Olson Plumbing & Heating Co. v. United States

602 F.2d 950, 26 Cont. Cas. Fed. 83,506, 221 Ct. Cl. 197, 1979 U.S. Ct. Cl. LEXIS 220
CourtUnited States Court of Claims
DecidedJuly 18, 1979
DocketNo. 496-77
StatusPublished
Cited by33 cases

This text of 602 F.2d 950 (Olson Plumbing & Heating Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Olson Plumbing & Heating Co. v. United States, 602 F.2d 950, 26 Cont. Cas. Fed. 83,506, 221 Ct. Cl. 197, 1979 U.S. Ct. Cl. LEXIS 220 (cc 1979).

Opinion

SMITH, Judge,

delivered the opinion of the court:

This is a contract case in which, by cross-motions for summary judgment, the court is asked to review a decision of the Armed Services Board of Contract Appeals (the board)1 in accordance with the standard of review of the Wunderlich Act. 41 U.S.C. §§ 321, 322 (1976). The question for decision is whether the board’s determination, that the Government did not waive its right to terminate the production and design contract with plaintiff, is supported by substantial evidence and is correct as a matter of law. We hold that the contract was properly terminated and affirm the decision of the board.

I.

On October 21, 1970, plaintiff, Olson Plumbing & Heating Company (Olson), was awarded contract No. FO-5611-71-C-0025, a Small Business Set-Aside, for the installation of a high temperature hot water line encased in fiberglass reinforced plastic (FRP) at the United States Air Force Academy (Academy) near Colorado Springs, Colorado.2 Since the FRP conduit was a relatively new product and there were no regulations governing its use, the design specifications inserted into the contract by the Government were drawn from the design specifications of Ric-Wil, an experienced manufacturer of FRP conduit.3 These specifications were incomplete. The omitted design details had to be provided by the supplier of FRP conduit chosen by the contractor. In its letter confirming its bid, plaintiff informed defendant that it was going to use conduit supplied by the E. B. Kaiser Company (EBKO).4

[201]*201Initially, plaintiff had until June 20,1971, 202 days after the notice to proceed was issued, to finish the line. It worked on the above-ground portion of the line while waiting for the first delivery of pipe. After receiving the first shipment of FRP conduit on March 1, 1971, plaintiff installed, backfilled, and successfully pressure-tested the portion of the line beneath the parking lot. Subsequent deliveries of pipe were discovered to have been damaged during shipping, and air pressure leaks were discovered in the installed portion of the line which had been laid with the first shipment of conduit.

On April 26 and 27, 1971, representatives of Olson, the Academy, and EBKO met and discussed the problems. The recommendation of the EBKO representative to patch and repair some of the pipe in the field under the supervision of a factory representative and to reject 18 sections of conduit was adopted. The representative of the manufacturer of the pipe, Wolf Ridge Plastics, Inc., concurred with this recommendation, and both plaintiff and the Government relied on this advice. This was not the end of plaintiffs troubles. The anchors designed by EBKO were defective and had to be redesigned. Olson had to replace two anchors located beneath the parking lot.

On July 6, 1971, the replacement conduit arrived at the site and was discovered to have also been damaged during shipment. It was rejected and returned to the manufacturer. In August 1971, the parties agreed to extend the completion date for 77 days or until September 8, 1971.5 Olson did not complete the contract by the due date, but defendant did not terminate the contract for default. Instead, on the delivery date, September 8, 1971, it sent plaintiff two letters stating that it was not waiving its rights by permitting plaintiff to continue performance and that liquidated damages would be assessed at the rate of $105 per day as stipulated in the contract, from September 8,1971, until the date of completion. Another due date was not set.

[202]*202On September 23, 1971, plaintiff received the same 18 sections of pipe which it had previously rejected and returned. Attempts to repair these sections had been made at the factory, but they were only partially successful. EBKO’s advice to repair and use the casings which had been rejected in April was agreed to by the parties. These repairs were successful. After backfilling and pressure-testing, new leaks developed at the top of the casings and above the pipe supports. On January 12, 1972, the carrier pipe was connected and used until the reprocurement contractor had to disconnect the line.

