Everett Plywood Corp. v. United States

512 F.2d 1082, 20 Cont. Cas. Fed. 83,191, 206 Ct. Cl. 244, 17 U.C.C. Rep. Serv. (West) 111, 1975 U.S. Ct. Cl. LEXIS 243
CourtUnited States Court of Claims
DecidedFebruary 19, 1975
DocketNo. 743-71
StatusPublished
Cited by46 cases

This text of 512 F.2d 1082 (Everett Plywood Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Everett Plywood Corp. v. United States, 512 F.2d 1082, 20 Cont. Cas. Fed. 83,191, 206 Ct. Cl. 244, 17 U.C.C. Rep. Serv. (West) 111, 1975 U.S. Ct. Cl. LEXIS 243 (cc 1975).

Opinion

Per Curiam:

This case comes before the court on plaintiff’s and defendant’s exceptions, filed October 1, 1974, and October 30, 1974, respectively, to the recommended decision of Trial Judge Hal D. Cooper, filed July 12, 1974, pursuant to Rule 134 (h). The court has considered the case on the briefs and oral argument of counsel. Since the court agrees with the recommended decision of the trial judge, with minor modifications by the court, it hereby adopts the same, as modified, as the basis for its judgment in this case as hereinafter set forth. Therefore, it is concluded that plaintiff is entitled to recover in accordance with the opinion and judgment is entered for plaintiff in the sum of $34,570.83.

Trial Judge Cooper’s opinion, with minor modifications by the court, is as follows:

This action asserts a breach by the Forest Service of a contract for the sale of timber on Tonga Ridge. It is a sequel to the court’s earlier decision in Everett Plywood & Door Corp. v. United States, 190 Ct. Cl. 80, 419 F. 2d 425 (1969), hereinafter referred to as Tonga I. In Tonga I, the court found a breach of warranty of quantity for which plaintiff was awarded damages. The present case asserts an additional breach of the same contract based on defendant’s refusal to grant an extension thereof which would have allowed plaintiff to cut the remaining timber on Tonga Ridge. In addition, plaintiff seeks recovery of certain road repair and maintenance costs it incurred in the performance of the contract.

In defense, it is contended that plaintiff has so split its cause of action that, by reason of the court’s judgment in Tonga I, plaintiff is barred from any further relief. Also defendant denies there was any breach of the contract and denies that plaintiff is entitled to any recovery whatsoever.

The facts regarding the contract were fully stated in Tonga I and will be restated here only to the extent necessary to an understanding of the parties’ contentions. The original term of the contract, executed in 1955, extended to December 31, 1960. When plaintiff commenced logging, excessive defects in the timber were discovered, resulting in a substantial underrun. It was this underrun that was the basis for the [250]*250Tonga I case. During the pendency of that suit, filed in 1964, plaintiff was granted successive extensions of the contract and logging continued through the 1967 season. By that time, the only remaining timber was on Unit 15 of Tonga Ridge.

In requesting an extension of the contract for the 1968 season, plaintiff assigned as the reason therefor the difficulties presented by the short logging season at the high elevation at which Unit 15 was located and closed its request with the statement that “we should have no trouble completing the sale this coming season.”

The Forest Service’s policy governing extensions, both when the contract was entered in 1955 and when plaintiff’s request for 1968 was made, was a very liberal one. The Forest Service Handbook stated it in the following terms:

2433.12 — Procedure. Ordinarily, the timber sale contract is written on the basis that time is not of the essence. The termination date is fixed when the sample contract is drafted and thus becomes a condition of sale, * * * an extension of time may be granted by the officer approving the sale, his successor, or his superior, unless disadvantageous to the United States.

Extensions were regularly granted for a variety of reasons ranging from bad weather to poor economic conditions. Forest Service personnel testifying at trial could recall no specific instance where, prior to 1969, an extension had been denied and plaintiff had never been denied an extension on any of its other Forest Service contracts. The fact is that extensions of contracts were granted by the Forest Service with very little urging.

On April 8, 1968, the Forest Service granted plaintiff’s request for an extension, but warned plaintiff that “only under extraordinary conditions will this sale be considered for another extension.”

Plaintiff attempted but failed to complete logging on Unit 15 in the 1968 season. Although a number of excuses were given, it is doubtful, in view of the normally adverse conditions prevailing at high elevations, that any of the difficulties encountered by plaintiff were truly “extraordinary.”

