Phillips Construction Co. v. United States

179 Ct. Cl. 883, 1967 U.S. Ct. Cl. LEXIS 217, 1967 WL 8865
United States Court of Claims·Decided April 14, 1967·No. No. 335-63·Published·Cited by 2 cases

Opinion

Per Curiam:

This case was referred to Trial Commissioner Lloyd Fletcher with directions to make findings of fact and recommendation for conclusions of law. The commissioner has done so in a report and opinion filed on November 18, 1966, in which the facts are stated in the opinion. Plaintiff has filed no exceptions to or brief on this report and the time for so filing pursuant to the Pules of the court has expired. On February 27,1967, defendant filed a motion that the court adopt the commissioner’s opinion and dismiss the petition, to which motion the plaintiff has filed no opposition or response. Since the court agrees with the trial commissioner’s findings, opinion and recommended conclusion of law, as hereinafter set forth, it hereby adopts the same as the basis for its judgment in this case without oral argument. Defendant’s motion to adopt is granted, and since plaintiff is not entitled to recover, its petition is dismissed.

[885] OPINION OP COMMISSIONER*

Fletcher, Commissioner:

In this action review is sought through an assignment of errors of a decision by the Armed Services Board of Contract Appeals (ASBCA No. 6288) denying plaintiff’s claim for increased costs of interior painting performed under a Capehart Housing Contract.

The contract, dated October 2, 1957, called for plaintiff to construct 800 family units in a Capehart project adjacent to Myrtle Beach Air Force Base, Myrtle Beach, South Carolina. The specifications attached to the Invitation for Bid had included certain alternatives. Of importance here was Alternate No. 22, reading in pertinent part:

Furnish and install on walls of all units plaster in lieu of gypsum wallboard as shown on drawings and specified under Section 14 hereinbefore.
* ❖ * % *
d. * * * The finish must be allowed to draw a few minutes and then shall be troweled with water to a smooth finish, free from cat faces and other blemishes.
e. Plaster shall be painted as specified for wallboard.

Plaintiff’s bid, including its quotation on Alternate No. 22, was accepted, and hence the contract, as awarded, provided for plaster walls to be installed throughout the project instead of gypsum wallboard. The specifications with respect to plastering provided, among other things, that:

Samples may be taken by the Contracting Officer at any time from plaster work in place. Areas represented by samples which show over-sanding will be rejected. Sec. 13-18.

It will be noted that Alternate No. 22(e), supra, required that, in painting plastered surfaces, the contractor should follow the painting directions contained in the main body of the specifications relating to wallboard. Insofar as pertinent here, those specifications provided as follows:

Sec. 15-02 (c). If for any reason the painting contractor considers it impossible or impractical to get a first-class job with the materials and methods specified [886] and tinder the conditions involved he shall notify the Contracting Officer through the general contractor, in writing, prior to commencing, that portion of the work and he shall state the conditions he considers unsatisfactory and his recommendation for rectifying them.
* * • * * *
Sec. 15-03 (f). Sand surfaces (except sand finished plastered ceilings) smooth before priming and sand between all coats to produce an even smooth finish.
* íj: # ij:
Sec. 15-07. Wallboard: All wallboard shall be given one coat of high grade resin emulsion sealer, designed specifically for application over gypsum wallboard, equal to Sheetrock Sealer as manufactured 'by the U.S. Gypsum Company.1 Wallboard shall then be given one coat of “Texolite Primer” tinted to approximate finish color and one finish coat of latex base emulsion paint equal to “Texolite Duraval” as manufactured by the U.S. Gypsum Company.

Plaintiff entered into a subcontract with S. M. Batts for all painting work, both interior and exterior, for a lump sum of $230,700. He commenced painting in the spring of 1958 and within a relatively short period began to experience difficulties. Initially, the problem centered on the painting of wood surfaces, particularly those fashioned from southern pine. When the specified water base paint was applied to those surfaces, an unsightly “fuzzing” or raising occurred in the grain of the wood. The difficulty was overcome by substituting a more expensive oil base paint. Although this added expense was a part of plaintiff’s original claim, it now appears to have been abandoned. On pages 5-6 of its Assignment of Errors, plaintiff states:

Since there is a conflict of testimony concerning whether the original specifications were in accord with “good practice” and, bearing in mind that this appeal is based upon the record below, plaintiff will not press here its claim on account of the improper specifications of the type and kind of paint but will content itself with pressing its claim for loss sustained as a result of the sanding required of it. .

[887] The starting point for the facts underlying the claim for losses sustained through alleged excessive sanding requirements is plaintiff’s letter to the contracting officer dated November 17, 1958. In that letter plaintiff referred to earlier discussions and correspondence concerning painting procedures and materials and, in accordance with Section 15-02 (c) of the Specifications, supra, notified the Government of plaintiff’s view that it was impossible or impractical to obtain a first-class painting job with the materials and methods specified under the conditions involved. The letter first recommended that all woodwork be primed with an oil base primer-sealer, suggested that to obtain, proper protection a third coat of paint should be applied to the exterior surfaces, and, as a final recommendation, stated:

Under the conditions involved, the materials specified and particularly the use of certain darker shades of paint, as per the color schedule furnished us, we do not believe we will be able to obtain a first-class painting job on interior plastered wall surfaces. If it were possible for plastered surfaces to thoroughly cure-out during one complete heating, season, it is possible that two coats of paint would give adequate coverage. Due to the construction schedule involved, this is not possible and there has been evidence of lime spots burning through painted surfaces. To improve this situation, we have recommended that a third coat of paint be installed on interior plastered wall surfaces. At least one living unit has had this third coat application for inspection by your personnel.

The contracting officer responded by a letter dated November 19, 1958, in which he complained that the painting job on the interior plastered walls was not satisfactory and requested plaintiff to enlist the aid of representatives of the paint manufacturer and of the U.S. Gypsum Company.

Free access — add to your briefcase to read the full text and ask questions with AI

Phillips Construction Co. v. United States, 179 Ct. Cl. 883, 1967 U.S. Ct. Cl. LEXIS 217, 1967 WL 8865 (cc 1967).

179 Ct. Cl. 883 (Phillips Construction Co. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related