On January 11, 1972, the parties met and agreed to test some remedies for the leaks above the pipe supports.6 The tests were conducted between April 24 and May 5, 1972. After the testing was completed, plaintiff refused to implement any suggested repairs unless the Government or the manufacturer would guarantee the results. Plaintiff did not propose a solution. During the summer of 1972, the line was further damaged by exposure and was torn apart in four places by a summer flood.

In a letter dated June 19, 1972, plaintiff stated that the specifications were impossible of performance without changes and that a claim for expenses would be filed. On August 4, 1972, defendant replied with a letter to Olson to show cause, listing deficiencies in the line and inviting Olson to supply reasons why the contract should not be terminated for default. Plaintiffs attorney responded with a request that the contract be terminated for convenience or converted to a cost-plus contract. This request was rejected at a meeting held on August 23, 1972.

At the final meeting held on September 15, 1972, the Government suggested as a solution that the spacing for the pipe supports be revised and that the existing pipe be replaced with FRP conduit which was at least 0.300-inch thick.7 Plaintiff interpreted the Government’s recommendation as a directive. Instead of suggesting an alternative [203]*203method of repair, on October 3, 1972, plaintiffs attorney informed the Government that its request that Olson replace the conduit and/or respace the pipe supports was beyond the scope of the contract and that Olson would not resume performance. The Government terminated the contract for default on October 17, 1972. The reprocuring contract officer requested bids for both repairing and replacement of the existing system. The bid for repair was higher than the bids for replacement. The reprocurement contract was awarded to the lowest bidder. The reprocurement contractor timely completed replacement of the underground system using Rie-Wil conduit and the Government’s specifications which were, in all material respects, similar to those in plaintiffs contract.

On appeal to the ASBCA from the contracting officer’s decision to terminate the contract, the board found that the Government was within its rights when it terminated plaintiff for default because plaintiff had abandoned the contract and the Government had not waived the due date. The board found that there had been a tacit agreement between the parties that work would be held in abeyance from January 12, 1972, until the joint testing project could be completed and that plaintiff should be given credit for the 10 days it should have taken to repair the damage caused by a summer flood. Accordingly, it reduced the 733 days of liquidated damages assessed against Olson to 514 days.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Consorzio Stabile GMG S.c.ar.1.
Armed Services Board of Contract Appeals, 2023
State Corps v. United States
Federal Claims, 2019
ECC CENTCOM Constructors, LLC
Armed Services Board of Contract Appeals, 2018
Jennifer Lanclos v. United States
133 Fed. Cl. 113 (Federal Claims, 2017)
Stathis v. United States
120 Fed. Cl. 552 (Federal Claims, 2015)
ASFA International Construction Industry and Trade, Inc.
Armed Services Board of Contract Appeals, 2014
5860 Chicago Ridge, LLC v. United States
104 Fed. Cl. 740 (Federal Claims, 2012)
Todd Construction, L.P. v. United States
94 Fed. Cl. 100 (Federal Claims, 2010)
General Injectables & Vaccines, Inc. v. Gates
527 F.3d 1375 (Federal Circuit, 2008)
Hutton Contracting Co. v. City of Coffeyville
487 F.3d 772 (Tenth Circuit, 2007)
Tecom, Inc. v. United States
66 Fed. Cl. 736 (Federal Claims, 2005)
Bernardi Brothers v. United States
47 Fed. Cl. 708 (Federal Claims, 2000)
PCL Construction Services, Inc. v. United States
47 Fed. Cl. 745 (Federal Claims, 2000)
Abcon Associates, Inc. v. United States
44 Fed. Cl. 625 (Federal Claims, 1999)
SIPCO Services & Marine Inc. v. United States
42 Cont. Cas. Fed. 77,277 (Federal Claims, 1998)
Davies Precision Machining, Inc. v. United States
35 Fed. Cl. 651 (Federal Claims, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
602 F.2d 950, 26 Cont. Cas. Fed. 83,506, 221 Ct. Cl. 197, 1979 U.S. Ct. Cl. LEXIS 220, Counsel Stack Legal Research, https://law.counselstack.com/opinion/olson-plumbing-heating-co-v-united-states-cc-1979.