Indemnity Insurance Co. of North America v. United States

34 Cont. Cas. Fed. 75,436, 14 Cl. Ct. 219, 1988 U.S. Claims LEXIS 10
CourtUnited States Court of Claims
DecidedJanuary 28, 1988
DocketNos. 122-85C, 343-85C
StatusPublished
Cited by6 cases

This text of 34 Cont. Cas. Fed. 75,436 (Indemnity Insurance Co. of North America v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Indemnity Insurance Co. of North America v. United States, 34 Cont. Cas. Fed. 75,436, 14 Cl. Ct. 219, 1988 U.S. Claims LEXIS 10 (cc 1988).

Opinion

OPINION

MEROW, Judge:

In these consolidated cases, plaintiff has filed a motion for summary judgment requesting that the October 12, 1984 termination for default by the government of its construction agreement be converted to a termination for the government’s convenience. The plaintiff bases its motion on the following facts. The original completion date passed without government termination of the contract and plaintiff continued to perform work which the government had knowledge of and encouraged. The government did not establish a new completion date prior to the default termination. Defendant has crossed moved for partial summary judgment in its favor. The parties agree there are no material facts in issue. For the reasons set forth below in the body of this opinion, defendant’s motion is granted; plaintiff’s motion is denied.

Facts

On September 29, 1982, the U.S. Army Communications and Electronics Command, Ft. Monmouth, New Jersey, awarded Arctic Comer, Inc. (Arctic) a contract for the rehabilitation of the Barker Circle Barracks at Ft. Monmouth, New Jersey. The plaintiff is a surety company which issued performance and payment bonds to Arctic as principal.1 The original contract completion date was March 1, 1984. However, since Arctic had completed only 50 percent of the contract work by the beginning of February 1984, the contract with Arctic was terminated for default (lack of progress) on February 7, [221]*2211984. A Takeover Agreement was executed between the government and the plaintiff, effective March 8, 1984, pursuant to which the plaintiff agreed to perform all of the uncompleted work under the contract.2 The Agreement provided for progress payments and contained a work completion date of July 1, 1984. The Agreement also provided that liquidated damages “will be assessed at the rate of $200 per calendar day until the work required by the contract is completed by the Surety,” commencing on March 2, 1984. On June 22, 1984, the contracting officer sent a cure notice to plaintiff stating that lack of progress endangered timely completion of the contract. Later, the completion date was extended to July 20, 1984, by contract modification. The plaintiff responded to the notice on July 3, 1984, claiming excusable delays. The government requested more specifics and on July 13 the plaintiff listed a number of government-caused delays. By letter of July 27, the contracting officer rejected each claim of excusable delay and requested the plaintiff to show cause why the Takeover Agreement should not be terminated for default. The plaintiff responded on August 10 and 16, 1984, again stating the government had caused the delays and that it had committed in excess of $400,000 toward contract completion. A meeting was held between the contracting officer and representatives of the plaintiff to determine if default could be avoided. By letter of September 7, the contracting officer notified plaintiff the government would only forbear termination until October 1, 1984, if plaintiff secured a new prime contractor. In addition, the plaintiff was told that acceptance of any work would be for the purpose of mitigating damages and that liquidated damages would continue to accrue. The plaintiff agreed to seek bids for a new contractor. However, work on the project basically stopped after September 22. Subsequently, on October 12, 1984, the contracting officer terminated the Takeover Agreement for default because of plaintiffs lack of significant progress, including the fact that no new prime contractor had been secured.

Plaintiff filed with the Claims Court the complaint in No. 122-85C on February 28, 1985, requesting the termination be found improper and that it receive equitable adjustments for government-caused conditions. On March 11, 1985, plaintiff submitted a certified claim to the contracting officer for $867,788. The contracting officer has not issued a decision regarding the claim. The claim in No. 343-85C was filed on June 7, 1985, stating the same causes of action as in No. 122-85C, but requesting, in the alternative, either equitable adjustments or breach of contract damages. On August 15, 1985, defendant’s motion to consolidate the two cases was allowed. Subsequently, on October 11, 1985, plaintiff filed an amended complaint in No. 122-85C adding the cause of action which is the subject of the plaintiff’s motion and defendant’s cross-motion for summary judgment, i.e., that the defendant waived the contract completion date rendering the default termination for failure to complete on time improper. Thus, plaintiff claims the government’s action was in breach of contract entitling the plaintiff to damages.

Discussion

The plaintiff relies on DeVito v. United States, 188 Ct.Cl. 979, 413 F.2d 1147 (1969), which it claims sets forth the proposition that “[t]he Government is estopped from terminating a contract from default for failure to meet the completion date, if the Government encourages continued performance, but does not terminate within a reasonable time or does not set a new completion date.” The court in DeVito explained, at 990-91, 413 F.2d 1147, the rule regarding the waiver of the right to terminate:

Where the Government elects to permit a delinquent contractor to continue performance past a due date, it surrenders its alternative and inconsistent right under the Default clause to terminate, assuming the contractor has not abandoned [222]*222performance and a reasonable time expired for a termination notice to be given. * * * The necessary elements of an election by the nondefaulting party to waive default and delivery under a contract are (1) failure to terminate within a reasonable time after the default under circumstances indicating forbearance, and (2) reliance by the contractor on the failure to terminate and continued performance by him under the contract, with the Government’s knowledge and implied or express consent.
* * * The period for termination after default will naturally be greater where the contractor abandons performance or where his situation is such as to render performance impossible or unlikely, than where he continues performance in reliance on the lack of termination and proceeds to incur obligations in efforts to perform * * *.

The plaintiff claims the following facts support its position and mandate that, under the law, plaintiff is entitled to summary judgment that the government improperly terminated the Takeover Agreement: The contract completion date was July 20, 1984; the defendant did not terminate on July 20, 1984, but instead requested and allowed the plaintiff to continue performance; the government never set a new contract completion date; and, in reliance thereon, the plaintiff continued to perform until the contracting officer terminated the Agreement on October 12, 1984.

The defendant argues that neither the courts nor the boards of contract appeals have held that the DeVito rule “is as applicable to a construction contract, such as the one at issue here, as it is to supply contracts, such as the one at issue in De-Vito” Moreover, according to defendant, even if DeVito

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Corps v. United States
Federal Claims, 2019
5860 Chicago Ridge, LLC v. United States
104 Fed. Cl. 740 (Federal Claims, 2012)
Martin Construction, Inc. v. United States
102 Fed. Cl. 562 (Federal Claims, 2011)
Abcon Associates, Inc. v. United States
44 Fed. Cl. 625 (Federal Claims, 1999)
International Fidelity Insurance v. United States
37 Cont. Cas. Fed. 76,277 (Court of Claims, 1992)
Timberland Paving & Construction Co. v. United States
35 Cont. Cas. Fed. 75,713 (Court of Claims, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
34 Cont. Cas. Fed. 75,436, 14 Cl. Ct. 219, 1988 U.S. Claims LEXIS 10, Counsel Stack Legal Research, https://law.counselstack.com/opinion/indemnity-insurance-co-of-north-america-v-united-states-cc-1988.