Panoramic Studios, Inc. v. The United States

413 F.2d 1156, 188 Ct. Cl. 1092, 1969 U.S. Ct. Cl. LEXIS 56
CourtUnited States Court of Claims
DecidedJuly 16, 1969
Docket278-67
StatusPublished
Cited by4 cases

This text of 413 F.2d 1156 (Panoramic Studios, Inc. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Panoramic Studios, Inc. v. The United States, 413 F.2d 1156, 188 Ct. Cl. 1092, 1969 U.S. Ct. Cl. LEXIS 56 (cc 1969).

Opinion

PER CURIAM:

This case was referred to Trial Commissioner Mastín G. White with directions to make recommendation for conclusions of law on plaintiff’s motion for summary judgment and defendant’s cross-motion for summary judgment under the order of reference and Rule 99(c). The commissioner has done so in an opinion and report filed on January 14, 1969, wherein such facts as are necessary to the opinion are set forth. Plaintiff requested review of the commissioner’s opinion and recommended conclusion of law and the case has been submitted on oral argument of counsel and the briefs of the parties.

With respect to the termination claim, this case is to be distinguished on its facts from DeVito, Receiver v. United States, Ct.Cl., 413 F.2d 1147, likewise decided today. Here the contractor did nothing substantial toward performance from the end of August, 1965 to the end of April, 1966, and the Government did not by its conduct lead the contractor to believe that continued performance was expected.

On the breach-of-contract issue, the plaintiff contends that the principle of Helene Curtis, Inc. v. United States, 312 F.2d 774, 160 Ct.Cl. 437 (1963), and similar decisions, applies not only where the Government withholds necessary information prior to the making of the contract, but also where it with *1158 holds such information which it learns for the first time during performance. For a number of reasons we do not decide that issue in this case. The administrative record was not at all directed to that point and accordingly does not permit of a proper answer. Plaintiff did not ask for a de novo trial on the issue until the oral argument before the court, when it did so belatedly. We decline, however, to exercise our discretion to require a do novo trial at this late stage, especially since plaintiff has not given us any reason for believing that it could not have been expected to make inquiry on its own, in the course of performance, as to the process it now says the defendant learned about and did not tell plaintiff. *

Since the court agrees with the commissioner’s opinion and recommended conclusion of law, as hereinafter set forth, it hereby adopts the same, together with the above, as the basis for its judgment in this case. Therefore, plaintiff’s motion for summary judgment is denied, defendant’s cross-motion for summary judgment is allowed, and the petition is dismissed.

OPINION OF COMMISSIONER

WHITE, Commissioner: The plaintiff complains in the present case that the defendant acted wrongfully in partially terminating a contract (No. AF 23(601)-4034) between the parties, and also that the defendant breached such contract by failing to furnish to the plaintiff certain information known to the defendant.

Contract No. AF 23(601)-4034 (“the contract”) contained the usual “disputes,” “default,” and “termination for convenience” provisions. Under those provisions, the matter of the defendant’s partial termination of the contract because of alleged default on the part of the plaintiff has heretofore been the subject of administrative proceedings, which culminated in a decision that was rendered by the Armed Services Board of Contract Appeals on April 28, 1967 (ASBCA No. 11559) and was adverse to the plaintiff. In the present action, the plaintiff attacks the administrative decision of April 28, 1967 on the ground that three questions were erroneously decided by the Board.

The administrative record has been filed with the court; and the parties have submitted cross-motions for summary judgment on the basis of the pleadings and the administrative record. The plaintiff has not requested a trial de nova on its claim requesting an alleged breach of contract.

It is my opinion that the plaintiff is not entitled to recover.

The contract was awarded to the plaintiff on May 22, 1964 by the defendant (represented by a contracting officer of the Aeronautical Chart and Information Center, Department of the Air Force), following a competitive bidding procedure. It provided for the preparation by the plaintiff and delivery to the defendant of a radar map set (RMS No. 118), consisting of eight separate items, for a total price of $79,363.

The invitation for bids on the contract had instructed bidders to submit separate bids on the eight separate items that were to comprise the radar map set, but bidders had been informed that they must bid on an “all or none” basis and that the contract would be awarded to the responsible bidder whose bids on all eight items combined to make the lowest total. It was on this basis that the total of $79,363 quoted by the plaintiff on all eight items of the radar map set obtained the contract for the plaintiff.

The eight items of the radar map set, and the prices which the plaintiff was to receive under the contract for the prep *1159 aration and delivery of the several items, were as follows:

a. Basic Compilation------- $30,399
b. Master Model----------- 16,881
c. Negative Master Mold --- 2,400
d. Relief Model------------ 5,114
e. Planar Map------------- 14,875
/. Cross Country Slide Compilation ----------------- 3,687
g. Target Approach and Extended Target Approach Compilation------------- 1,400
h. Projection Slide Set----- 4,107
Total _______________ $79,363

The end products sought by the defendant under the contract were the projection slide set, the relief model, and the planar map, which were to be used in the F-105D Simulator-Trainer System. The other five items of the radar map set were needed to produce the projection slide set, the relief model, and the planar map.

The purpose of the simulator mentioned in the preceding' paragraph was to familiarize a pilot with the instrumentation of the F-105D aircraft, to develop his ability to identify terrain rapidly by viewing a radar scope, and to familiarize him with a target mission. The simulator used the projection slide set, the relief model, and the planar map to produce a radar image. The relief model and the planar map were held in an upright position, facing each other, by a metal frame or gantry, with a scanning device moving in the space between them. As the pilot took the aircraft on its simulated mission, its course was recorded on the slides. Projection of these paths on the appropriate map image enabled the instructor to monitor the mission in progress.

Under the original provisions of the contract, all eight items of the radar map set were to be delivered to the defendant within 150 days from the date of the award (May 22, 1964).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McCormick Construction Co. v. United States
35 Cont. Cas. Fed. 75,721 (Court of Claims, 1989)
Olson Plumbing & Heating Co. v. United States
602 F.2d 950 (Court of Claims, 1979)
Allied Paint Manufacturing Co. v. United States
470 F.2d 556 (Court of Claims, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
413 F.2d 1156, 188 Ct. Cl. 1092, 1969 U.S. Ct. Cl. LEXIS 56, Counsel Stack Legal Research, https://law.counselstack.com/opinion/panoramic-studios-inc-v-the-united-states-cc-1969.