In November 1968, prior to any request by plaintiff, the Forest Service decided to grant no further extensions of the [251]*251contract. This decision was communicated to plaintiff on December 20,1968. By letter of January 24,1969, plaintiff formally requested an extension of the contract for the 1969 season. There then followed a series of events, summarized in finding 19, the net result of which was the grant of a one-month extension of the contract from March 81,1969 to April 30,1969, followed by a final refusal, on April 22,1969, of any further extension. Meanwhile, on March 20, 1969, the trial judge’s decision in Tonga I was handed down.

When its request for reconsideration of the Forest Service’s decision was denied, plaintiff appealed to the Board of Forest Appeals which, ultimately, dismissed the appeal on the ground it had lost jurisdiction by reason of the subsequent resale of the timber on November 30,1969, by the Forest Service. The Board’s dismissal occurred on February 2,1971, some 14 months after the court’s per curiam affirmance of the trial judge’s decision in Tonga I.

I. The Split Cause of Action Defense

On the foregoing facts, defendant contends that plaintiff has split its cause of action and is barred from any further relief.

In Nager Electric Co. v. United States, 177 Ct. Cl. 234, 368 F. 2d 847 (1966), the court, in considering the issue of statute of limitations, stated the controlling principle governing the rule against split causes of action:

For reasons of judicial economy, convenience, and fairness to litigants, it is important to retain the principle that one non-divisible contract normally gives rise to only one claim, not to a succession of individual-item claims with all the burdens they would bring and problems they would entail. Supra at 254, 368 F. 2d at 861.

See, also, eestatemeNt, judgmeNts § 62 (1942).

Nonetheless, a separate action founded on a single non-divisible contract may be maintained if the later claim is severable from the earlier one, and, if at the time of commencement of the earlier suit, the later claim was not then capable of being asserted. United States v. Pan-American Petroleum Co., 55 F. 2d 753, 777 (9th Cir. 1932), cert. denied, 287 U.S. 612; Fellows v. National Can Co., 13 F. 2d 210, 211 [252]*252(E.D. Mich. 1926); eestatemeNT, judgments § 62, example (h.) (1942).1 However, if the claimant, before filing its first suit, is in possession of all the facts on which its second suit is based, the splitting of the claims into multiple suits is fatal to maintenance of the later-filed action. Container Transport International, Inc. v. United States, 199 Ct. Cl. 718, 468 F. 2d 926 (1972).

In this case, essentially three claims are presented, the principal one being based on the Forest Service’s refusal to grant an extension.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sikorsky Aircraft Corporation v. United States
122 Fed. Cl. 711 (Federal Claims, 2015)
PCL Construction Services, Inc. v. United States
84 Fed. Cl. 408 (Federal Claims, 2008)
Yankee Atomic Electric Co. v. United States
73 Fed. Cl. 249 (Federal Claims, 2006)
Precision Pine & Timber, Inc. v. United States
72 Fed. Cl. 460 (Federal Claims, 2006)
Cuyahoga Metropolitan Housing Authority v. United States
65 Fed. Cl. 534 (Federal Claims, 2005)
Young v. United States
60 Fed. Cl. 418 (Federal Claims, 2004)
Hansen Bancorp, Inc. v. United States
53 Fed. Cl. 92 (Federal Claims, 2002)
Trustmark Insurance v. ESLU, Inc.
153 F. Supp. 2d 1322 (M.D. Florida, 2001)
Alaska Pulp Corp. v. United States
48 Fed. Cl. 655 (Federal Claims, 2001)
Florida Power & Light Co. v. United States
42 Cont. Cas. Fed. 77,364 (Federal Claims, 1998)
Reservation Ranch v. United States
42 Cont. Cas. Fed. 77,286 (Federal Claims, 1997)
KMS Fusion, Inc. v. United States
41 Cont. Cas. Fed. 77,000 (Federal Claims, 1996)
Engle Investors v. United States
35 Cont. Cas. Fed. 75,757 (Court of Claims, 1989)
Louisiana Pacific Corp. v. United States
35 Cont. Cas. Fed. 75,547 (Court of Claims, 1988)
Darwin Construction Co., Inc. v. United States
811 F.2d 593 (Federal Circuit, 1987)
In Re Cohoes Industrial Terminal, Inc.
69 B.R. 717 (S.D. New York, 1987)
Squirrel Creek Associates v. United States
11 Cl. Ct. 212 (Court of Claims, 1986)
Carnation Co. v. Olivet Egg Ranch
189 Cal. App. 3d 809 (California Court of Appeal, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
512 F.2d 1082, 20 Cont. Cas. Fed. 83,191, 206 Ct. Cl. 244, 17 U.C.C. Rep. Serv. (West) 111, 1975 U.S. Ct. Cl. LEXIS 243, Counsel Stack Legal Research, https://law.counselstack.com/opinion/everett-plywood-corp-v-united-states-cc-1975.