Max M. Stoeckert, Doing Business as University Brick & Tile Co. v. The United States

391 F.2d 639, 183 Ct. Cl. 152, 1968 U.S. Ct. Cl. LEXIS 77
CourtUnited States Court of Claims
DecidedMarch 15, 1968
Docket31-63
StatusPublished
Cited by16 cases

This text of 391 F.2d 639 (Max M. Stoeckert, Doing Business as University Brick & Tile Co. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Max M. Stoeckert, Doing Business as University Brick & Tile Co. v. The United States, 391 F.2d 639, 183 Ct. Cl. 152, 1968 U.S. Ct. Cl. LEXIS 77 (cc 1968).

Opinion

ON PLAINTIFF’S MOTION AND DEFENDANT’S CROSS-MOTION FOR SUMMARY JUDGMENT

PER CURIAM:

This case was referred to Trial Commissioner Lloyd Fletcher with directions to make recommendation for conclusions of law on plaintiff’s motion and defendant’s cross-motion for summary judgment under Rule 54(b). The commissioner has done so in an opinion and report filed on July 21, 1967. Requests for review were filed by both parties and the case has been submitted to the court on oral argument of counsel and the briefs of the parties. Since the court agrees with the commissioner’s opinion and report, with minor modifications, it *641 hereby adopts the same, as hereinafter set forth, as the basis for its judgment in this case. Therefore, plaintiff’s motion for summary judgment is denied, defendant’s cross-motion for summary judgment is granted, plaintiff’s petition is dismissed and judgment is entered for defendant on its counterclaim in the sum of $5,764.54.

Commissioner Fletcher’s opinion as modified by the court is as follows:

The plaintiff asks the court to review three decisions of the Corps of Engineers Board of Contract Appeals (CEBCA), all of which relate to the same Government contract. Each decision was adverse to plaintiff’s contentions. The first decision was issued on November 30, 1961, and held that plaintiff’s contract was properly terminated for default. The second decision was issued on April 27, 1963, and held that, in the completion of the contract work following plaintiff’s default, the Government suffered excess costs amounting to $5,764.54, which excess costs were properly assessable against plaintiff. 1 The third decision was issued on August 19, 1965, and held that plaintiff’s motion for rehearing on the ground of newly discovered evidence should be denied as untimely and for the further reason that the proffered “new” evidence was irrelevant to the issue of plaintiff’s default. 2

Under the provisions of the contract in dispute, the plaintiff was required to install a quarry tile floor and ceramic tile wainscoting in the powerhouse for the McNary Dam located on the Columbia River between Oregon and Washington. This tile work was covered in but one section of lengthy specifications developed primarily for the installation of the powerhouse equipment. Plaintiff made a successful bid for the tile work which was scheduled to follow the installation of the generators and other powerhouse equipment. He was awarded the tile work under a contract dated November 17, 1952.

Plaintiff had anticipated installing about one-fourth of the tile each year over a four-year period. He made his first visit to McNary in June 1953, 3 at which time Government representatives advised him that it would not be feasible to lay the tile until the generator installation was substantially completed. It was mutually agreed that he should wait until such completion before commencing the quarry tile work. In the spring of 1956, plaintiff was advised that the generator installation would soon be completed. He was requested to submit samples and a progress schedule for the Government’s approval.

Thereupon, plaintiff hired a crew of experienced tile setters and placed them under the supervision of a foreman who had worked for him previously in Alaska. The quarry tile was to be placed on the floor of the main generator room of the powerhouse at elevation 287. The floor dimensions were 87 by 1,422 feet. The room was divided into an assembly bay, a station service bay, and the main expanse in which were placed 14 large generators. The floor was a concrete slab three feet thick designed to bear loads up to 1,000 pounds per square foot.

Plaintiff began work on the quarry tile floor by first laying a sample section on January 10, 1957. By this time, the concrete slab had been in place several years. Since the generators had been in operation, the powerhouse was *642 heated and there was a low controlled humidity therein. As a consequence, the slab was very dry. Also it had been exposed during installation of the equipment in the powerhouse, and in places there were oil, grease, and paint stains on it as well as general grime. The specifications required the floor to have a wood float finish and that it be left rough enough to form a base for various floor finishes (such as the tiling to be laid by the plaintiff). The evidence discloses that the floor was, in fact, fairly smooth, especially in the areas where plaintiff commenced his work. These several factors combined to make successful placement of the quarry tile floor a very difficult operation.

