost to the government.

The contract required that the work be completed within 120 days from August 5, 1978, the date the notice to proceed was issued. The contract completion date was, therefore, December 5, 1978. Defendant reports that from August 5, 1978 until September 12, 1978 plaintiff had workers on the site only once and that from the outset plaintiff began to fall behind its construction schedule. Indeed, defendant felt duty-bound to warn plaintiff of the slippage on several occasions. Plaintiff eventually re- • ceived two time extensions for performance [263]*263for a total of 52 days and two exclusionary periods for on-site work of nine months.2 Defendant determined the extended completion date to be June 4, 1979, however, unless there were extenuating circumstances not reported to the court, the actual extended completion date was October 24, 1979.3

The contractor and at least one of its subcontractors had great difficulty in performing the work called for in the contract. Plaintiff lays the fault at the feet of defendant, arguing that the instructions it received throughout the job from the contracting and engineering officers and their representatives were impossible to meet and that portions of the contract were impossible to perform. Defendant charged that plaintiff is guilty of neglect, incompetence and mismanagement and that its own problems led inevitably to the termination for default. The reasons given plaintiff by the contracting officer for the termination for default were (1) failure to complete the work within the time specified, (2) failure to correct items identified in a notice, dated September 8, 1979, that workmanship was unacceptable, and (3) failure of plaintiff to respond satisfactorily to defendant’s instructions to proceed with the project given on February 25, 1980, March 19, 1980 and May 5, 1980. The contracting officer also determined that plaintiff’s failure to perform was not due to causes beyond plaintiffs control, and was not without its fault or negligence.

THE TERMINATION FOR DEFAULT

A. Plaintiff’s Inability to Complete the Contract.

The contracting officer determined that the default termination was directly supported by plaintiff’s inability to properly weld aluminum pipe. The following contractual provisions were applicable to the welding issue, as well as to some of plaintiff’s other claims.

SECTION 6

MISCELLANEOUS PIPE

* * * * * *

A. 6-03 Run pipe in straight, continuous lengths between elbows.

B. Make all joints watertight and sealed by approved methods, applicable to the pipe use and material.

SECTION 7

FUEL PIPE AND FITTINGS

7-01. QUALITY ASSURANCE:

A. Applicable Publications: The following publications, latest editions, form part of this specification:

* * * * * *
3. American Petroleum Institute (API)
1104—Standard for Field Welding of Pipeline.
* * * * * *

PART 2—PRODUCTS

7-02. PRODUCTS AND MATERIALS:

A. New Fuel Transfer Piping and Appendages:
* *****
2. For Above Ground Installation: Stainless Steel Seamless Pipe and Fittings, American Iron & Steel Institute (AISI) Type 316 Alloy, ANSI B16.19, Schedule 5S dimensions.
OR AT THE CONTRACTOR’S OPTION:
[264]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

M.E.S., Inc. v. United States
104 Fed. Cl. 620 (Federal Claims, 2012)
Ferguson Propeller, Inc. v. United States
59 Fed. Cl. 51 (Federal Claims, 2003)
PCL Construction Services, Inc. v. United States
53 Fed. Cl. 479 (Federal Claims, 2002)
St. Paul Fire & Marine Insurance v. City of Green River
93 F. Supp. 2d 1170 (D. Wyoming, 2000)
Abcon Associates, Inc. v. United States
44 Fed. Cl. 625 (Federal Claims, 1999)
Town Center Management Corp. v. United States
39 Cont. Cas. Fed. 76,691 (Federal Claims, 1994)
Mega Construction Co. v. United States
39 Cont. Cas. Fed. 76,564 (Federal Claims, 1993)
Mega Construction Co. v. United States
37 Cont. Cas. Fed. 76,305 (Court of Claims, 1992)
International Fidelity Insurance v. United States
37 Cont. Cas. Fed. 76,277 (Court of Claims, 1992)
Southland Enterprises, Inc. v. United States
37 Cont. Cas. Fed. 76,238 (Court of Claims, 1991)
Chinook Research Laboratories, Inc. v. United States
22 Cl. Ct. 853 (Court of Claims, 1991)
Calfon Construction Inc. v. United States
35 Cont. Cas. Fed. 75,738 (Court of Claims, 1989)
Timberland Paving & Construction Co. v. United States
35 Cont. Cas. Fed. 75,713 (Court of Claims, 1989)
H. Landau & Co. v. United States
35 Cont. Cas. Fed. 75,599 (Court of Claims, 1988)
Baltimore Contractors, Inc. v. United States
34 Cont. Cas. Fed. 75,267 (Court of Claims, 1987)
H.H.O. Co. v. United States
34 Cont. Cas. Fed. 75,256 (Court of Claims, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
33 Cont. Cas. Fed. 74,888, 11 Cl. Ct. 257, 55 U.S.L.W. 2400, 1986 U.S. Claims LEXIS 764, Counsel Stack Legal Research, https://law.counselstack.com/opinion/martin-j-simko-construction-inc-v-united-states-cc-1986.