Timberland Paving & Construction Co. v. United States

35 Cont. Cas. Fed. 75,713, 18 Cl. Ct. 129, 1989 U.S. Claims LEXIS 179, 1989 WL 101100
CourtUnited States Court of Claims
DecidedAugust 31, 1989
DocketNo. 123-81C
StatusPublished
Cited by2 cases

This text of 35 Cont. Cas. Fed. 75,713 (Timberland Paving & Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Timberland Paving & Construction Co. v. United States, 35 Cont. Cas. Fed. 75,713, 18 Cl. Ct. 129, 1989 U.S. Claims LEXIS 179, 1989 WL 101100 (cc 1989).

Opinion

OPINION

BRUGGINK, Judge.

This action involves a road project awarded on September 29; 1978 to Timberland Paving & Construction Company, a Washington state corporation, by the United States acting through the Bureau of Indian Affairs (BIA). Timberland was default terminated on April 23, 1980. Plaintiff filed a complaint here pursuant to the Contract Disputes Act of 1978, 41 U.S.C. §§ 601-613 (1982) (CDA) asserting breach of contract, and seeking an equitable adjustment for changes and differing site conditions. Defendant counterclaimed, seeking liquidated damages and reprocurement costs. At the conclusion of the first trial, conducted over a two week period in Yakima, Washington, the court (Woods, J.) determined that Gene R. Powers, purportedly acting on behalf of the Government, did not in fact have the authority as Contracting Officer (CO) to issue a termination for default. 8 Cl.Ct. 653 (1985). The matter was remanded to the CO “to determine the amount due plaintiff as if the April 23, 1980, notice of termination for default ... had been issued pursuant to the contract clause providing for termination of the contract for convenience of the government.” Id. at 662. The matter has been the subject of two subsequent CO decisions and extensive efforts at settlement. The action is presently before the court after trial on June 27 and 28, 1989 on the merits of Timberland’s current claim for termination for convenience costs.

FACTUAL BACKGROUND1

The project at issue involved road work in the Signal Peak area of the Yakima Indian Reservation. It was given number YIR 140(4). The chief features of the original project design were: (a) excavating unclassified material bordering a xk mile stretch of the road (“rock bluff” area) to be used as fill in at least five grade change locations; (b) changing the road’s vertical grade in five locations; and (c) replacing the existing gravel surface with an asphalt surface. The primary purposes of the BIA’s design for the rock bluff excavation were to move the toe of the slope back approximately sixteen feet to create a catchment into which materials raveling from the slope face could drop without endangering traffic on the road and to provide fill for realignment of parts of the vertical grade. The contract required that a rock bluff between road stations 297 and 323 be excavated with a one-quarter-to-one backslope.2 The excavated material was to be used as fill elsewhere. The contract did not specify the method of excavation except as follows:

Section 203.03 Unless otherwise provided in the contract, rock excavation which requires drilling and shooting shall be presplit ... The finished presplit slope shall be reasonably uniform and free of loose rock. Variance from the true plane of the excavated backslope shall not exceed 12 inches (305 mm); however, localized irregularities or surface variations that do not constitute a safety hazard or an impairment to drainage courses or facilities will be permitted____

In addition, the contract rock bluff drawing contains the following note: “Rock excavation which requires drilling and shooting shall be presplit.”3

[133]*133The pre-existing road originally had been completed in 1964. The Contracting Officer’s Representative, W. David Argo, testified that the rock bluff was not in fact all rock. The bluff was approximately half a mile long, of which about 1800 feet were rock, and 1000 feet were dirt. One of the effects of the redesign brought about by the project was to steepen the slope. It was not anticipated that the new slope would be sufficient to keep all loose rock from falling. It was expected, rather, that rock would fall into the catchment at the base of the slope. Argo described the rock as having horizontal and vertical fracture planes which lent themselves to relative stability on a one-quarter-to-one slope.

Timberland did a site investigation before submitting its bid. On September 29, 1978, defendant awarded plaintiff the contract for a fixed price of $1,282,842.00. Work was to be completed within 220 calendar days after receipt of the notice to proceed. Timberland received the notice on October 19, 1978 and the performance period began to run the following day under the contract terms. On November 1, 1978 Timberland subcontracted with North Central Construction, Inc. (North Central). The subcontract required North Central to load, haul and place fill material including the rock and earth excavated by the excavation subcontractor. On November 6, 1978 Timberland subcontracted with the El-lensberg Joint Venture to crush and stockpile basecourse and paving aggregate. On November 27, 1978 plaintiff obtained Morgan & Son Earth Moving, owned by Jay Morgan (Morgan) to do the unclassified excavation work (clearing, pioneering, drilling and blasting the rock bluff area). Third party American Insurance Co. furnished payment and performance bonds for plaintiff in connection with the contract.

With respect to the decision to order commencement of work in October 1978, Argo testified that fall is a good time to do excavation work since the soil is normally dry. He also testified that there is usually no snow at the altitudes in question (2500— 4000 feet) in October, although he would expect some snow at the higher elevations in November or December. He referred to October and November as the tail end of the season, and said that late November was “pretty chancy”. The commencement of contract time was nevertheless appropriate, he felt, because it was possible to do rock work, although some amount of additional scaling4 might be precipitated because of the over-wintering of the cut slope. Timberland did not at the time complain about the start-to-work notice. No work was performed at the job site in 1978. Oil December 8, 1978, Argo issued an oral work suspension order due to inclement weather. On December 21, 1978 the CO suspended operations at the close of business the previous day.5

Daniel Pokorny, project engineer for Timberland, defended the decision not to proceed in October. He testified that access to the work site is tenuous any time from the first or middle of November. The only risk described, however, was that two pieces of Morgan’s equipment, a D8 Caterpillar tractor (CAT) and a drill, might be caught in snow. The difficulty with that was that the tractor might have to be “walked out,” or that a “circuitous” lower route back to Yakima might have to be employed. He conceded that it would have been possible to get the excavation work on the rock bluff started, along with other smaller items of work.

On April 23, 1979, Timberland received notice from defendant to resume work and was informed that 170 days remained for performance under the contract. On April 23, 1979 Morgan mobilized men and equipment to begin work on the rock bluff road section. Morgan began by building a “pioneer” road on the slope—a primitive road or bench cut into the top half of the slope, [134]*134both as a means of excavation and to enable drilling equipment to be brought in to operate off the bench. The roadbed was made partly by excavating with a bulldozer into the edge of the slope and partly by putting fill material lower down on the slope.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
35 Cont. Cas. Fed. 75,713, 18 Cl. Ct. 129, 1989 U.S. Claims LEXIS 179, 1989 WL 101100, Counsel Stack Legal Research, https://law.counselstack.com/opinion/timberland-paving-construction-co-v-united-states-cc-1989.