Proper laying of the type of tile floor specified by this contract requires that a cement mixture (to which the tile may adhere) be first placed over the concrete slab. This mixture is commonly known as the “setting bed.” The specifications here required that the setting bed be composed of “Class B mortar”, the ingredients of which were defined as one cubic foot of portland cement, one cubic foot of hydrated lime or lime putty, not more than six cubic feet of damp loose aggregate, and sufficient water for workability. Plaintiff, however, did not use the specified mortar for the setting bed but, instead, used a Class A mortar mix of one part cement to three parts aggregate but without lime or lime putty.

Before plaintiff commenced work the Government had removed all loose dirt from the slab with a vacuum cleaner. In addition, before placing the setting bed, plaintiff’s workmen swept the slab with a broom. They then wet the floor with a hose for 15 to 30 minutes, after which they sprinkled the floor with neat cement, placed the setting bed, and laid the tile thereon. In order to prevent exposure of the setting bed over a lunch hour or overnight, plaintiff’s workmen covered with mortar only those portions of the floor which could be laid with tile within one-half of a working day. Their procedure for filling the joints was to fill them with concrete mix which they wetted down using a hose with a fog nozzle.

Almost immediately following commencement of the quarry tile work, the Government inspector expressed his doubt that plaintiff’s procedures would obtain a bond between the mortar setting bed and the concrete floor slab. However, he was assured by plaintiff’s foreman that they would get plenty of bond. While bond between the concrete floor slab and the setting bed for tile is not specifically mentioned in the specifications, Government representatives and both plaintiff and his foreman thought that such a bond was a normal product of a workmanlike tile-laying process and was a requirement of this job.

Because of previous difficulties in securing a satisfactory quarry tile floor in the previously constructed Bonneville Dam Powerhouse, the Government employees at the site were aware of the special procedures and the care that would be necessary to obtain a satisfactory tile floor on this job. Plaintiff’s foreman was told of these prior difficulties and suggestions were made as to how they should be overcome. It was especially emphasized that the slab must be thoroughly clean and wet. The record shows that plaintiff’s foreman paid little, if any, attention to these suggestions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Westchester Fire Insurance v. United States
52 Fed. Cl. 567 (Federal Claims, 2002)
Becho, Inc. v. United States
47 Fed. Cl. 595 (Federal Claims, 2000)
Mega Construction Co. v. United States
39 Cont. Cas. Fed. 76,564 (Federal Claims, 1993)
Mega Construction Co. v. United States
37 Cont. Cas. Fed. 76,305 (Court of Claims, 1992)
Prairie Land Construction, Inc. v. Village of Modesto
571 N.E.2d 1210 (Appellate Court of Illinois, 1991)
Louisiana Pacific Corp. v. United States
35 Cont. Cas. Fed. 75,547 (Court of Claims, 1988)
Tester Corp. v. United States
1 Cl. Ct. 368 (Court of Claims, 1983)
Skip Kirchdorfer, Inc. v. United States
29 Cont. Cas. Fed. 82,028 (Court of Claims, 1981)
Olson Plumbing & Heating Co. v. United States
602 F.2d 950 (Court of Claims, 1979)
Alfred A. Altimont, Inc. v. United States
579 F.2d 622 (Court of Claims, 1978)
Everett Plywood Corp. v. United States
512 F.2d 1082 (Court of Claims, 1975)
Astro-Space Laboratories, Inc. v. United States
470 F.2d 1003 (Court of Claims, 1972)
United States v. Rich Company
437 F.2d 549 (Ninth Circuit, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
391 F.2d 639, 183 Ct. Cl. 152, 1968 U.S. Ct. Cl. LEXIS 77, Counsel Stack Legal Research, https://law.counselstack.com/opinion/max-m-stoeckert-doing-business-as-university-brick-tile-co-v-the-cc-1968.